Case Law[2022] ZASCA 127South Africa
Zurich Insurance Company South Africa Ltd v Gauteng Provincial Government (734/2021) [2022] ZASCA 127; [2023] 1 All SA 368 (SCA); 2023 (1) SA 447 (SCA) (28 September 2022)
Supreme Court of Appeal of South Africa
28 September 2022
Headnotes
Summary: Insurance contract – damage to rock mass when tunnels for Gautrain Rapid Rail System constructed – whether insured’s claim had prescribed – whether rock mass surrounding tunnel void part of property insured – whether order declaring insured’s right to indemnification, and to be paid such amounts as are later proved, an effective order.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Supreme Court of Appeal
South Africa: Supreme Court of Appeal
You are here:
SAFLII
>>
Databases
>>
South Africa: Supreme Court of Appeal
>>
2022
>>
[2022] ZASCA 127
|
Noteup
|
LawCite
sino index
## Zurich Insurance Company South Africa Ltd v Gauteng Provincial Government (734/2021) [2022] ZASCA 127; [2023] 1 All SA 368 (SCA); 2023 (1) SA 447 (SCA) (28 September 2022)
Zurich Insurance Company South Africa Ltd v Gauteng Provincial Government (734/2021) [2022] ZASCA 127; [2023] 1 All SA 368 (SCA); 2023 (1) SA 447 (SCA) (28 September 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZASCA/Data/2022_127.html
sino date 28 September 2022
THE
SUPREME COURT OF APPEAL OF SOUTH AFRICA
JUDGMENT
Reportable
Case no. 734/2021
In the matter between:
ZURICH INSURANCE
COMPANY SOUTH AFRICA LTD
Appellant
and
GAUTENG PROVINCIAL
GOVERNMENT
Respondent
Neutral
citation:
Zurich
Insurance Company South Africa Ltd v Gauteng Provincial Government
(Case no. 734/2021)
[2022] ZASCA 127
(28 September
2022)
Coram:
Ponnan and Plasket JJA and Basson, Weiner and
Siwendu AJJA
Heard:
16 August 2022
Delivered:
28 September 2022
Summary:
Insurance contract – damage to rock mass
when tunnels for Gautrain Rapid Rail System constructed –
whether insured’s
claim had prescribed – whether rock
mass surrounding tunnel void part of property insured – whether
order declaring
insured’s right to indemnification, and to be
paid such amounts as are later proved, an effective order.
ORDER
On
appeal from:
Gauteng Local Division of
the High Court, Johannesburg (Wepener J sitting as court of first
instance).
The appeal is dismissed
with costs including the costs of two counsel.
JUDGMENT
Plasket JA (Ponnan JA
and Basson, Weiner and Siwendu AJJA concurring)
[1]
This appeal, against an order made by Wepener J in the Gauteng Local
Division of the
High Court, Johannesburg (the high court), concerns a
claim for the enforcement of a contract of insurance (the policy)
concluded
by the appellant, the Zurich Insurance Company South Africa
Ltd (Zurich) with, inter alia, the respondent, the Gauteng Provincial
Government (the province). After the province had discovered what it
believed to be damage to parts of the tunnel system in which
the
Gautrain Rapid Rail System operates, and Zurich had repudiated a
claim made in terms of the policy, the province issued summons
in
which it claimed declaratory relief to the effect that Zurich was
obliged to indemnify it in respect of the repair, replacement
or
making good of the damage to the tunnels, and that it was required to
pay the province the amount that it proved in due course
in respect
of its loss. It also sought costs of suit.
[2]
After a lengthy trial, Wepener J issued an order essentially in the
terms sought by
the province. His order reads as follows:
‘
1
Subject to all the terms and conditions of the policy, it is declared
that the
defendant is obliged to indemnify the plaintiff for the cost
of replacing and/or repairing and/or making good all damage (as
defined
in [paragraph 15] of the particulars of claim) to the tunnels
from Rosebank Station to Marlboro Portal as described in [paragraph
11] of the plaintiff’s particulars of claim.
[1]
2
It is declared that the defendant, on the basis of prayer 1 above, is
required
to pay to the plaintiff such amount as is proved by the
plaintiff as constituting the cost of replacing and/or repairing
and/or
making good all damage to the tunnels as described in
paragraph 15 of the particulars of claim, subject to the limit of
indemnity
and deductibles as set out in the policy.
3
The defendant is to pay the plaintiff’s costs of suit,
including the
costs occasioned by the employment of two counsel.’
[3]
On the application of Zurich, he granted leave to appeal directly to
this court. In
his judgment, he said that while a large number of
grounds had been raised in the notice of appeal, they were ‘reduced
to
three during argument’ and that he was of the view that
there were only prospects of success on appeal ‘on these three
issues’. His order reads as follows:
‘
I
consequently grant leave to appeal to the Supreme Court of Appeal on
the following issues:
1
Whether the order issued by this court is capable of practical
enforcement;
2
Whether the respondent’s claim has become prescribed;
3
Whether the rock surrounding the void formed part of the property
insured.’
[4]
It appeared, on the face of it, that Wepener J may have sought to
grant leave to appeal
against three of his reasons for upholding the
province’s claim. It is a foundational procedural principle
that an appeal
lies against a substantive order of a court rather
than against the reasons for its judgment.
[2]
If it had been Wepener J’s intention to grant leave to appeal
against his reasons, his order may have been incompetent. The
result
would then have been that we would have had no jurisdiction to
entertain the appeal.
[3]
[5]
Both Mr Loxton, for Zurich, and Mr Subel, for the province, submitted
that this had
not been Wepener J’s intention and that, even if
he had not expressed himself as clearly as he might have, he had
intended
to grant leave to appeal against his order but to limit the
grounds of appeal. Court orders, like other written instruments, must
be interpreted in a unitary, holistic process having regard to the
words used, the contextual setting and the apparent intended
purpose.
[4]
This order is to be
interpreted within the context of it being trite law that ‘leave
to appeal may be limited so as to allow
only particular grounds of
appeal to be advanced’
[5]
and of the clear indication in paragraphs 1 and 2 of the judgment
that Wepener J had applied his mind to the grounds of appeal
that
had, in his view, reasonable prospects of success.
[6]
It is clear in these circumstances that Wepener J intended to grant
leave to appeal
against the entire order that he had made but that he
considered only three of the various grounds advanced by Zurich to
have any
prospects of success. Understood thus, the order granting
leave to appeal is not irregular, with the result that we have
jurisdiction
to consider and determine this appeal.
The background
[7]
The Gautrain is a joint venture between the province and a private
entity. In terms
of a concession agreement, the province granted to
Bombela Concession Company (Pty) Ltd (Bombela) a concession to
design, construct,
partially finance, operate, maintain and generate
income from the Gautrain for the duration of the concession.
[8]
The Gautrain runs from Park Station in the central business district
of Johannesburg,
past a number of stations including Rosebank and the
Marlboro Portal, to the Oliver Tambo International Airport, on one
line, and
to Hatfield in Pretoria, on another. Parts of the rail
network are below ground in tunnels, while others are above ground.
This
matter concerns the construction of tunnels between the stations
of Rosebank and Sandton, on the one hand, and Sandton and the
Marlboro Portal, on the other.
[9]
The construction that was envisaged was defined in the concession
agreement as ‘the
works’, a term that meant all work that
was to be undertaken to achieve the objects of the agreement,
including the construction
of tunnels. In terms of a schedule to the
concession agreement, tunnels were to be constructed so that they
would comply with specified
permissible water-flow limits and were to
be sufficiently water-tight to ensure that the long term ambient
hydrological conditions
around any of the tunnels would not be
disturbed.
[10]
The parties who were insured in terms of the policy included the
province; Bombela (described
as the principal); Bombela TKC (Pty) Ltd
(described as the contractor) and ‘all contractors and
sub-contractors of any tier
in connection with THE PROJECT’;
the ‘Material Contractor and Sub contractors of the Material
Contractor’; ‘Lenders
Agent, the Lenders and Security
Company’; and consultants, designers, suppliers and advisers
‘of any tier’, as
well as the ‘Independent
Certifier and others providing goods or services in connection with
THE PROJECT’. These broad
categories of bodies were defined as
‘the insured’. Various aspects of the project were
performed by different Bombela-related
entities such as Bombela TKC
(Pty) Ltd, mentioned above, and Bombela Civils Joint Venture (Pty)
Ltd. For the sake of convenience,
I shall, in what follows, refer to
all of the Bombela entities simply as Bombela, without distinguishing
between them.
[11]
The purpose of the policy was to indemnify the insured against any
damage contemplated by it,
and to pay to or indemnify the insured for
the full cost of the replacement, repair or making good of the
damage. In broad terms,
it covered ‘the project’ which
was defined to mean the ‘financing, pre-fabrication, design,
engineering, procurement,
construction, erection, hot testing,
commissioning, operation and maintenance’ of the Gautrain, ‘all
associated and
ancillary works in connection therewith’ and
‘any Contract or Agreement written or implied entered into by
the INSURED
in connection therewith’.
[6]
[12]
The ingress of water, when tunnels are constructed below the water
table, is always a serious
engineering concern. The reason is
obvious: the excavation process, especially the drill and blast
method used in the construction
of the tunnels in question, disturbs
the rock mass around the void that is created and renders that rock
more permeable. As was
explained by Dr Nick Barton, an engineer with
significant expertise in rock mechanics and whose evidence was
accepted by the high
court, damage is caused by an ‘increase
and extension of the excavation disturbed zone’ with the result
that ‘joint
deformation is increased, blast gasses penetrate
deeper, over-break may occur, and
inflow is enhanced
due to a
general increase in joint apertures, in addition to less well
controlled blast-induced fracturing’. Professor Steinar
Roald,
an eminent civil engineering expert in the field of grouting, whose
evidence was also accepted by the high court, explained
that a
‘tunnel below the ground water table will serve as a
large
drainage pipe
that lowers the ground water level’.
[13]
It is no longer in dispute in this appeal, in the light of the
limited leave to appeal that was
granted by the high court, that what
was described by Dr Barton and professor Roald is precisely what
occurred in the tunnels in
issue in this matter. Dr Barton explained
the problem thus:
‘
A
tunnel releasing about 250 Olympic swimming pools of water per year
(>600 000 000 litres/year) from 20 litres/second
out-of-the-tunnels flow over approximately 10 km, therefore drawing
down the water table, is obviously an undesirable and environmentally
damaging construction. Of particular concern to Gautrain/Province is
that the
internal
environment of their rail tunnel, being much wetter and more humid
than intended, has prejudiced the life-time and need for maintenance.
Unfortunately, the tunnel cannot be “fixed” without great
expense and long-term alternative service measures. All this
is
because the desirable high-pressure
pre-injection
was not performed, even though it was designed. It now can no longer
be performed. The “pre” (ahead of the tunnel face)
is
lost forever.’
[14]
When the excavation of a tunnel is planned and designed, mitigation
measures are required to
prevent the sorts of mishaps described by Dr
Barton. He referred to the usual method as high pressure
pre-injection, or pre-grouting.
This method involves the high
pressure spraying of grout as the tunnel is excavated, with the
purpose of sealing fissures in the
surrounding rock mass created by
the stresses placed on it by the excavation process, particularly the
drilling and blasting. Pre-grouting
was planned for the construction
of the tunnels in question but, in the words of Dr Barton, was
‘inexplicably dropped by
the contractor’.
[15]
If a tunnel has been constructed without pre-grouting having been
done, an immense remedial problem
is created. Post-grouting is a poor
alternative for pre-grouting because it is far less effective, is
more difficult to apply and
is both more time-consuming and costly.
Lining the affected tunnels with cast concrete and membranes would,
on the face of it,
appear to be a more effective method of repair but
practical problems stand in the way of its application. Dr Barton
explained
that ‘as the tunnel is “live”, such major
remedial work would lead to a massive disruption of passenger
services’.
In these circumstances, he said, the only feasible
remedy may be the construction of new tunnels. But this is a debate
for another
day.
[16]
A number of material facts are common cause. They are, first, that
the tunnels did not meet the
specifications that had been set as to
the maximum permissible levels of water ingress. The second is that
the construction of
the tunnels is covered by the policy, although
what is meant by the term ‘tunnel’ remains in dispute.
The third is
that no pre-grouting work was performed in the
construction of the tunnels in question. Fourthly, it was accepted by
all that the
damage in respect of which the province sought to be
indemnified occurred as a result of the construction of the tunnels.
[17]
It is also not in dispute that payment of the premiums stipulated in
the policy were up-to-date.
It can also be accepted as settled that
proper notice of the claim was given to Zurich by the province.
The issues
[18]
I now turn to a consideration of the three issues that require
determination in this appeal.
The first is whether the province’s
claim against Zurich had prescribed. The second is whether the rock
mass that surrounds
the void of the tunnels is part of the property
insured. The third is the propriety and effectiveness of the high
court’s
order.
Prescription
[19]
In terms of
s 11
(d)
of the
Prescription Act 68 of 1969
, the
prescription period in respect of the debt in this case is three
years.
Section 12(1)
provides that, as a general rule, ‘prescription
shall commence to run as soon as the debt is due’.
Section
12(3)
states that the debt ‘shall not be deemed to be due until
the creditor has knowledge of the identity of the debtor and of
the
facts from which the debt arises’ but includes a proviso that
‘a creditor shall be deemed to have such knowledge
if he could
have acquired it by exercising reasonable care’. Prescription
may be interrupted in various ways including, in
terms of
s 15(1)
,
‘by the service on the debtor of any process whereby the
creditor claims payment of the debt’.
[20]
The onus of establishing that a claim has prescribed rests on the
party raising prescription
– in this case, Zurich. In order to
discharge that onus, the onus-bearing party is required to prove the
date when prescription
began to run and that the other party had the
requisite knowledge of the material facts from which the debt arose
at that time.
[7]
[21]
The nature of the knowledge that a party is required to have in order
for prescription to start
running was set out thus by this court in
Truter
and Another v Deysel
:
[8]
‘
For
the purposes of the Act, the term “debt due” means a
debt, including a delictual debt, which is owing and payable.
A debt
is due in this sense when the creditor acquires a complete cause of
action for the recovery of the debt, that is, when the
entire set of
facts which the creditor must prove in order to succeed with his or
her claim against the debtor is in place or,
in other words, when
everything has happened which would entitle the creditor to institute
action and to pursue his or her claim.’
The
position was summarized by Cameron and Brand JJA in
Minister
of Finance and Others v Gore NO
[9]
when they stated that, for purposes of prescription, ‘time
begins to run against the creditor when it has the minimum facts
that
are necessary to institute action’.
[22]
Gore
also dealt with what was meant by knowledge, on the part of a
creditor, of the facts constituting their cause of action. Cameron
and Brand JJA held in this respect:
[10]
‘
[18]
Rabie certainly did cry fraud soon after 3D-ID lost the tender. But
what did he know when he did so? The defendants' argument
seems to us
to mistake the nature of “knowledge” that is required to
trigger the running of prescriptive time. Mere
opinion or supposition
is not enough: there must be justified, true belief. Belief, on its
own, is insufficient. Belief that happens
to be true (as Rabie had)
is also insufficient. For there to be knowledge, the belief must be
justified.
[19] It is well
established in our law that:
(a)
Knowledge is not confined to the mental state of awareness of facts
that is produced by
personally witnessing or participating in events,
or by being the direct recipient of first-hand evidence about them.
(b)
It extends to a conviction or belief that is engendered by or
inferred from attendant circumstances.
(c)
On the other hand, mere suspicion not amounting to conviction or
belief justifiably
inferred from attendant circumstances does not
amount to knowledge.
It follows that belief
that is without apparent warrant is not knowledge; nor is assertion
and unjustified suspicion, however passionately
harboured; still
less, is vehemently controverted allegation or subjective
conviction.’
[23]
Zurich pleaded that the province’s claim against it had
prescribed. Construction of one
of the tunnels was completed by 4
January 2009, and of the second tunnel by 2 July 2009. If there had
been damage caused to them,
no further damage could have been caused
by the contractors after these dates. The province was, at all times,
aware of the identity
of the defendant. It was also aware of the
facts giving rise to the debt from these dates on, or it ought
reasonably to have had
this knowledge from these dates on. As a
result, Zurich alleged, prescription began to run on 4 January 2009,
in the case of the
first tunnel, and on 2 July 2009 in the case of
the second tunnel. The claims prescribed three years later, not
having been interrupted
by the service of summons, which only
occurred on 26 February 2015.
[24]
The province replicated to the plea of prescription. It simply denied
that the claim had prescribed.
[25]
Zurich led no evidence in order to establish its defence of
prescription. Instead, it relied
on an inference that, if damage had
been caused, it was the result of the drilling and blasting method of
excavation. It also argued
that the province must have been aware of
the damage that it alleged because it had a support team in place to
monitor the construction
of the tunnels, and that this team, made up
of suitably qualified people, must have observed the damage at the
time of the construction.
[26]
The province’s answer to this was that matters were not that
simple. It led the evidence
of one witness on the prescription issue.
He was Mr David Marx. He was employed to render commercial and
dispute management to
the Gautrain Management Agency. He is a civil
engineer and holds, in addition to a master’s degree in civil
engineering,
a Master of Business Administration degree. He testified
about the process that unfolded from when the construction of the
tunnels
commenced until the service of summons on Zurich. Strong
credibility findings in his favour were made by Wepener J and, it
seems
to me, justifiably so.
[27]
As to the first point raised by Zurich, Mr Marx testified that the
support team did its work
principally by way of desk-top monitoring.
There was consequently no specialist on-site oversight by the support
team. It is so,
however, that the support team had been informed that
no pre-grouting had been done. It also understood that the water
ingress
tolerance specifications that had been agreed to were the
10x10 water inflow specification – a ‘local’
tolerance
not exceeding 10 litres of water per minute per any 10
metres of tunnel – and the 1x1 water inflow specification –
a seepage rate for the entire tunnel not exceeding one litre of water
per square metre per day.
[28]
The problem of excessive water ingress into the tunnels arose at an
early stage. The province
was aware of the problem, but not of its
cause, and had engaged with Bombela in relation thereto. It adopted a
cautious approach
and also notified Zurich on a number of occasions
that it believed that it may have had a claim in terms of the policy.
It was,
however, faced with a problem: while the excessive ingress of
water could have been caused by any number of factors, it was not
able to identify any damage. On each occasion, Zurich’s
assessors investigated and reported that they had found no sign of
damage.
[29]
The province had been assured by Bombela that the problem would be
remedied. Instead, however,
a dispute developed between the province
and Bombela about the applicable specifications and whether the
tunnels were compliant
with the specifications. The dispute was
referred for resolution in terms of the concession agreement. The
tribunal of first instance,
the Dispute Resolution Board (DRB), found
on 10 June 2011 that, for the most part, the tunnels were compliant
with the 10x10 specification,
which was the agreed specification. One
section of the tunnels was not compliant with this specification, and
it ordered Bombela
to perform remedial work on this section.
[30]
Once this finding was made, the province was bound by it. Clause 6.4
of Schedule 10 of the concession
agreement provided that ‘[u]nless
and until any decision issued by the DRB is overturned in Arbitration
in terms of clause
8 of Schedule 10, it shall be binding on the
parties’. The result was that if the water ingress was the
manifestation of
damage, the province had to accept that no damage
had occurred because, subject to the remedial work that had been
ordered by the
DRB, the tunnels had been found to be compliant with
the specifications.
[31]
The province referred the DRB’s decision to arbitration. An
arbitration award was made
on 23 November 2013. The arbitration panel
(retired judges Streicher and Combrinck JJA and Joffe J) found that
both the 10x10 and
1x1 specifications were contemplated by the
concession agreement and that:
‘
1.2
The sections of the tunnel Park to E2, Rosebank to Sandton and
Sandton to Marlboro fail to comply
with the Concession Specifications
in that the rate of water infiltration into these sections exceeds
the maximum infiltration
rate of 1 litre/m
2
/day.
1.3
The section of the tunnel Park to E2 fails to comply with the
Concession Specifications
in that the rate of water infiltration into
this section exceeds the maximum infiltration rate permitted at any
isolated section
of 10 metres namely 10 litres/min/10 metres.’
[32]
It was only after the arbitration award was handed down that the
province began, once again,
to investigate whether there was damage
to the tunnels, as contemplated by the policy. In March 2014, it
consulted with professor
Roald on the issue. He was not able to
provide an answer but suggested that the province consult with an
expert in rock mechanics,
such as Dr Barton. He was duly approached
and came to South Africa in April 2014. He attended joint meetings of
the province and
Bombela. In the words of Mr Marx, he ‘shared
his damages proposition . . . with Bombela’. The province made
Dr Barton
available to Bombela because it took the view that Bombela,
as one of the insured in terms of the policy and the concessionaire,
should initiate the claim if damage could be identified. As it
happened, Bombela was reluctant to make a claim, so the province
did
so itself.
[33]
It was only after Dr Barton had explained the concept of excavation
disturbance zones (EDZs)
that the province realized that
indemnifiable damage may have been caused to the tunnels. He
explained the effects of tunneling,
especially by means of drilling
and blasting, in terms of four EDZs. The first, EDZ1, involves the
disturbance due to the stress
redistribution in the rock mass as a
result of the excavation of the void. The second, EDZ2, is the
disturbance arising from the
deformation of rock joints following the
stress redistribution in the rock mass. The third, EDZ3, is the
cracking, loosening and
enhanced permeability in the rock mass as a
result of the penetration of blast gases and shock-loading. The
fourth, EDZ4, is the
unnecessary
deeper damage in the form of
deepened joint deformation caused by a failure to pre-grout when this
is required. He explained the
connection between the EDZs as follows:
‘
Within
and beyond the unavoidable disturbances caused by excavation . . . is
damage caused by defective design and/or omission of
pre-injection.
Deformation is inevitably increased, blast gasses are bound to
penetrate deeper, more over-break may occur and inflow
is unavoidably
enhanced, all due to a failure to pre-grout. We can collectively
refer to these unwanted and unplanned disturbances
as the damage
EDZ.’
[34]
In May 2014, Dr Barton investigated whether damage in the form of
EDZ4 was present in the tunnels.
He concluded and expressed the
opinion that the failure to pre-grout when blasting had caused EDZ4
damage to the rock mass surrounding
the void of the tunnel. And, as
Wepener J observed in his judgment, ‘EDZ4 is a specialist
matter and not, as far as the evidence
before me showed, physically
detectable during an inspection’.
[35]
By letter dated 5 February 2015, the province made a claim against
Zurich in terms of the policy.
On 25 February 2015, summons was
served on Zurich.
[36]
In order to have a complete cause of action, the province had to have
knowledge that damage to
the tunnels had occurred. It is clear from
the chronology of events that I have outlined that the province may
have suspected for
some time that damage to the tunnels had been
caused. It could, however, not quite identify the damage or its cause
and neither
could the assessors when they investigated on the
strength of the province’s concerns. It was only when Dr Barton
alerted
them to the possibility of EDZ4 damage, and then confirmed
this to be the case, that the requisite knowledge of damage could be
attributed to the province. That occurred in about May 2014.
[37]
It is necessary to stress the following two points. First, the
province acquired actual knowledge
of damage in 2014 but it was not
possible for it to have had knowledge attributed to it any earlier
because of the specialized
knowledge and expertise necessary to
establish that damage had occurred. Secondly, when Dr Barton deduced
that EDZ4 damage had
been caused, he established a fact, rather than
an inference of negligence or a conclusion of law. Only then could it
be said that
the province had a ‘complete cause of action’.
[38]
In the result, prescription began to run in May 2014 and was
interrupted by the service of summons
in February 2015, some nine
months later. Consequently, as far less than three years separated
these two events, the province’s
claim had not prescribed and
the court below was correct when it held that the plea of
prescription had to fail.
Is the rock mass
surrounding the tunnels part of the property insured?
[39]
Paragraph 15 of the province’s particulars of claim deal with
the damage to the property
insured. It pleaded that: (a) Bombela, its
contractors and sub-contractors ‘undertook the design and
construction of the
tunnels and provided the materials for purposes
of doing so’; (b) as a result of ‘defective design, plan,
specification,
material and/or workmanship’ they damaged the
property insured, ‘more particularly the tunnels’; and
(c) the
damage was caused by ‘failing to pre-grout’ in
order to meet the agreed specifications and consisted of ‘an
increased
and extended “excavation disturbed zone”’
that resulted in ‘more deeply penetrating joint adjustments and
generally increased joint deformation, and thus unnecessarily
increased permeability and resulting water inflow, due to an increase
in joint apertures’.
[40]
The damage was said to be ’in excess of what would normally
have been expected if good
industry practices’ had been adopted
in the design and construction of the tunnels; and was attributable
to ‘a combination
of defective design, plan, specification and
poor workmanship due, predominantly, to the absence of an adequately
planned and executed
pre-grouting strategy’.
[41]
Zurich’s plea to paragraph 15 anticipated its plea of
prescription and also denied that
‘there was any damage
occasioned to any Property Insured as alleged or at all’. It
also denied that whatever damage
may have been occasioned ‘amounts
to damage as envisaged in the policy and it denies that any damage
was occasioned to PROPERTY
INSURED’. In this way, the question
whether the rock mass surrounding the tunnels was property insured,
as defined in the
policy, was raised.
[42]
As a result of the limitation of the grounds of appeal by Wepener J,
two important issues are
no longer in dispute. They are that damage
occurred and that the damage was caused to the rock mass that
surrounds the tunnels.
The correctness or otherwise of Zurich
argument that the rock mass is not part of the property insured
depends, ultimately, on
an interpretation of the policy, and an
answer to the question ‘what is a tunnel?’.
[43]
In
Centriq
Insurance Company Ltd v Oosthuizen and Another
,
[11]
Cachalia JA made the point that while insurance contracts must be
interpreted like any other written instrument – having
regard
to language, context and purpose in a unitary exercise aimed at
achieving a commercially sensible result
[12]
-- their specific purpose activates other considerations too. He
stated in this regard:
[13]
‘
But
because insurance contracts have a risk-transferring purpose
containing particular provisions, regard must be had to how the
courts approach their interpretation specifically. Thus, any
provision that places a limitation upon an obligation to indemnify
is
usually restrictively interpreted, for it is the insurer's duty to
spell out clearly the specific risks it wishes to exclude.
In the
event of real ambiguity the doctrine of interpretation,
contra
proferentem
, applies and the policy is
also generally construed against the insurer who frames the policy
and inserts the exclusion. But, like
other aids to the interpretation
of contracts of this nature, the doctrine must not be applied
mechanically, for exclusion clauses,
like other contractual clauses,
must be construed in accordance with their language, context and
purpose with a view to achieving
a commercially sensible result.’
He
also sounded a word of caution – that ‘courts are not
entitled, simply because the policy appears to drive a hard
bargain,
to lean to a construction more favourable to an insured than the
language of the contract, properly construed, permits’.
[14]
[44]
I turn to the policy and its terms. In the preamble to the policy,
the insurers, in return for
the payment of premiums by the insured,
agreed to indemnify them ‘against all such DAMAGE or liability
as herein provided’.
The term ‘damage’ is defined
in the definition clause to mean ‘physical DAMAGE’,
including ‘physical
loss or physical destruction’.
[45]
In the summary that follows the preamble, the project that is the
subject of the policy is described
as the ‘financing,
pre-fabrication, design, engineering, procurement, construction,
erection, hot-testing, commissioning,
operation and maintenance of
the Gautrain Rapid Rail Link in the Republic of South Africa and all
associated and ancillary works
in connection therewith’. In the
definitions clause it is stated that the project ‘shall be as
stated in the Summary
and any Contract or Agreement, written or
implied, entered into by the INSURED in connection therewith’.
[46]
The term ‘PROPERTY INSURED’ has two components. It is
defined, in the first place,
to mean ‘the permanent and
TEMPORARY WORKS including Rolling Stock and materials contained
therein and other property used
or for use in connection with THE
PROJECT including site camps and installations of any kind and free
issue materials’, and
secondly, to mean tunnel boring
machinery. The term ‘TEMPORARY WORKS’ is defined as ‘all
things, including access
scaffolding erected or constructed for the
purpose of making possible the erection or installation of the
permanent works and which
it is intended shall not pass to the
ownership of the Principal’. Although ‘permanent works’
is not defined,
it appears to be all works other than temporary
works.
[47]
The term ‘TUNNEL WORKS’ is also defined. It means ‘works
intended to create
any sub ground surface, passage, cavern or tunnel,
including shafts, however constructed, including cut and cover and
station boxes
below ground’, but the definition shall not apply
‘to foundation works nor basement levels for above ground
surface
structures, or fitting out or other similar works’.
[48]
The definition of ‘CIVIL WORKS’ is also relevant. This
term is defined to mean ‘Tunnel
Works (but not their contents),
Station Box structures (but not their contents), Buildings (but not
their contents), Bridges, Embankments,
Cuttings, Foundations and
Roads’.
[49]
In
section 1
of the policy, under a heading ‘MATERIAL DAMAGE’,
what was termed an ‘Operative Clause’ reads as follows:
‘
Except
as hereinbefore excluded, the Insurers will pay to or indemnify the
INSURED under this Policy for the full cost of replacing
and/or
repairing and/or making good DAMAGE to the PROPERTY INSURED howsoever
caused occurring during the Period of Insurance.’
[50]
Four clauses refer specifically to the tunnel works. One of the
deductibles in
Section 1
relates to a deductible of R7 100 000
for ‘any one EVENT in respect of DAMAGE to TUNNEL WORKS’.
And in the exclusions
to
Section 1
, clause 8 is devoted in its
entirety to exclusions in respect of tunnel works. A final sub-clause
of clause 8 makes it clear that
tunnel works are part of the property
insured. This sub-clause reads:
‘
In
the event of indemnifiable loss or damage the maximum amount payable
under this Policy shall be limited to the expenses incurred
to
reinstate PROPERTY INSURED A to a standard or condition technically
equivalent to that which existed immediately before the
occurrence of
loss or damage but not in excess of the percentage stated below of
the original average per-metre construction cost
of the immediate
damaged area.’
[51]
In the memoranda to
Section 1
, the insurers undertook to pay the
‘costs and expenses necessarily and reasonably incurred by THE
INSURED in the removal
and disposal of debris, detritus and material
foreign to THE PROJECT’ in respect of tunnel works, subject to
an indemnity
limit. Similar provisions apply to extra charges such as
overtime and night work in respect of tunnel works.
[52]
From the above, it seems to me that the policy is intended to give
extremely wide cover to the
insured. That cover operates in respect
of damage to ‘the PROPERTY INSURED howsoever caused’,
subject to various limitations
and exclusions. In this scheme, a
number of terms that have been defined in the policy, such as
‘property insured’,
‘tunnel works’ and ‘civil
works’, tend to overlap: what emerges clearly enough, however,
is that tunnel
works, being permanent works, fall within the
definition of the property insured, and tunnels works specifically
include tunnels.
Tunnel works are also the subject of specific
exclusions and limitations. They would only be subject to those
exclusions and limitations
if they were part of the property insured.
[53]
What the policy does not do, however, is define what is meant by a
tunnel. The dictionary definition
of a tunnel is ‘an artificial
underground passage, as built through a hill or under a building . .
.’.
[15]
It can, I
believe, be inferred that an underground passage has, of necessity, a
floor, a roof and sides and that they comprise
the surrounding rock
mass through which the passage was excavated.
[54]
I turn to the evidence of Dr Barton and professor Roald as to what,
in civil engineering terms,
a tunnel is. I do so because the context
within which the policy, and the word ‘tunnel’ that
appears in it, must be
interpreted is a massive civil engineering
project involving, centrally, the excavation of tunnels through rock.
When the word
‘tunnel’ was used in the policy, it must
have been used as a technical, civil engineering term. In
circumstances such
as this, expert evidence is admissible, and does
not offend the parol evidence rule. In
Wides
v Davidson
[16]
Claasen J held that ‘it is a clear principle that oral evidence
may be given to prove that a word used in a contract has
a special
meaning in a particular locality, trade or usage if it was intended
that the word was to be used in that special sense’.
So too, an
expert may explain the meaning of technical terms, but they may not
venture their opinion of what they believe the document
being
interpreted means.
[17]
[55]
In the executive summary of Dr Barton’s expert report he said
that, in the light of Zurich’s
argument, he had to devote
‘considerable space’ to a ‘rock mechanics
explanation that the rock mass surrounding
the actual cylindrical
excavation is very much part of, indeed by far the most essential
component, of any and all tunnels in rock
masses’. He described
Zurich’s contrary contention as ‘
extra-ordinary
’
and one which he had never encountered before ‘during a long
career and hundreds of projects in more than three-dozen
countries’.
[56]
The reason why the rock mass is such an essential component of a
tunnel is because of its load-bearing
capacity. The concept that it
is a fundamental component of the tunnel is a universally accepted
one among tunnel designers throughout
the world. The surrounding rock
mass is crucial to the stability of tunnels, whether man-made or
naturally formed. The rock mass
has, Dr Barton said, even been
described as the ‘principal structural material’ involved
in the construction of a tunnel,
being far stronger than concrete or
steel. These materials simply cannot withstand the tremendous loads
involved, and which are
instead ‘distributed through as much as
tens of metres of rock mass’.
[18]
[57]
Simply put, without the surrounding rock mass ‘with typically a
“cylinder thickness”
of at least one tunnel diameter, and
without its multiple-component response to excavation, thereby
allowing the newly excavated
tunnel to exist, there can be no tunnel,
by simple definition’. As a result, the entire ‘tunnel-forming
cylinder .
. . is the tunnel by default’. This exposition was
summarized by Dr Barton as follows:
‘
A
“rock” tunnel cannot exist unless it is surrounded by its
own load-bearing “cylinder” of rock, estimated
to be at
least one tunnel diameter thickness for convenience. This “cylinder”
would also be the appropriate volume
into which the micro-cements
could have penetrated, (say 0 to 10m from the tunnel periphery), if
pre-grouting had been performed.
The rock blocks and rock joints in
this nearest “10m thick cylinder” take an active and
necessary part in the stress
redistribution, which compensates for
removal of the stressed rock from within the newly created tunnel
void. The load that immediately
builds up in the surrounding rock
“cylinder” (in fact it starts to build up also about one
diameter ahead of any given
tunnel face) allows the formation of the
more or less stable tunnel structure. Clearly the surrounding rock is
the main element
of the insured property.’
[58]
I have quoted from Dr Barton’s expert report but what he has
written therein is consistent
with his evidence, which Wepener J
accepted without qualification. His opinion that the surrounding rock
mass is an indispensable
component of a tunnel was supported by
professor Roald, whose evidence was also accepted without
qualification by Wepener J. Professor
Roald made the point that
‘[t]unnelers around the world have long recognized that the
rock mass surrounding a tunnel forms
the principal component of the
tunnel structure’ and that they recognize that even if a tunnel
requires a lining, ‘the
most important component of the
structure is the ground/rock surrounding the tunnel’. From this
he concluded that ‘what
constitutes a tunnel is far more than
just the (final) tunnel lining’.
[59]
In civil engineering terms, then, a tunnel is more than the void left
after the excavation process.
It includes the natural support for the
void, without which there would be no tunnel. A tunnel such as those
with which this case
is concerned, is therefore a void surrounded by
its own load-bearing cylinder of rock of about one tunnel diameter in
thickness.
The parties, in agreeing to the terms of the policy in
relation to a civil engineering project involving, inter alia, the
construction
of tunnels in rock, must have had the above concept of a
tunnel in mind when they included tunnels as part of ‘tunnel
works’
within the property insured. The contextual evidence of
Dr Barton and professor Roald points decisively to this meaning of
the
term. This too, is a commercially sensible interpretation as it
avoids a patent absurdity – the contrary interpretation of
only
a void being part of the property insured would make no sense at all
because, by definition, no damage could ever be caused
to a void; and
the inclusion of it in the policy, subject to exclusions and
limitations, would have been an elaborate act of futility.
[60]
I conclude, therefore, that the property insured by the policy
includes the rock mass that surrounds
the void created by the process
of excavation. The result is that the EDZ4 damage caused by the
failure to pre-grout the tunnels
is indemnifiable in terms of the
policy.
The enforceability
of the order
[61]
I have quoted the order made by Wepener J in paragraph [2] above. It
has, apart from costs, two
operative parts. Paragraph 1 fixed
Zurich’s liability by declaring that it was obliged to
indemnify the province for the
cost of replacing, repairing or making
good the damage to the tunnels. The damage referred to was that
alleged in paragraph 15
of the particulars of claim, and the tunnels
were those referred to in paragraph 11 of the particulars of claim.
This declaration
of Zurich’s liability was made subject to ‘all
the terms and conditions of the policy’.
[62]
In paragraph 2, it was declared ‘on the basis of prayer 1
above’, that Zurich was
obliged to pay the province the amount
that it proved to be the cost of remedying the damage to the tunnels
but this obligation
was made ‘subject to the limit of liability
and deductibles as set out in the policy’.
[63]
Orders like the one made by Wepener J are not unusual in claims of
this nature. In
Cape
Town Municipality and Another v Allianz Insurance Co Ltd
[19]
Howie J explained the rationale and effect of the two-stage process
as follows:
‘
Plaintiffs
are quite patently not seeking to obtain payment of part of the
indemnity now and part later. They are seeking to enforce
their
rights to the indemnity. If further proceedings are instituted by
plaintiffs in due course to exact payment from defendant
pursuant to
judgment in the present case, such further action will be necessary
by reason of the fact that the present action is
only concerned with
the issue of liability, and the further action will cover elements of
plaintiffs' claim not canvassed in the
current action. Conversely,
those elements of the claim covered in the present matter will be
res
judicata
hereafter. But the two actions
together will still deal only with one cause of action. Although the
relief sought in the present
case differs from the relief which will,
on the above supposition, be sought in the second action, the precise
form of the relief
and, if it is monetary relief, the
quantum
thereof, are not elements of the cause of action. For example, if D
commits continuing wrongful acts accompanied by fault and thereby
causes damages to P's property with consequent patrimonial loss, P's
cause of action is fixed irrespective of whether he sues for
damages
or applies for an interdict.’
[64]
And, in
Cadac
(Pty) Ltd v Weber-Stephen Products Co and Others
[20]
Harms DP held that, from a procedural point of view, this two-stage
process was acceptable:
‘
I
cannot see any objection why, as a matter of principle and in a
particular case, a plaintiff who wishes to have the issue of
liability decided before embarking on quantification, may not claim a
declaratory order to the effect that the defendant is liable,
and
pray for an order that the quantification stand over for later
adjudication. It works in intellectual property cases, albeit
because
of specific legislation, but in the light of a court's inherent
jurisdiction to regulate its own process in the interests
of justice
— a power derived from common law and now entrenched in the
Constitution (s 173) — I can see no justification
for refusing
to extend the practice to other cases. The plaintiff may run a risk
if it decides to follow this route because of
the court's discretion
in relation to interest orders. It might find that interest is only
to run from the date when the debtor
was able to assess the quantum
of the claim. Another risk is that a court may conclude that the
issues of liability and quantum
are so interlinked that it is unable
to decide the one without the other.’
In this matter, given the
complexity of the issues not only on the merits but also, I would
imagine, on the quantification of the
damage, it was eminently
reasonable for the province to proceed by way of the two stage
process.
[65]
Zurich’s complaint about the order is that, to quote from its
heads of argument, it ‘does
not bring finality to the dispute
as it does not leave only the issue of quantum to be determined’.
It was argued on this
basis that the order was the result of an
improper exercise of a discretion on the part of Wepener J, was
unenforceable as a result
and ought to be set aside.
[66]
Zurich’s attack on the order is premised on the argument that
it did not draw a clear distinction
between the merits and quantum.
This was said to be so in the sense that the declarator in respect of
the indemnity in paragraph
1 was made subject to ‘all the terms
and conditions of the policy’; and that the declaratory order
in paragraph 2,
to the effect that Zurich was required to pay the
amount proved by the province in respect of the damage it suffered,
was made
subject to ‘the limit of liability and deductibles as
set out in the policy’.
[67]
Even if Zurich’s argument was correct that elements of the
merits were left undecided that,
on its own, would not render the
order vague, ambiguous and unenforceable. Whatever issues remain for
determination in the second
stage of the proceedings are not res
judicata.
[68]
The order unambiguously gives effect to the high court’s
finding that the damage to the
tunnels alleged by the province fell
within the terms of the policy, and that Zurich was, as a result,
obliged to indemnify the
province. When it did so, it rendered this
issue res judicata. It disposed finally of it and left the remaining
issues to be determined
later. The provisos to paragraphs 1 and 2 of
the order do not concern whether Zurich was liable to indemnify the
province, but
the quantification of the damage that it suffered.
They, and paragraph 2 in particular, postulate the second stage of
the proceedings
concerning proof of the amount that it will cost to
remedy the damage, less any relevant exclusions and limits.
[69]
This, it would appear, was precisely what Zurich had in mind, when it
pleaded in the alternative
to there having been no damage to the
tunnels, that ‘insofar as Plaintiff’s claim is in respect
of alleged damage to
Tunnel Works, its entitlement to indemnification
is limited to the cost it has actually incurred to reinstate the
damaged property
as is provided for in the final paragraph of clause
8 of the EXCLUSION TO SECTION 1 clause’. The second stage of
the process
envisages the quantification of the province’s
claim. In so doing, the order sensibly makes provision for exclusions
and
limitations specified in the policy to be taken into account, to
the extent that they apply.
[70]
The order of the high court is clear, unambiguous and enforceable.
Zurich’s argument to
the contrary is untenable.
Conclusion
[71]
The three grounds in respect of which leave to appeal was granted
have all been decided against
Zurich and in favour of the province.
The result is that the appeal must fail.
[72]
I make the following order:
The appeal is dismissed
with costs, including the costs of two counsel.
C Plasket
Judge of Appeal
APPEARANCES
For the
appellant:
C Loxton SC (with D Smith)
Instructed
by:
Knowles Husain Lindsay Inc, Johannesburg
McIntyre Van der Post,
Bloemfontein
For the
respondent:
A Subel SC (with A C Botha SC)
Instructed
by:
Werksmans Attorneys, Johannesburg
Symington De Kok,
Bloemfontein
[1]
I
have, in the square brackets in paragraph 1 of the order, corrected
two patent errors. In its original form, the order transposed
paragraphs 11 and 15 of the particulars of claim. Paragraph 11
defined the tunnels that were the subject of the claim, while
paragraph 15 set out the damage that the province alleged it had
suffered.
[2]
Administrator,
Cape and Another v Ntshwaqela and Others
[1989]
ZASCA 167
;
1990 (1) SA 705
(A) at 715D;
South
African Reserve Bank v Khumalo and Another
[2010] ZASCA 53
;
2010 (5) SA 449
(SCA) para 4;
Tecmed
Africa (Pty) Ltd v Minister of Health and Another
[2012] ZASCA 64
;
[2012] 4 All SA 149
(SCA) paras 16-17.
[3]
Molteno
Bros v South African Railways
1936
AD 408
at 413.
[4]
Firestone
South Africa (Pty) Ltd v Gentiruco AG
1977
(4) SA 298
(A) at 304D-F;
Natal
Joint Municipal Pension Fund v Endumeni Municipality
[2012] ZASCA 13
;
2012 (4) SA 593
(SCA) para 18;
Capitec
Bank Holdings Ltd and Another v Coral Lagoon Investments 194 (Pty)
Ltd and Others
[2021] ZASCA 99
;
2022 (1) SA 100
(SCA) para 25.
[5]
Douglas
v Douglas
[1995]
ZASCA 147
;
[1996] 2 All SA 1
(A) at 8i-j.
[6]
I
have added punctuation to enhance readability. I shall do so below
whenever I cite the policy.
[7]
Gericke
v Sack
1978
(1) SA 821
(A) at 827H-828C;
Links
v Department of Health, Northern Province
[2016] ZACC 10
;
2016 (4) SA 414
(CC) paras 24 and 44.
[8]
Truter
and Another v Deysel
[2006]
ZASCA 16
;
2006 (4) SA 168
(SCA) para 16. See too
Evins
v Shield Insurance Co Ltd
1980 (2) SA 814
(A) at 838D-H;
MacKenzie
v Farmers Co-operative Meat Industries Ltd
1922 AD 16
at 23;
Abrahamse
& Sons v SA Railways and Harbours
1933 CPD 626
at 637.
[9]
Minister
of Finance and Others v Gore NO
[2006]
ZASCA 98
;
2007 (1) SA 111
(SCA) para 17.
[10]
Paras
18-19.
[11]
Centriq
Insurance Company Ltd v Oosthuizen and Another
[2019]
ZASCA 11; 2019 (3) SA 387 (SCA).
[12]
Para
17.
[13]
Para
18.
[14]
Para
21.
[15]
Concise
Oxford English Dictionary
(12
ed) (2011).
[16]
Wides
v Davidson
1959
(4) SA 678
(W) at 681D-E.
[17]
Gentiruco
AG v Firestone (SA) (Pty) Ltd
1972
(1) SA 589
(A) at 617F-618C;
KPMG
Chartered Accountants (SA) v Securefin Ltd and Another
[2009] ZASCA 7
;
2009 (4) SA 399
(SCA) para 40.
[18]
Dr
Barton said that at a depth of 40 metres below surface, ‘there
are already 100 tons/square meter of vertical rock stress’.
[19]
Cape
Town Municipality and Another v Allianz Insurance Co Ltd
1990
(1) SA 313
(C) at 332H-333B.
[20]
Cadac
(Pty) Ltd v Weber-Stephen Products Co and Others
[2010]
ZASCA 105
;
2011 (3) SA 570
(SCA) para 13.
sino noindex
make_database footer start
Similar Cases
Constantia Insurance Company Limited v The Master of the High Court, Johannesburg and Others (512/2021) [2022] ZASCA 179; 2023 (5) SA 88 (SCA) (13 December 2022)
[2022] ZASCA 179Supreme Court of Appeal of South Africa97% similar
68 Wolmarans Street Johannesburg (Pty) Ltd and Others v Tufh Limited (1263/2022) [2024] ZASCA 48 (15 April 2024)
[2024] ZASCA 48Supreme Court of Appeal of South Africa97% similar
Assmang (Pty) Ltd v Commissioner for the South African Revenue Service and Others (311/2024) [2025] ZASCA 121 (29 August 2025)
[2025] ZASCA 121Supreme Court of Appeal of South Africa97% similar
Strategic Partners Group (Pty) Ltd and Others v The Liquidators of Ilima Group (Pty) Ltd (in liquidation) and Others (1291/2021) [2023] ZASCA 27; [2023] 2 All SA 658 (SCA) (24 March 2023)
[2023] ZASCA 27Supreme Court of Appeal of South Africa97% similar
BP Southern Africa (Pty) Ltd v Commissioner for the South African Revenue Service (801/2022) [2024] ZASCA 2; 87 SATC 34; 2025 (4) SA 59 (SCA) (12 January 2024)
[2024] ZASCA 2Supreme Court of Appeal of South Africa97% similar