Case Law[2022] ZAGPJHC 329South Africa
Qualelect Investments Holdings (Pty) Ltd v AZRAPART (Pty) Ltd (2020/15965) [2022] ZAGPJHC 329 (13 May 2022)
High Court of South Africa (Gauteng Division, Johannesburg)
13 May 2022
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2022
>>
[2022] ZAGPJHC 329
|
Noteup
|
LawCite
sino index
## Qualelect Investments Holdings (Pty) Ltd v AZRAPART (Pty) Ltd (2020/15965) [2022] ZAGPJHC 329 (13 May 2022)
Qualelect Investments Holdings (Pty) Ltd v AZRAPART (Pty) Ltd (2020/15965) [2022] ZAGPJHC 329 (13 May 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2022_329.html
sino date 13 May 2022
IN
THE HIGH COURT OF SOUTH AFRICA,
GAUTENG
DIVISION, JOHANNESBURG
CASE
NO: 2020/15965
REPORTABLE:
NO
OF
INTEREST TO OTHER JUDGES: NO
13
May 2022
In
the matter between:
QUALELECT
INVESTMENT HOLDINGS (PTY) LTD
Applicant
and
AZRAPART
(PTY) LTD
Respondent
JUDGMENT
MOORCROFT
AJ:
Order
[1]
In this matter I made the following order on 11 May 2022:
“
Having
read the papers and having heard counsel for the parties, judgment is
given for the applicant as follows:
1.
Payment of R902 754.01 (Nine Hundred and Two Thousand, Seven Hundred
and Fifty-Four Rand
and One Cent);
2.
Payment of R476 132,42 (Four Hundred and Seventy-Six Thousand, One
Hundred and Thirty-Two
Rand and Forty-Two Cents);
3.
Interest a tempora morae at a rate of 7,25%
a.
on the amount of R902 754,01 from 21 November 2019 to the final date
of payment;
b.
on the amount of R476 132,42 from 25 January 2020 to the final date
of payment;
4.
Costs.”
[2]
The reasons for the order follow below.
Introduction
[3]
This matter
concerns the interpretation of a document styled a ‘
letter
of appointment’
dated 12 August 2019 in terms of which the respondent, referred to as
the Employer, appointed the applicant to do the electrical
installation at the Fourways Mall Extensions Project
[1]
in Johannesburg. The applicant was appointed directly by the Employer
and was not a subcontractor.
[4]
The applicant contends that the letter of appointment constitutes the
written agreement between the parties and that it provides for
interim payment certificates to be issued and be submitted to the
respondent for payment. The respondent disputes the right to interim
payments.
[5]
It is common cause that -
5.1
three such interim payment certificates, numbered 1, 3, and
5 were
issued and presented;
5.2
all three
were signed electronically
[2]
by
and on behalf of CKR Consulting Engineers and are headed “
progress
evaluation certificate”
;
5.3
CKR Consulting Engineers were the respondent’s engineers
and
agents;
5.4
the first certificate was issued in September and paid in November
2019;
5.5
the second and third certificates were issued in November 2019
and
January 2020 respectively and the respondent denies an obligation to
pay these certificates.
[6]
In this application the applicant seeks payment of the second and
third
certificates. The respondent denies liability and argue that
the letter of appointment does not provide for interim payment
certificates,
and that variations were not approved. It also alleges
that motion proceedings are inappropriate as there are disputes of
fact.
The
legal status of a payment certificate
[7]
The legal
status of a payment certificate was dealt with in a number of cases
and the principles are not contentious.
[3]
7.1
A payment certificate is a liquid document and when it is signed by
the employer’s agent
it is as if the employer itself had given
an acknowledgement of debt in favour of the contractor;
7.2
The certificate creates a distinct cause of action;
7.3
The underlying contract does not form part of the cause of action;
7.4
The employer is bound to and by the certificate, subject to the
principles of the law of agency;
7.5
The employer is not entitled to dispute the validity of the
certificate on the basis that the
certificate was given negligently
or that the discretion of the agent (usually an engineer or
architect) was not exercised properly;
7.6
The certificate can be attacked on a limited number of grounds, such
as fraud;
7.7
The fact that provision is made for a payment certificate does not by
itself imply that provision
is also made for interim payment
certificates.
Interpretation
of the letter of appointment
[8]
The dispute in this matter is centred on the question whether the
letter
of appointment provides for interim payment certificates, in
other words, the interpretation of the letter of appointment which
constitutes the contract.
[9]
Any
document must be interpreted in its context and on the basis of the
words used.
[4]
A useful starting
point in interpretation is the following
dictum
by Innes CJ in
Glenn
Brothers v Commercial Agency Co Ltd
[5]
:
“
In
reading a document like this,
[6]
we are justified in looking at the circumstances under which the
guarantee was given, and the position of the various parties
concerned. That is necessary in order to enable us rightly to
understand and to place ourselves in the position of the parties at
the time. But, having done that, I do not think we should gather from
the circumstances what the parties meant, or what it is fair
and
equitable to think they meant, and then see whether we can
ingeniously so read the document as to deduce that meaning from
its
language. The right method is first to have regard to the words of
the document, and if they are definite and clear we must
give effect
to them. In every case where a document has to be construed so as to
arrive at the intention of the parties, if a meaning
is apparent upon
the face of the document, that is the meaning which should be given
to it. The tendency of the older authorities,
Roman-Dutch and
English, was to place a strict and adverse construction upon a
document of suretyship. On the other hand, later
cases --- in England
at any rate --- rather tend in the opposite direction. I think the
proper rule is that without bias --- without
prejudice one way or the
other --- we should ascertain from the words of the document the
intention of the parties, and if the
words have a clear and definite
meaning we should give effect to it.”
[10]
A century
later, Wallis JA said in
Natal
Joint Municipal Pension Fund v Endumeni Municipality
[7]
that:
“
[18]
….The present state of the law can be expressed as follows.
Interpretation is the process of attributing meaning to
the words
used in a document, be it legislation, some other statutory
instrument, or contract, having regard to the context provided
by
reading the particular provision or provisions in the light of the
document as a whole and the circumstances attendant upon
its coming
into existence. Whatever the nature of the document, consideration
must be given to the language used in the light of
the ordinary rules
of grammar and syntax; the context in which the provision appears;
the apparent purpose to which it is directed
and the material known
to those responsible for its production. Where more than one meaning
is possible each possibility must be
weighed in the light of all
these factors.
[8]
The process is objective not subjective. A sensible meaning is to be
preferred to one that leads to insensible or unbusinesslike
results
or undermines the apparent purpose of the document. Judges must be
alert to, and guard against, the temptation to substitute
what they
regard as reasonable, sensible or businesslike for the words actually
used. To do so in regard to a statute or statutory
instrument is to
cross the divide between interpretation and legislation. In a
contractual context it is to make a contract for
the parties other
than the one they in fact made. The “inevitable point of
departure is the language of the provision itself”,
[9]
read in context and having regard to the purpose of the provision and
the background to the preparation and production of the document.”
[11]
Because it is the purpose of interpretation to determine the
intention of the parties as
expressed in their written agreement, it
might be permissible to evaluate how the parties themselves saw their
contract and how
they acted out its terms. This should however be
done with some circumspection. It may very well happen that a party
to a contract
may change its mind about the contract after it came
into being and then started to act in a way subtly or materially,
consciously
or unconsciously different from the original intention.
Because the terms of the contract are cast in stone when it is
entered
into, such a subsequent change of mind, whether substantial
or negligible, cannot cast its shadow back on the contract. It is
after
all not for the witness to tell the Court what the contract
means whether by words or by conduct.
[12]
In the present matter the respondent paid the first interim
certificate. There is no explanation
to the effect that it did so in
error. The inference must be that when it paid the first certificate
it believed that it was obliged
to do so. I attach little weight to
this fact however as, if the amount was in fact not due and the
respondent misunderstood its
own obligations at the time, such
misunderstanding on its part cannot possibly influence the
interpretation of the contract. One
would however then have expected
this to be clarified in the answering affidavit.
Analysis
of the letter of appointment
[13]
The letter
of appointment
[10]
provided
for a scope of work reflected in an attached document
[11]
that originated with the applicant, namely an application for
progress payment dated 8 August 2019.
13.1
The price is quoted as R1 266 415.68, exclusive of value
added tax
and the “
unit costs shall be fixed and firm and not subject
to any adjustment whatsoever”.
13.2
Any variation to the price “
shall immediately be brought to
the attention of CKR Consulting Engineers (“CKR”),
Quanticost Quantity Surveyors and
SIP Project Managers (“SIP)”
.
13.3
A detailed working programme was to be submitted by
the applicant for
review and approval by the project managers.
13.4
The applicant was obliged to provide welfare facilities
for its staff
and to comply with the construction drawings and specifications
issued by CKR Consulting Engineers.
13.5
Material and workmanship warranties were to be provided
on certified
completion of the works by CKR Consulting Engineers and the applicant
was to provide an undertaking that current resources
would not be
used by the applicant for direct works and therefore the applicant
would not prejudice a third party, Mota-Engil Construction
South
Africa, from fulfilling its obligations in terms of the principal
billing agreement.
13.6
Payment terms are dealt with in clause 11 and in terms
of clause 12
the “
VAT invoice and statement shall be addressed to”
the postal address of the respondent.
13.7
Clause 11 reads as follows:
“
11 Payment
terms:
11.1
Application for payment – on completion of the works
and by no
later than the 20
th
day of the month.
11.2
Certificate for payment, Issue date – 25
th
day of
the month.
11.3
Certificate for payment, payment due date – 24 (twenty
four)
calendar days from the Certificate for Payment issue date. ”
13.8
Application for payment had to be made on completion
of the works and
by no later than the 20
th
day of the month.
13.9
A certificate for payment must then be issued by the
25
th
day and payment was due 24 calendar days from the certificate for
payment issue date.
13.10
All previous correspondence shall be regarded as null and void, i.e.
does not influence the interpretation of this document.
[14]
The agreement therefore provided for a sequence of events, namely
14.1
an application for payment,
14.2
then approval by means of a certificate
for payment,
14.3
then a VAT invoice and statement.
[15]
These words all have their usual meanings, a certificate being a
document attesting to
a fact and a statement in this context being a
summary of debits and credits. An invoice records a demand for
payment.
[16]
The applicant argues that the agreement provides for periodic
payments and thus for progress
payments certified in respect of works
completed by the 20
th
day of the month, for an interim
payment certificate to be issued by the 25
th
, and payment
to take place 24 days later.
[17]
Clause 11 does not expressly refer to interim payment certificates
but the fact that it
provides for a payment certificate issued on the
25
th
day of the month on the basis of the completion of
works by not later than the 20
th
, and then also provides
for an invoice and a statement, makes it clear that the agreement
does provide for payment certificates
to be issued on a monthly basis
and not only, as the respondent contends, at the very end of the
contract.
[18]
On the respondent’s interpretation all the work would have to
be completed and the
applicant would then have to apply for payment
by the 20
th
of the month. The respondent argues that the
certificate of payment referred to is nothing but an invoice.
[19]
On this interpretation the certificate would be an invoice but there
would not only be
a further invoice but also a statement. This would
be an inexplicable, three-fold duplication (or triplication) and on
the respondent’s
interpretation of the document there would be
no need for a statement or indeed a separate invoice. The statement
would merely
duplicate the invoice that would already be a
duplication of the certificate.
[20]
I conclude that the letter of appointment provides for interim
payment certificates to
be issued and that the respondent’s
engineers (Mr Hobson and Mr Bruzzone) did issue and sign three such
certificates. There
are no disputes of fact that make motion court
proceedings inappropriate.
[21]
It is worth noting, though it is of no relevance to the
interpretation of the contract,
that the engineer who signed the
disputed certificates stood by his signatures and provided the
applicant with an affidavit to
confirm his signature and the fact
that he issued the certificates. He signed as the agent of the
Employer.
Variations
[22]
The respondent also argued that variations were not approved. In
terms of clause 5 of the
letter of appointment, the employer’s
agents had to be apprised of any variations in the price.
[23]
These were approved when the respondent’s engineers certified
the payments.
Conclusion
[24]
I therefore conclude that the agreement provided for interim payment
certificates to be
issued by the respondent’s engineer, and
that he did so. The respondent is bound by the certificates issued by
their engineer.
Interest
[25]
The applicant claims interest on the outstanding amounts at the rate
of 10% per annum.
No case is made out on the papers for this interest
rate and the applicant is entitled only to
mora
interest in
terms of the
Prescribed Rate of Interest Act, 55 of 1975
; in other
words 7.25% per annum when the application was brought.
Costs
[26]
The applicant seeks a punitive cost award. In my view a punitive cost
award is not justified.
The respondent was entitled to argue its
interpretation of the agreement in Court and was not dishonest or in
bad faith in doing
so.
[27]
For all these reasons I made the order quoted in paragraph 1 above.
J
MOORCROFT
ACTING
JUDGE OF THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION
JOHANNESBURG
Electronically
submitted
Delivered:
This judgement was prepared and authored by the Acting Judge whose
name is reflected and is handed down electronically
by circulation to
the Parties / their legal representatives by email and by uploading
it to the electronic file of this matter
on CaseLines. The date of
the judgment is deemed to be
13 MAY 2022
.
COUNSEL
FOR THE APPLICANT: A
J GLENDINNING
INSTRUCTED
BY:
E
TAYLOR ATTORNEYS
COUNSEL
FOR RESPONDENT:
S GROBLER SC
INSTRUCTED
BY:
E G COOPER MAJIEDT INC
DATE
OF THE HEARING:
3 MAY 2022
DATE
OF ORDER:
11 MAY 2022
DATE
OF JUDGMENT:
13 MAY 2022
[1]
I.e., a construction project.
[2]
The respondent initially opposed the application
also on the basis that the certificates were not signed but
this
defence was abandoned when the consulting engineer deposed to an
affidavit in reply that confirmed his signature and with
copies
signed in the traditional fashion also attached.
[3]
See
Randcon
(Natal) (Pty) Ltd v Florida Twin Estates (Pty) Ltd
1973 (4) SA 181
(D);
Smith
v Mouton
1977
(3) SA 9
(W);
Thomas
Construction (Pty) Ltd (In Liquidation) v Grafton Furniture
Manufacturers (Pty) Ltd
1986
(4) SA 510
(N) 514 – 515;
Ocean
Diners (Pty) Ltd v Golden Hill Construction CC
[1993] ZASCA 41
;
1993
(3) SA 331
(A);
Joob
Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture
2009
(5) SA 1
(SCA);
Basil
Read (Pty) Ltd v Regent Devco (Pty) Ltd
[2010] ZAGPJHC 75.
Group
Five Construction (Pty) Ltd v Minister of Water Affairs and Forestry
[2010] ZAGPPHC 36,
2010
JDR 0512 (GNP)
para 13.
[4]
See Christie
The
Law of Contract in South Africa
,
5
th
Edition, 2006, pp 210 to 215.
[5]
1905
TS 737
at pp 740 – 741.
[6]
The document was a written order for the supply
of flour.
[7]
[2012]
2 All SA 262
(SCA),
2012 (4) SA 593
(SCA para 18. See also
Bastian
Financial Services
(
Pty
)
Ltd
v General Hendrik Schoeman Primary School
2008 (5) SA 1
(SCA)
[2008] ZASCA 70
; ,
[2008]
4 All SA 117
(SCA)
paras 16–19;
KPMG
Chartered Accountants
(
SA
)
v
Securefin Ltd & Another
2009 (4) SA 399
(SCA),
[2009]
2 All SA 523
(SCA)
para 39.
[8]
Footnote 15 in the judgment refers to
Re
Sigma Finance Corp
[2008]
EWCA Civ 1303
(CA) para 98;
Re
Sigma Finance Corp
(
in
administrative receivership
)
Re
the Insolvency Act 1986
[2010]
1 All ER 571
(SC)
para 12;
Rainy
Sky SA & Others v Kookmin Bank
[2011]
UKSC 50
,
[2012] Lloyds Rep 34
(SC) para 28, and an article by Lord
Grabiner QC “
The
Iterative Process of Contractual Interpretation”
(2012) 128
LQR
41
.
[9]
Footnote 16 refers to
Re
Sigma Finance Corp
[2008]
EWCA Civ 1303
(CA) para 98 and
South
African Airways
(
Pty
)
Ltd
v Aviation Union of South Africa & Others
2011 (3) SA 148
(SCA)
paras 25–30 [also reported at
[2011]
3 All SA 72].
[10]
Annexure MK5 to founding affidavit (Caselines 001-22).
[11]
Annexure MK6 (Caselines 001-25).
sino noindex
make_database footer start
Similar Cases
Qualelect Investment Holdings (PTY) Ltd v Belo Kies Construction (PTY) Ltd (2021/3529) [2022] ZAGPJHC 430 (22 June 2022)
[2022] ZAGPJHC 430High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Qelesile and Another v Road Accident Fund (14719/2020; 5168/2021) [2023] ZAGPJHC 221 (11 February 2023)
[2023] ZAGPJHC 221High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Selepe v University of Johannesburg (2022/638) [2022] ZAGPJHC 1062 (21 April 2022)
[2022] ZAGPJHC 1062High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Lekalakala v Transnet SOC Limited and Others (19753/2019) [2025] ZAGPJHC 340 (3 April 2025)
[2025] ZAGPJHC 340High Court of South Africa (Gauteng Division, Johannesburg)98% similar
Imalenia and Another v Khwela and Others (48512/2021) [2022] ZAGPJHC 835 (26 October 2022)
[2022] ZAGPJHC 835High Court of South Africa (Gauteng Division, Johannesburg)98% similar