Case Law[2022] ZAGPJHC 333South Africa
Twenty Third Century Systems (Pty) Ltd and Another v SAP African Region (Pty) Ltd (2020/40953) [2022] ZAGPJHC 333 (16 May 2022)
High Court of South Africa (Gauteng Division, Johannesburg)
16 May 2022
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2022
>>
[2022] ZAGPJHC 333
|
Noteup
|
LawCite
sino index
## Twenty Third Century Systems (Pty) Ltd and Another v SAP African Region (Pty) Ltd (2020/40953) [2022] ZAGPJHC 333 (16 May 2022)
Twenty Third Century Systems (Pty) Ltd and Another v SAP African Region (Pty) Ltd (2020/40953) [2022] ZAGPJHC 333 (16 May 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2022_333.html
sino date 16 May 2022
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
CASE
NO:
2020/40953
REPORTABLE:
NO
OF
INTEREST TO OTHER JUDGES: NO
REVISED.
NO
In
the matter between:
TWENTY-THIRD
CENTURY SYSTEMS (PTY) LTD
FIRST PLAINTIFF
TWENTY-THIRD
CENTURY SYSTEMS GLOBAL (PTY) LTD SECOND PLAINTIFF
And
SAP
AFRICA REGION (PTY) LTD
DEFENDANT
JUDGMENT
MANOIM
J
[1]
This case requires me to decide an important principle of contract
law that has been
raised by way of two special pleas.
[2]
In this matter, the plaintiffs sue for loss of profits. The defendant
seeks to avoid
liability by relying on two provisions in the since
cancelled agreement.
[3]
The question is, under what circumstances a party who has repudiated
a contract can
still rely on certain provisions of that contract
against the other party which accepted the repudiation.
[4]
Expressed differently; do all the terms of a contract die with it on
termination or
do some terms survive and if so, which type.
Background
[5]
Over the years the second plaintiff, TTCS, and its predecessors, have
entered into
agreements with the defendant, SAP.
[1]
The essence of these agreements was that TTCS was appointed as a
service provider of SAP products in certain territories. This
entailed selling various information technology services offered by
SAP to its customers.
[6]
SAP is a prominent international provider of these products. TTCS in
turn developed
a customer base for SAP products in various
territories in Sub-Saharan Africa, excluding South Africa. Most of
these customers
are public sector organisations.
[7]
This case concerns their most recent agreement which comprises a
suite three of contracts
that the parties entered into, in May 2016.
It is common cause that they can be treated together as one agreement
for the purpose
of this decision.
[9]
On 1 July 2019 SAP purported to cancel the agreement. SAP then
proceeded to advise
TTCS’ customer base that TTCS was no longer
one of its licensees and hence it was no longer accredited to sell,
service or
maintain SAP software. TTCS claims that as a result, these
customers ceased their business relationship with it and diverted
this
business to SAP Africa.
[10]
However, the 1 July 2019 letter of cancellation erroneously referred
to a September 2009 agreement
between SAP and TTCS. But no such
agreement between the two parties had ever been concluded. This
was pointed out to SAP
by TTCS’ attorneys.
[2]
This precipitated a further letter from SAP to TTCS’ attorneys,
dated 10 July 2019.
[11]
In this letter SAP now states that it had issued the notice to
terminate in respect of the agreement
of May 2016. It then went on to
state that although it was not obliged to give reasons for invoking
the termination it nevertheless
alleged that TTCS was no doubt aware
that “…
significant
corruption allegations
”
against
TTCS: “…
have
been publicly reported”
SAP
went on to allege that there had been multiple violations of SAP’s
Partner Code of Conduct: “…
including
involvement in improper payments and handling of confidential
information.”
[3]
[12]
SAP further alleged that: “Due to the severity and
pervasiveness of these actions, it is
SAP’s view that these
breaches are incapable of remedy.”
[4]
[13]
TTCS’s attorneys wrote back on 15 July 2019 alleging that it
was SAP that had repudiated
the agreement but significantly they
stated: “…our client accepts such repudiation given the
extent of the damage
that your client has caused our client by making
false statements as to the cancellation of your client’s
relationship with
our client.”
[14]
On 30 November 2020, the plaintiffs instituted the present action. In
it, the plaintiffs claim
damages from SAP for loss of profits as a
result of the repudiation of the agreement, which cumulatively
amounted to USD$ 68 034
351 .49.
[15]
SAP in response has raised two special pleas. The first is that the
claim is time barred as it
has been brought more than one year after
the repudiation was made known to the plaintiffs. This time bar plea
emanates from one
of the clauses in the agreement. The second
special plea is that another term of the agreement precludes either
party from
making a claim for loss of profits against the other.
[16]
In its replication TTCS alleged that SAP could not both repudiate the
agreement and then seek
to rely on some of its terms to escape
liability.
[17]
The parties then agreed that this latter issue – the special
pleas and the replication
thereto, should be a separated issue and
heard first. On 30 September 2021 I made an order to this effect at
the request of the
parties.
[18]
On 16 February 2022 I heard argument from both parties in relation to
the separated issue.
Clauses
in the agreement
[19]
The exclusion of liability clause is contained in clause 2 of the
Partner Edge General Terms
and Conditions for the Africa Region
(Partner Edge GTCS)
[20]
It is lengthy so I will confine myself to the essential language. In
a section entitled:
“
Exclusion
of damages; Limitation of liability: Anything to the contrary herein
notwithstanding except for:
(
there follow a list of exceptions not relevant here) but it then goes
on to state: “
Under
no circumstances and regardless of the nature of any claim will SAP,
its licensors or partners be liable to each other or
any other person
or entity …or be liable in any amount for special, incidental,
consequential, or indirect damages, loss
of goodwill or profits work
stoppage, data loss, computer failure or malfunction, attorneys fees,
court costs, interest or exemplary
or punitive damag
es.”
[21]
Put simply, this clause operates to exclude TTCS from bringing its
claim for loss of profits.
There is no dispute that if this clause is
still binding on the parties this is what its effect is.
[22]
The same reliance is placed on the time bar clause. Here the clause
says a partner must initiate
a cause of action within “…
one
year of the date the Partner knew or should have known after
reasonable investigations of the facts giving rise to the claim.”
[23]
According to SAP, the plaintiffs knew of the facts giving rise to
their claim from at least July
2019. First, this is apparent from the
letter of complaint from their attorneys dated 3 July 2019. But
certainly, this would have
been put beyond doubt by the letter from
SAP to the plaintiffs’ attorneys dated 10 July 2019 where SAP
sets out its basis
for alleging that TTCS had breached the agreement.
As it happened the action was only brought in November 2020, thus
over a year
later, and hence, according to the terms of the
agreement, was time barred. On the facts as pleaded I accept that the
plaintiffs
did acquire this knowledge by at least 10 July 2019 and
thus if the clause is indeed still binding the claim is time barred.
Legal
Issues
[24]
There is no serious dispute that the terms of the agreement;
a.
Preclude a claim for damages for loss of profits;
b.
Limit the time period for bringing an action within one year.
[25]
What is in dispute is whether the defendant can still rely on some of
its terms to avoid liability
after having repudiated the contract.
The plaintiffs case is that it cannot.
[26]
The plaintiffs argument can be summarized in the well-known phrase
that ‘a litigant cannot
both approbate and reprobate’.
More simply it cannot blow hot and cold at the same time- deny the
contract whilst for other
purposes seeking to rely on it.
[27]
The defendant’s contention is that despite repudiation, certain
clauses survive termination,
and, in this case, they are the
exclusion of claims for damages for loss of profits and the one-year
time limitation. The defendant
also maintains that it was entitled to
repudiate as TTCS was in breach of the agreement.
[28]
Both parties are able to find some case law to support their
respective contentions but none
of the cases are directly in point.
[29]
This case turns on which line of authority is most persuasive to the
current case.
Case
Law on termination of contracts
[30]
Van Huysteen makes the general point that, a contract is a bundle of
obligations. Termination
does not mean that the entire contract
dissolves. Rather, certain of the obligations may cease whilst others
may survive. That
is the difference between a contract that is void
and one that is cancelled.
[5]
[31]
Since it is common cause this contract was cancelled voidness does
not arise.
[32]
The next question is whether it makes a difference to the survival of
certain clauses as to whether
the party which caused the breach is
entitled nevertheless to invoke them.
[33]
In an early English case,
Johannesburg Municipal Council v
Stewart
, Lord Shaw observed:
“
It does not
appear to me to be sound law to permit a person to repudiate a
contract and thereupon specifically to found upon a term
in that
contract which he has thus repudiated.”
[6]
[34]
Viscount Haldane followed the approach of Lord Shaw a few years later
in
Jureidini v National British and Irish Millers Insurance Co.,
Ltd
where he remarked
:
“…
.
when
there is a repudiation which goes to the substance of the whole
contract I do not see how the person setting up the repudiation
can
be entitled to insist on a subordinate term of the contract still
being enforced.”
[7]
[35]
The
Johannesburg
case had concerned whether an arbitration
clause in the agreement could still be relied upon if the contract
had been terminated.
Lord Shaw and Viscount Haldane had answered this
question in the negative. But in a later case,
Heyman and Another
v Darwins Ltd
,
which also concerned whether an arbitration
clause survives termination, the speeches of the law lords indicate
that they took a
different view to that of their predecessors.
Viscount Simon expressed this in no uncertain terms:
“
I
do not agree that an arbitration clause expressed in such terms as
above ceases to have any possible application merely because
the
contract has " come to an end," as, for example, by
frustration. In such cases it is the performance of the contract
that
has come to an end. ”
[8]
[36]
In another of the speeches in
Heyman,
Lord Macmillan alluded
to the earlier decisions:
“
There still
remains the difficulty raised by the dicta of Lord Shaw and Viscount
Haldane which I have quoted above. It is said to
be wrong to allow a
party to a contract, who has refused to perform his obligations under
it, 'at the same time to insist on the
observance of a clause of
arbitration embodied in the contract. The doctrine of approbate and
reprobate is said to forbid this.
I appreciate the apparent dilemma
but, with the greatest respect, I venture to think it is based on a
misapprehension. The key
is to be found in the distinction which I
have endeavoured to draw between the arbitration clause in a contract
and the executive
obligations undertaken by each party to the other.
I can see nothing shocking or repugnant to law in one business man
saying to
another that he regrets he finds himself unable to go on
with his deliveries under a contract between them, and at the same
time
asking the other to join with him in a reference under an
arbitration clause in their contract in order to ascertain what
compensation
is to be paid for his default. The parties have both
agreed that all questions between them shall be settled by their own
tribunal.
The question of the consequences which are to follow from a
breach, including a total breach, of the obligations undertaken by
one of the parties is just, such a question as both parties have
agreed should go to arbitration. It is not a case of one party
refusing to perform the obligations he has undertaken in favour of
the other and at the same time insisting that obligations in
favour
of himself shall continue to be performed.
The
arbitration clause, as I have said, is not a stipulation in favour of
either party.
I
am accordingly of opinion that the doctrine of approbate and
reprobate does
not
apply to prevent a party to a contract who has declined to proceed
further with the performance of his obligations to the other
party
from invoking an arbitration clause in the contract for the purpose
of settling all questions to which his declinature has
given rise. In
all this I have assumed that the arbitration clause in its terms is
wide enough to cover the dispute.”
[9]
(My
emphasis)
The
Shaw approach
[37]
The approach of Lord Shaw in
Johannesburg,
notwithstanding its later disavowal in
Heyman
,
has nevertheless been followed in some South African cases that the
plaintiff relies on.
[38]
Thus, in
Erasmus v Pienaar
the court held after quoting from
Lord Shaw that:
'It does not appear to me
to be sound law to permit a person to repudiate a contract, and
thereupon specifically found upon a term
in that contract which he
has thus repudiated.”
[10]
[39]
This approach in Erasmus v Pienaar was followed in a later case,
Taggart
v Green
.
Most recently it was followed again in the case of
Discovery
Life Ltd v Hogan and Another
.
[11]
[40]
Moreover, the language of not being entitled to approbate and
reprobate was expressly used by
the court in
Vromolimnos
and Another v Weichbold and Another
[12]
[41]
Thus, as the plaintiff argues, it cannot be said that this approach
of Lord Shaw has not been
followed on several occasion by our courts
notwithstanding its rejection in Heyman.
Heyman
approach
[42]
On the other hand, Heyman has been followed in other South African
cases such as
Atteridgeville
Town Council
.
[13]
In Atteridgeville the court upheld an arbitration clause despite the
fact that both parties were in agreement that the contract
had been
cancelled. But the court distinguished the situation where both
parties have agreed to cancel an agreement by mutual consent,
with
one where they are only in agreement that the contract has been
cancelled but each seeks to claim damages from the other.
“
Here each party
accepts that the opposite party no longer has a duty to perform his
or their primary obligations under the agreements.
To that extent
they are ad idem. At the same time each seeks to claim damages from
the other arising from an alleged unlawful repudiation.
There can be
no question of consensual cancellation, or anything akin to it. The
two situations differ toto caelo. That the parties
to a contract
individually hold the same view as to the consequences that will flow
from a repudiation cannot be equated with the
meeting of their minds
necessary for consensual cancellation. The mere stating of the
proposition highlights its untenability.”
[14]
[43]
What then distinguishes those cases following Heyman where courts
have held that on termination
some contractual clauses survive and
others, following the Lord Shaw approach, state that the repudiating
party cannot rely on
them?
[44]
The cases in South Africa following the approach of Lord Shaw, have
been cases where the repudiating
party has attempted to rely on a
notice clause in the contract despite evincing a clear intention (as
for instance was said by
the court in the Discovery case) intention
to repudiate.
[45]
In that line of cases, it is not surprising that the courts would not
allow the repudiator to
both approbate and reprobate.
[46]
But in the cases following Heyman the clause at issue has been an
arbitration clause. Here courts
have upheld these clauses post
termination seemingly because parties have agreed in advance a
dispute settling mechanism and hence,
they should be held to this
even after termination. (The only exception as noted in
Atteridgeville is where cancellation is brought
about by mutual
consent. That is not the case
in casu
)
[47]
The question then in this case is whether the clauses at issue in
this case are more analogous
to arbitration clauses which survive or
notice clauses which do not.
[48]
In my view they are more analogous to arbitration clauses. The
parties in contracting out of
damages for loss of profits and
limiting time periods for any claim do so in clear contemplation that
one party may be in breach
of the contract and agreeing what rules
should then apply. Thus, they are similar to the situation where
parties agree on arbitration
in anticipation of any dispute they may
have.
[49]
The question is what does the agreement tell us about the parties
intentions in the event of
cancellation? As Van Huysteen remarks:
“
Of particular
importance is the question whether the parties intended that the
provision that gave rise to the particular right
should be in force
after cancellation.”
[15]
[50]
The clear terms of the agreement are that these clauses survive
termination. For instance, in
the Partner Edge section there is a
section headed “Survival” This section refers to several
clauses in the agreement
including the limitation of liability clause
and then states that they: “... will survive any termination of
any part of
this agreement.”
[16]
[51]
This is then reinforced by the following provision:
“
The provisions of
this Agreement allocate the risks as between SAP and Partner [TTCS].
The fees paid by the Partner reflect this
allocation of risk and the
limitation of liability herein. It is expressly understood and agreed
that each and every provision
of this agreement which provides for a
limitation of liability, disclaimer of warranties or exclusion of
damage, is intended by
the Parties to be severable and independent of
any other provision and to be enforced as such.”
[17]
[52]
Moreover, these clauses are reciprocal.
[18]
Either party would have been entitled to rely on them in the event of
a breach by the other. This distinguishes them from
some of the
breach cases where the notice period or provision existed to the
advantage only of the party in breach. Lord MacMillan
in Heyman in
the passage I underlined earlier had remarked on the significance of
reciprocity in coming to this conclusion.
[53]
I have not been asked to consider the point as to whether, despite
the clauses creating reciprocal
rights, they are nonetheless
asymmetrical, in the sense that despite their notional equality,
de
facto
they operate to favour one party over the other. That is
not raised in the papers and would in any event require evidence to
be
led.
[54]
Thus, both textually and in terms of a purposive approach to the
application of the common law
the special pleas should by upheld.
Public
Interest Grounds
[55]
The plaintiffs also rely on a public interest ground for holding that
these two provisions do
not survive termination when it is the result
of a breach by one of the parties.
[56]
The plaintiffs argue that a party should not be allowed to seek
refuge in the provisions of a
contract that it seeks to reject
because of the harsh consequences on the innocent party. This
argument although clothed in constitutional
language adopts the same
line of reasoning as Lord Shaw did in relation to approbation and
reprobation. I do not consider this
posits a novel constitutional
argument not already recognised in the common law.
[57]
Moreover, the Constitutional Court has made clear that whilst
constitutional arguments can be
raised in contractual cases the bar
to doing so is high. In
Boadicea
one of the case the plaintiff
relies on the court nevertheless posed this question:
“
Have the
applicants discharged the onus of demonstrating that the enforcement
of the renewal clauses would be contrary to public
policy in the
particular circumstances of this case? A party who seeks to avoid the
enforcement of a contractual term is required
to demonstrate good
reason for failing to comply with the term.”
[19]
[58]
The plaintiffs in this case have not discharged this onus.
Conclusion
[59]
I have considered both the common law and public interest arguments
raised by the plaintiffs
in this case. I consider that
notwithstanding these, the two relevant clauses have survived the
termination of the contract. The
plaintiffs in this case chose not to
sue for specific performance instead choosing to accept the
repudiation and cancel. In so
doing they had to accept that the
consequences of the clauses, which they had agreed upon
ex ante
,
is that they survive termination.
[60]
Accordingly, the special pleas are upheld and consequently the claim
falls to be dismissed.
ORDER
1. The special pleas are
upheld.
2. The plaintiffs’
claim is dismissed.
3. The plaintiffs are
liable for the costs of the defendant including the costs of two
counsel.
N
MANOIM
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION, JOHANNESBURG
This
judgment was handed down electronically by circulation to the
parties’ and/or parties’ representatives by email
and by
being uploaded to CaseLines. The date and time for hand-down is
deemed to be 10h00 on 16 May 2022.
Date
of Hearing:
16
February 2022
Date
of Judgment:
16 May
2022
Appearances:
Counsel
for the Plaintiff:
Advocate A. Bham SC
Instructed
by:
Stein Scop Attorneys Inc
Counsel
for the Defendant:
Advocates M. Van
der Nest SC and C. Vetter
Instructed
by:
Nortons
Inc
[1]
The
second plaintiff is the wholly owned subsidiary of the first. The
plaintiffs contend that in entering the contract the second
plaintiff acted as agent of the first, something the defendant
denies. However, both parties agree that this issue is not relevant
to my deciding the special pleas. I will therefore refer simply to
the second plaintiff as TTCS from now on and the defendant
as SAP
[2]
See letter dated 3 July 2019 Case Lines 001-45. They alleged the
notice of termination was “…
premature
and likely ineffectual.
”
[3]
Case Lines 001-49. It is not necessary for me to go into the further
allegations contained in the letter as the reasons are not
germane
to the current proceedings.
[4]
Case
Line 001-51
[5]
Van
Huysteen et al,
Contract,
General Principles
volume
6 paragraph 12.95 onwards.
[6]
[1909] S.C. (H.L.) 53; 2 Digest 335 a
[7]
[1915] A.C. 499
at p. 505
[8]
March
1942 All ER annotated page 343 H
[9]
Speech
of Lord Macmillan,
Heyman
op.
cit. pages 347-8
[10]
1984
(4) SA 9
(T) at 24B-C.
[11]
2021(5)
SA 456 (SCA) at paragraph 20
[12]
1991(2)SA
157(C). Here the court held “
A
repudiator is not entitled to be given an opportunity to retract his
repudiation before it is accepted by the innocent party
and he
cannot rely, as in this case on the provisions of a general
forfeiture clause in the contract. He is not entitled to approbate
and reprobate
.”9
at 163 C-D
[13]
Atteridgeville
Town Council and another v Livanos t/a Livanos Brothers Electrical
1992 (1) SA 296 (A).
[14]
Ibid,
304-305
[15]
Van
Huysteen, op. cit., paragraph 12.108.
[16]
See
clause 13 in Article 17, Part1 of the Partner Edge Agreement
[17]
See
clause 2(b) in Article 1, Part 2 of the Partner Edge Agreement
[18]
Ibid
[19]
Beadica
231 CC AND Others v Trustees, Oregon Trust and Others
2020 (5) SA 247
(CC) at
paragraph 91.
sino noindex
make_database footer start
Similar Cases
South African Transport and Allied Workers Union v South African Securitisation Programme (RF) Ltd and Others (2020/ A5066) [2022] ZAGPJHC 66 (7 February 2022)
[2022] ZAGPJHC 66High Court of South Africa (Gauteng Division, Johannesburg)99% similar
South African National Civil Organisation v Ramosie and Others (7016/2019) [2022] ZAGPJHC 323 (6 May 2022)
[2022] ZAGPJHC 323High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Seventy Five on Maude (Pty) Limited v Aveng Africa (Pty) Limited t/a Aveng Grinaker LTA (003754/2022) [2023] ZAGPJHC 564 (26 May 2023)
[2023] ZAGPJHC 564High Court of South Africa (Gauteng Division, Johannesburg)99% similar
South African National Parks v Madyayimile Trading CC and Another (1995/2020) [2022] ZAGPJHC 619 (23 August 2022)
[2022] ZAGPJHC 619High Court of South Africa (Gauteng Division, Johannesburg)99% similar
South African Municipal Workers Union National Medical Scheme (SAMUMED) v City of Ekurhuleni and Others (5068/2021) [2022] ZAGPJHC 701; [2022] 4 All SA 878 (GJ) (25 August 2022)
[2022] ZAGPJHC 701High Court of South Africa (Gauteng Division, Johannesburg)99% similar