Case Law[2024] ZAGPPHC 9South Africa
Proserve Consulting (Pty) Ltd v RMV Engineering Projects (Pty) Ltd (A95/2022) [2024] ZAGPPHC 9 (15 January 2024)
High Court of South Africa (Gauteng Division, Pretoria)
15 January 2024
Headnotes
judgment application and found that none of the defences raised would result
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 9
|
Noteup
|
LawCite
sino index
## Proserve Consulting (Pty) Ltd v RMV Engineering Projects (Pty) Ltd (A95/2022) [2024] ZAGPPHC 9 (15 January 2024)
Proserve Consulting (Pty) Ltd v RMV Engineering Projects (Pty) Ltd (A95/2022) [2024] ZAGPPHC 9 (15 January 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_9.html
sino date 15 January 2024
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
CASE
NO:
A95/2022
(1)
REPORTABLE:
YES
/NO
(2)
OF INTEREST TO OTHER JUDGES:
YES
/NO
(3)
REVISED:
DATE:
15/1/2024
SIGNATURE
In
the matter between:
PROSERVE
CONSULTING (PTY) LTD
Appellant
And
RMV
ENGINEERING PROJECTS (PTY)
LTD
Respondent
JUDGMENT
TOLMAY
J
INTRODUCTION
1.
This is an appeal with the leave of the
court a quo. The respondent (RMV) sought the enforcement of an
adjudication determination
(the determination) made by an
adjudicator. The appellant (ProServe) disputed the enforcement
application on the basis that the
adjudicator’s determination
was late and no reasons were provided and the adjudicator therefore
exceeded his mandate. ProServe
has since abandoned the argument that
no reasons were provided. The court a quo found in favour of RMV and
enforced the determination
by the adjudicator.
BACKGROUND
2.
The parties entered into an NEC3
Engineering and Construction Contract (the contract). ProServe was
appointed as the lead contractor
by the Gauteng Department of
Infrastructure Development (the GDID) for the construction of a
primary school (the project). ProServe
appointed RMV as the
contractor. GDID was not a party to the contract. A dispute arose
between ProServe and RMV regarding two payment
certificates. This
dispute was referred to the adjudicator for resolution. The
adjudicator found in favour of RMV and ProServe
was ordered to pay R2
531 720.48 (two million five hundred and thirty-one thousand seven
hundred and twenty rand forty eight cents)
pertaining to the two
disputed certificates.
3.
The NEC3 contract is a standard contract
used in the constructing industry, it emanates from the United
Kingdom, and is like other
contracts in the construction industry
intended to introduce uniformity of contract in the construction
industry domestically and
internationally. Clause W1.3(8)
provides that the adjudicator decides the dispute
and notifies the parties and the project manager of his decision and
reasons within
four weeks of the end of the period for receiving
information. It also provides that the four-week period may be
extended if the
parties agree. It reads as follows:
“
The
Adjudicator decides the dispute and notifies the Parties and the
Project Manager of his decision and his reasons within four
weeks of
the end of the period for receiving information. This four-week
period may be extended if the Parties agree
.”
This
clause states clearly that the adjudicator is empowered to decide the
dispute within a specified time, unless the parties agree
on an
extension.
4.
Clause 1.4(3) provides that if the
adjudicator does not provide his decision within the time provided by
the contract a party may
notify the other party that he intends to
refer the dispute to the tribunal. It also provides that a party may
not refer a dispute
to the tribunal unless this notification is given
within four weeks of the date by which the adjudicator should have
notified his
decision. It reads as follows:
“
If
the Adjudicator does not notify his decision within the time provided
by this contract, a Party may notify the other Party that
he intends
to refer the dispute to a tribunal. A Party may not refer a dispute
to the tribunal unless this notification is given
within four weeks
of the date by which the Adjudicator should have notified his
decision
”.
THE ISSUE TO BE DECIDED
5.
The remaining issue to be determined is
whether the adjudicator was mandated to deliver his determination
after the agreed date.
6.
The adjudicator was given the date of
20 July 2020, or 28 days after the last date of submissions. On 21
July 2020, after not receiving
the adjudicator’s decision,
ProServe informed the adjudicator that his mandate had expired, and
he was therefore functus
officio. The adjudicator responded and
apologized that he made a mistake in the calculation of the date on
which his determination
was due, and offered to repay the deposit
that was paid to him. ProServe indicated that he could keep the
deposit. This is a clear
indication that the adjudicator initially
accepted that his mandate had lapsed. RMV, however demanded that he
nonetheless render
a decision. The adjudicator capitulated and
rendered a decision on 27 July 2020. ProServe refused to accept the
decision and argued
that the determination was not valid due to the
fact that the adjudicator’s mandate had lapsed.
THE
APPLICABLE LEGAL PRINCIPLES
7.
The
determination of the dispute between the parties requires the
interpretation of the contract. The approach that should be followed
in the interpretation of contracts have been set out in
Natal
Joint Municipal Pension Fund v Endumeni
[1]
(Endumeni).
8.
Although
Endumeni referred to context, it might be interpreted to refer to a
more limited understanding of what would constitute
context as
relating to the provisions of a contract only. In
University
of Johannesburg v Auckland Park Seminary and Another
[2]
(University of Johannesburg) it was clarified that context must be
considered when interpreting any contract and from the outset
“…as
part of the unitary exercise of interpretation”.
9.
In
Capitec
Bank Holdings (Pty) Ltd and Another v Coral Lagoon Investments
[3]
it
was eloquently explained as follows:
“
Endumeni
simply gives expression to the view that the words and concepts used
in a contract and their relationship to the external
world are not
self-defining. The case and its progeny emphasise that the meaning of
a contested term of a contract (or provision
in a statute) is
properly understood not simply by selecting standard definitions of
particular words, often taken from dictionaries,
but by understanding
the words and sentences that comprise the contested term as they fit
into the larger structure of the agreement,
its context and purpose.
Meaning is ultimately the most compelling and coherent account the
interpreter can provide, making use
of these sources of
interpretation. It is not a partial selection of interpretational
materials directed at a predetermined result.
Most contracts, and
particularly commercial contracts, are constructed with a design in
mind, and their architects choose words
and concepts to give effect
to that design. For this reason, interpretation begins with the text
and its structure. They have a
gravitational pull that is important.
The proposition that context is everything is not a licence to
contend for meanings unmoored
in the text and its structure. Rather,
context and purpose may be used to elucidate the text.
”
10.
This more expansive approach must then also
relate to inter alia the nature, scope, purpose and origin of the
contract. This approach,
in my view, will take cognisance of the fact
that the contract forms part of a specific industry which may require
a specific approach
when interpreting it.
11.
The correct approach then seems to be
to allow context and purpose to “elucidate the text”. In
the context of the matter
before us, the matter was decided on papers
and as a result the question of extrinsic evidence did not arise. The
terms of the
contract are quite clear and do not require any special
consideration. The context, namely the fact that this is a
construction
contract is however relevant when interpreting the terms
of the contract. It must also be emphasised that these contracts
require
speedy resolutions of disputes and that the appointment of an
adjudicator and time limits for his decision are included in the
contract to address this need.
12.
The
court was referred to three decisions that deal with the adjudicators
mandate in NEC3 contracts. The first is
Freeman
NO v Eskom Holdings
[4]
(Freeman). In this matter the court heard a summary judgment
application and found that none of the defences raised would result
in success and granted the summary judgment. The court found that in
the absence of a clause that makes time of the essence, failure
by an
adjudicator to deliver the award in the time stipulated in the
contract, cannot be rendered as binding on the parties or
of any
force and effect. The court found support for this conclusion in
clause 93.1 of that contract which provided for a procedure
to be
followed if an adjudicator fails to notify the parties of the
decision or fail to do so within the time provided by the
contract.
[5]
13.
The
second decision referred to is the matter of
Group
Five Construction (Pty) Ltd v Transnet(Pty) Ltd
[6]
(Group Five). In that matter the adjudicator requested an extension
of the time period. The respondent refused to grant the extension
and
on the same day the respondent gave notice to the applicant to refer
the dispute to the tribunal. Despite this, the adjudicator
continued
to communicate and receive information from the applicant and
published his decision out of time. The court held that
the
adjudicator’s mandate terminates in a NEC3 contract at the end
of the time period set by the agreement and that time
is of the
essence in these types of contracts.
[7]
14.
In
Group Five reference was made to international and academic authority
that supports the conclusion that the court came to.
[8]
The importance of speed in these type of contracts and the importance
of keeping to time limits to achieve that goal, as
well as the
fact that the decision is not permanent and may be challenged on
arbitration were pointed out. I agree with the conclusion
by the
court in Group Five that absent a consent to an extension, the
adjudicator’s mandate is terminated.
[9]
15.
The
third judgment referred to is the matter of
Sasol
South Africa (Pty) Ltd v Murray and Roberts.
[10]
The
court however in that matter found that the adjudicator had not
exceeded the time limit. The adjudicator requested further
information as he was entitled to do. The parties proceeded to an
oral hearing which was regarded as evidence gathering process.
Consequently, the period had been extended by consent and the
decision was rendered within the extended period.
16.
The contract in the present matter makes
specific provision for the eventuality that the decision is not
communicated in the allocated
time limit. In this matter, the
contract provides that the time period may be extended by agreement
between the parties. This can
only be interpreted to mean that absent
such an agreement the period may not be extended. This approach is
enforced by the need
for fair, rapid and inexpensive decisions in
construction contracts.
17.
Clause W.1.4(3) provides for the occasion
where the adjudicator does not notify his decision within the time
provided by the contract.
Under those circumstances a party may
notify the other party that he intends to refer the dispute to the
tribunal. This clause
furthermore provides that a party may not refer
a dispute to the tribunal unless notification is given within four
weeks of the
date by which the adjudicator should have notified his
decision. It is therefore clear that the contract itself provides for
the
process that should be followed in the event of a failure of the
adjudicator to notify the parties timeously of his decision and
the
parties are bound by the terms of the agreement.
18.
Taking into consideration the context and
purpose of construction contracts, the need for a speedy adjudication
process and the
terms of the agreement, the adjudicator’s
mandate was limited to a specific moment in time and once that
expired, he was
not mandated to make an adjudication and therefore
the adjudication cannot be enforced.
19.
As a result, the court a quo misdirected
itself when it was concluded that the application should succeed,
therefore the appeal
should be upheld.
The following order is
made:
1. The appeal is upheld.
2.The court a quo’s
order is set aside and substituted with the following:
a) The application is
dismissed.
b) The respondent is
ordered to pay the costs, including the costs of the appeal.
R G TOLMAY
JUDGE OF THE HIGH COURT
GAUTENG DIVISION,
PRETORIA
D MAKHOBA
JUDGE OF THE HIGH COURT
GAUTENG DIVISION,
PRETORIA
L COETZEE
ACTING JUDGE OF THE HIGH
COURT
GAUTENG DIVISION,
PRETORIA
Appearances:
For
Appellant:
Adv
HWS Martin
Instructed
by
Cliffe
Dekker Hofmeyer
For
Respondent:
Adv
P Bellin
Instructed
by
E
Taylor Attorneys
Date
of Hearing:
4
October 2023
Date
of Judgment:
15
January 2024
[1]
2012
(4) SA 593
(SCA) at para 18: “
Interpretation
is the process of attributing meaning to the words used in a
document, be it legislation, some other statutory
instrument, or
contract, having regard to the context provided by reading the
particular provision or provisions in the light
of the document as a
whole and the circumstances attendant upon its coming into
existence. Whatever the nature of the document,
consideration must
be given to the language used in the light of the ordinary rules of
grammar and syntax; the context in which
the provision appears; the
apparent purpose to which it is directed and the material known to
those responsible for its production.
Where more than one meaning is
possible each possibility must be weighed in the light of all these
factors. The process is objective
not subjective. A sensible meaning
is to be preferred to one that leads to insensible or unbusinesslike
results or undermines
the apparent purpose of the document. Judges
must be alert to, and guard against, the temptation to substitute
what they regard
as reasonable, sensible or businesslike for the
words actually used. To do so in regard to a statute or statutory
instrument
is to cross the divide between interpretation and
legislation. In a contractual context it is to make a contract for
the parties
other than the one they in fact made. The ‘inevitable
point of departure is the language of the provision itself’,
read in context and having regard to the purpose of the provision
and the background to the preparation and production of the
document.”
[2]
(2021)
50503 JOL (CC) at para 69.
[3]
(2021)
JOL 50742
(SCA) at para 50-51.
[4]
(2010)
JOL 25357 (GSJ).
[5]
Ibid
at para 22 – 25.
[6]
(2019)
JOL 45795 (GJ).
[7]
Ibid
at para 21.
[8]
Ibid
at para 17 – 20.
[9]
Ibid
at para 21.
[10]
(2021)
JOL 50626
(SCA).
sino noindex
make_database footer start
Similar Cases
Pro Secure (Pty) Ltd v Mogale City Local Municipality and Others (2025-043172) [2025] ZAGPPHC 479 (16 May 2025)
[2025] ZAGPPHC 479High Court of South Africa (Gauteng Division, Pretoria)99% similar
LSO Consulting Engineers (Pty) Ltd and Another v Ndyamara and Others (56620/2021) [2022] ZAGPPHC 168 (23 March 2022)
[2022] ZAGPPHC 168High Court of South Africa (Gauteng Division, Pretoria)99% similar
Sezigen Consulting Engineers And Project Managers (Pty) Ltd v Mpati N.O and Others (25428/22) [2024] ZAGPPHC 193 (9 February 2024)
[2024] ZAGPPHC 193High Court of South Africa (Gauteng Division, Pretoria)99% similar
Kgoano Consulting and Projects Management CC and Another v Business Partners Limited (30127/2021) [2024] ZAGPPHC 319 (4 April 2024)
[2024] ZAGPPHC 319High Court of South Africa (Gauteng Division, Pretoria)99% similar
South African Professional Firearms Trainers Council NPC v Quality Council for Trades and Occupations and Others (097482/2024) [2024] ZAGPPHC 1388 (2 October 2024)
[2024] ZAGPPHC 1388High Court of South Africa (Gauteng Division, Pretoria)99% similar