Case Law[2024] ZAGPPHC 193South Africa
Sezigen Consulting Engineers And Project Managers (Pty) Ltd v Mpati N.O and Others (25428/22) [2024] ZAGPPHC 193 (9 February 2024)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 193
|
Noteup
|
LawCite
sino index
## Sezigen Consulting Engineers And Project Managers (Pty) Ltd v Mpati N.O and Others (25428/22) [2024] ZAGPPHC 193 (9 February 2024)
Sezigen Consulting Engineers And Project Managers (Pty) Ltd v Mpati N.O and Others (25428/22) [2024] ZAGPPHC 193 (9 February 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_193.html
sino date 9 February 2024
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
Case
Number: 25428/22
REPORTABLE:
NO
OF
INTEREST TO OTHER JUDGES: NO
DATE:
09/02/2024
In
the matter between:
SEZIGEN
CONSULTING ENGINEERS
AND
PROJECT MANAGERS (PTY) LTD
Applicant
and
JUDGE
L MPATI
N.O.
First
Respondent
(Cited
in his official capacity as the Arbitrator)
ARBITRATION
FOUNDATION OF
SOUTHERN
AFRICA
Second
Respondent
HOUSING
DEVELOPMENT
AGENCY Third
Respondent
Delivered:
This
judgment was prepared and authored by the Judge whose name is
reflected and is handed down electronically by circulation to
the
parties/their legal representatives by e-mail and by uploading it to
the electronic file of this matter on Caselines The date
and for
hand-down is deemed to be
09
February 2024
.
JUDGMENT
KUBUSHI,
J
INTRODUCTION
[1]
This is an application to review and set aside part of an arbitration
award. The application is launched by Sezigen Consulting Engineers
and Project Managers (Pty) Ltd ("the Applicant") against
an
Arbitration Award delivered on 28 January 2022 by the First
Respondent, the Retired Justice Lex Mpati, in his official capacity
as the Arbitrator ("the First Respondent"). In particular,
the Applicant seeks to review and set aside only the portion
of the
Arbitration Award regarding the findings on damages.
[2]
In seeking to review and set aside part of the First
Respondent's
Arbitration Award, the Applicant relies on section 33(1) of the
Arbitration Act ("the Arbitration Act").
[1]
Specifically, the Applicant relies on subsection (b) which provides
that where an arbitration tribunal has committed any gross
irregularity in the conduct of the arbitration proceedings or has
exceeded its powers, the Court may on application of any party
to the
reference after due notice to the other party or parties, make an
order setting the award aside. As it will appear more
clearly later
in the judgment, the review application in this matter, is premised
on the allegations that the Arbitrator has committed
gross
irregularity in the conduct of the arbitration proceedings.
[3]
The matter is opposed only by the Third Respondent, the Housing
Development Agency ("the Third Respondent"). The First and
Second Respondents have given notice to abide the outcome
of the
proceedings. In opposing the application, the Third Respondent
requests that the review application be dismissed with costs
on the
scale between attorney and client, including the costs consequent
upon the employment of two counsel.
[4]
The application was not brought within the period as envisaged
in
section 33 of the Arbitration Act. In addition to the review relief
sought, the Applicant wanted specific relief to extend the
period
fixed to launch the application as envisaged in section 38 of the
Arbitration Act. The Third Respondent opposed the condonation
application but abandoned the opposition at the commencement of the
hearing thereof. Condonation should, therefore, be granted.
[5]
The Applicant has in its papers, raised an
in limine
point
which was mounted on the contention that the deponent to the
answering affidavit, Mr Justice Naledzani who is the Third
Respondent's
acting Legal Manager, was not duly authorised to depose
to the answering affidavit and also, did not have personal knowledge
of
the facts of this matter. This point was, also, abandoned at the
commencement of the hearing of this application.
FACTUAL
BACKGROUND
[6]
On 18 September 2018, the Applicant was appointed by
the Third
Respondent as a service provider for the establishment of a
Project
and Programme Management Office
("PMO"). The Applicant
alleges that subsequent to the appointment, the parties entered into
negotiations in respect of
the contract price which was reduced as
the Third Respondent did not have sufficient funds to cover the
amount proposed by the
Applicant in its bid; the method of
termination or suspension of the Agreement which could only be done
in consultation with the
Applicant; and the review of the project
which would require a discussion three months before the start of the
next financial year.
[7]
Premised on the negotiations, the Applicant and the Third Respondent
entered into a written agreement - a Service Level Agreement ("the
Agreement"). In terms of the said Agreement, the Applicant
was
appointed as an independent contractor to render certain services on
behalf of the Third Respondent. The Agreement was effective
from 2
October 2018 to 31 March 2021, for a period of 27 months, spanning
over three financial years. The agreement was subject
to review at
the beginning of the 2019/2020 and 2020/2021 financial years, subject
to budget availability and an addendum which
will be signed at the
beginning of each financial year, depending on the project
requirements. Discussions in this regard would
be entered into three
months prior to the start of the next financial year.
[8]
The Agreement provided for the Applicant to provide certain
services
to assist the Third Respondent in the establishment of the PMO. The
scope of work to be achieved was set out in an addendum
attached to
the Agreement as Annexure "A". The Applicant was therefore,
in terms of the scope of work expected to deliver
services such as a
project stage plan, a project management office implementation
mythology and resource capacity plan, implementation
plan and change
management strategy.
The Third
Respondent would then be liable for payment of the services provided
by the Applicant at the total Agreement amount of
R41 396 524.70
inclusive of VAT
,
excluding disbursements at 5% of R36 073 145.45. Payment of the
services was to be done in line with the payment milestones agreed
to
by the parties in the Agreement. The fees would include disbursements
reasonably incurred by the Applicant in performing the
services as
set out in the Agreement.
[9]
It was an explicit term of the Agreement that the Third Respondent
may in consultation with the Applicant, terminate or suspend all or
part of this Agreement for any reason on 30 days' written notice
to
the Applicant which shall upon receipt of such notice, immediately
suspend all work.
[1O]
According to the Applicant, even though the Applicant was able to
complete the project within less than a year, it was
agreed between
the parties during the negotiations, that the Applicant spread the
scope of work over three financial years, which
actually meant that
the payments would be spread over three financial years in order to
lessen the payment burden on the Third
Respondent. The delivery
support was, however, to be provided over three years as
per
the
agreed deliverables and because this was an actual service that would
be provided.
[11]
On 11 October 2018, the Third Respondent instructed the Applicant by
issuing a purchase
order ("the First Purchase Order") for
the first phase of the services for 2018/2019 financial year to the
value of R13
020 848. The purchase order was based on a programme and
milestones as agreed between the parties and as set out in an
addendum
attached to the Agreement as Annexure "B".
Annexure "B" which is titled 'Payment Milestones', sets out
all
the payment milestones to be achieved and the related payment
amount for each milestone. According to the Applicant, it delivered
these milestones and services to the Third Respondent as
per
the
Payment Milestone attached to the Agreement. The said milestones were
even completed far beyond the First Purchase Order due
to the nature
of the work being integrated and co-dependant. However, the agreement
was that the Applicant would only invoice the
Third Respondent for
this work once it had received the next purchase order from the Third
Respondent,
this
in
order
to
facilitate the
payment
over
three
financial years,
as
agreed between the
parties.
[12]
It is common cause that after completion of the work related to the
First Purchase
Order, the Applicant rendered three invoices to the
Third Respondent totalling R3 846 411. 51, which invoices were paid.
The total
outstanding amount in terms of the First Purchase Order was
R9 174 436. 49. According to the Applicant, when it rendered the said
invoices, it had already completed most of the milestones, except
those which were time based, which still had to be delivered
under
the delivery support. The further total outstanding amount of R28 375
676.70 inclusive of VAT but excluding disbursements
of 5%, which made
up the balance of the total Agreement amount of R41 396 524.70, was
to be allocated over the remainder of the
financial years.
[13]
On 20 December 2018, the Applicant was informed by the Third
Respondent and without
consultation, and contrary to the Agreement,
that the Applicant's Agreement had been suspended. The Applicant
disputed the suspension
of the Agreement as unlawful, but the Third
Respondent continued with it and subsequently made it clear to no
longer be bound to
the terms of the Agreement. The Applicant did not
receive payment of the work already done due to the suspension of the
Agreement
by the Third Respondent.
[14]
On 23 July 2019, the Applicant made formal demand for payment of the
Agreement amount
and outstanding amounts, being the outstanding
amount of R9 174 436. 49
in
terms of the First Purchase Order, and the amount of R28 375 676.70
inclusive of VAT excluding disbursements of 5%, which was
supposed to
have been allocated over the remainder of the financial years.
Despite such demand, the Third Respondent, allegedly,
refused
alternatively, failed further alternatively, neglected to make
payment of the amount so demanded. This caused the Applicant
to
initiate the private arbitration proceedings which proceeded before
the First Respondent.
Arbitration
Proceedings
[15]
The Applicant being not satisfied with the conduct of the Third
Respondent in suspending
the Agreement without consultation with it,
referred the matter for arbitration with the Arbitration Foundation
of Southern Africa
("AFSA"), as
per
the terms of the
Agreement. The arbitration proceedings were adjudicated by the First
Respondent who on 28 January 2022 issued an
unsigned Award wherein he
requested the parties to point to evidence regarding damages, and on
28 February 2022 delivered the final
Award.
[16]
In its statement of claim, the Applicant averred that it suffered
damages 'due to
the unlawful and unexpected suspension of the
Agreement by the Third Respondent; that it accepted the repudiation
of the Agreement
and that it attempted to mitigate further damages by
preventing further costs. It consequently, claimed from the Third
Respondent,
payment of the sum of R37 550 113. 19 as damages
allegedly suffered as a result of the suspension of the Agreement.
The said amount
was divided into two claims, namely Claim 1 made up
of an amount of R9 174 436.49, allegedly being the outstanding amount
for services
rendered by the Applicant in terms of the First Purchase
Order; and Claim 2 in the sum of R28 375 678.70, allegedly being for
the
outstanding agreement amount in terms of milestones completed and
damages for early cancellation of the agreement. The Third Respondent
denied liability in respect of both these claims.
[17]
The first issue which the First Respondent dealt with was the
question of whether
in suspending the Agreement between it and the
Applicant, the Third Respondent complied with the terms of clause 17
of the Agreement
which allowed the Third Respondent to terminate or
suspend the Agreement in consultation with the Applicant. The First
Respondent
found in favour of the Applicant on this issue, that is,
he found that the Third Respondent acted unlawfully in suspending the
Agreement without consulting the Applicant, which resulted in the
repudiation of the Agreement. A further finding by the First
Respondent was that the Applicant suffered damages as a result of the
suspension of the Agreement by the Third Respondent. Even
though such
findings were
made
in
favour
of
the
Applicant,
nevertheless,
the
First
Respondent found that
the Applicant failed to discharge its
onus
regarding
the quantum of damages. The review, thus, relates to the
quantification of the amount claimed by the Applicant as there
is
already a correct finding regarding the merits of the claim - hence
the Applicant's quest to review and set aside only a portion
(the
damages) of the award.
Article
12 Application
[18]
The Applicant was aggrieved by the Award issued by the First
Respondent contending
that the First Respondent failed to address and
make findings on each of the Applicant's respective claims and
instead dealt with
the claims combined as damages. As a result, the
Applicant initiated the Article 12 Application in accordance with
Article 12.7
of the AFSA Commercial Rules, on the ground that the
First Respondent failed to give due regard, consideration and attach
sufficient
weight to the portfolio of evidence provided and led by
the Applicant's witnesses regarding the quantification of the
damages.
[19]
In essence, the Applicant sought a correction of the Arbitration
Award on the basis
that the First Respondent had not referenced the
following documents for purposes of quantifying the claim, namely,
the Project
Procedure Manual page 500 volume E, the ISO 9001
document, the statement of claim, the statement of defence and the
testimony of
the Applicant's witnesses. On 12 March 2022, the First
Respondent delivered his ruling refusing the Article 12.7 Application
on
the basis that none of the documents referred to and testimonies,
elicit or constitute any evidence to prove the Applicant's damages
or
loss. This resulted in the Applicant approaching Court for the review
application.
RELIEF
SOUGHT
[20]
The relief sought by the Applicant is to review and set aside the
Arbitration Award
in so far as the finding on damages is made and
either:
20.1.
Replace it with an order of this Court; or
20.2.
Alternatively, for the first Respondent to hear the matter on
damages;
or
20.3.
Further alternatively, to have the matter referred back to the
Arbitration
Foundation of Southern Africa ("AFSA") to
proceed
de novo
before another arbitrator.
ARGUMENT
[21]
There are two jurisdictional factors which the Applicant must prove
in order to succeed
in the review application. The Applicant must
show that the First Respondent committed a gross irregularity in the
conduct of the
arbitration proceedings or has exceeded his powers.
From the Applicant's papers, it is evident that the Applicant relies
on the
element of gross irregularity of the conduct of the
arbitration proceedings which resulted in the Applicant not having
its case
fully and fairly determined, that led to the Applicant
having an unfair hearing of the matter. The mainstay of the
Applicant's
grief is that it failed to receive a fair hearing because
the First Respondent failed to properly assess all the evidence
placed
before him and make a finding as
per
his mandate on
Claim 1 and Claim 2, instead, the First Respondent dealt with the two
claims as if it were a single claim for damages
without assessing the
evidence that related individually to each of the claims to assist
him in quantifying the claims.
[22]
According to the Applicant, the First Respondent was mandated to
assess the two individual
claims placed before him. Claim 1 was based
on the First Purchase Order and the evidence tendered in that respect
related to the
scope of work that had been completed in terms of the
First Purchase Order but was not yet invoiced at the time of the
suspension.
Claim 2, on the other hand, was based on work completed,
where a purchase order and milestones had not been provided, and the
evidence
relating thereto was provided in terms of the project
implementation plan to prove the claim for damages in this regard.
[23]
The two claims, so the Applicant argues, are set apart by the fact
that Claim 1 had
a purchase order with a complete breakdown of
payments to be made upon completion; whereas, Claim 2 had no such
breakdown. Thus,
the First Respondent not only dealt with the
assessment of the claims incorrectly but failed to deal with them as
per
his mandate set out in the pleadings. This resulted in the
First Respondent not attaching weight to the correct evidence or any
evidence placed before him for the determination of the respective
claims.
DISCUSSION
[24]
Because of the decision finally reached in this judgment, it is not
necessary to
deal with each and every aspect that has been raised in
issue by the parties, as the issues have to be revisited. It is trite
that
quantification of losses needs to be based on factual evidence,
documents and witness statements, as well as expert reports. Losses
should be quantified at the amount which should be paid to the
claimant to put it in the same position that it would have been
but
for the wrongful act.
[25]
The First Respondent found that he could not do the calculation for
the damages or
loss suffered by the Applicant because, according to
him, the parties had agreed that the milestones and deliverables
should be
charged on a time basis only, and there was no evidence
before him to suggest the method of calculating the loss suffered by
the
Applicant. In order to calculate the extent of the Applicant's
damages or loss he intimated that he required evidence of the time
spent on the work performed on each milestone in respect of which no
invoice has been submitted for payment. He explains this evidence
as
'something akin to the portfolio of evidence and amounts paid in
respect of past claims or invoices.'
[26]
From the totality of uncontested evidence presented by the Applicant,
it appears that there were milestones and deliverables
that were
completed and/or achieved which, as the First Respondent found,
formed part of the loss or damages claimed by the Applicant.
It
would, thus, mean that there was actual performance on the part of
the Applicant and it (the Applicant), would under such circumstances
have to be compensated for the loss occasioned by the repudiation of
the contract.
[27]
It is accepted without concluding that from the evidence tendered by
the Applicant, it does not appear that the parties had
agreed that
the milestones and deliverables should be paid on a time basis only.
It is, also, accepted without concluding that
the evidence that the
First Respondent required, which he says was not placed before him,
was presented to him in evidence by the
Applicant's witnesses. Claim
1 is based on actual performance in terms of the purchase order
issued and the evidence presented
if properly evaluated, might have
assisted the First Respondent in the calculation of the loss.
[28]
The Applicant's Claim 2 is based on positive
interesse
on
the ground that the Third Respondent unlawfully and without due cause
repudiated the Agreement. It is a fundamental principle
of our law
that an injured party should be placed, by an award of damages, as
far as possible in the position he would have occupied
had the
agreement been fulfilled. Put differently, he should be placed in the
position he would have occupied had the agreement
been properly and
timeously performed.
[2]
[29]
In addition, in
Hersman
v Shapiro and
Co.
[3]
Stratford J stated the approach that a Court should take :
"Monetary
damages having been suffered, it is necessary for the court to assess
the amount and make the best use it can of
the evidence before it.
There are cases where the assessment by the court is little more than
an estimate; but even so, if it is
certain that pecuniary damages
have been suffered, the court is bound to award damages. It is not so
bound in the case where evidence
is available to the plaintiff which
he has not produced; in those circumstances the Court is justified in
giving, and does give,
absolution from the instance. But where the
best evidence available has been produced, though it is not entirely
of a conclusive
character and does not permit of a mathematical
calculation of the damages suffered, still, if it is the best
evidence available,
the Court must use it and arrive at a conclusion
based upon it."
[30]
There is no finding by the First Respondent that damages herein are
capable
of mathematical computation expecting the Applicant to have
produced evidence to substantiate the exact amount of the damages.
Perhaps, this is a case where the First Respondent could have
assessed the damages on the available evidence.
CONCLUSION
[31]
The conclusion is that the First Respondent committed a gross
irregularity
in failing to properly assess the evidence that was
before him. In committing this irregularity, the First Respondent
prevented
the Applicant from having a fair trial.
[32]
It has been held that under our law a Court has a wide discretion,
and could
refer the award back to the arbitrator to be rendered final
and complete. But it does not follow that the Court will always
follow
that course, it will exercise its discretion.
[4]
Consequently, the relief the Applicant seeks ought to be granted with
an order that the matter be referred back to AFSA to be heard
de
novo
before
another arbitrator.
COSTS
[33]
The Applicant claimed costs only if the matter is opposed. The matter
has become
opposed, and the Applicant being the successful party
should be awarded costs against the opposing party, who is the Third
Respondent.
[34]
The Third Respondent's Counsel, however, submitted that due to the
issue of failure
by the Applicant to select the parts of the record,
which is voluminous, for reading by the Court and the Third
Respondent, the
Applicant should be meted out by a punitive cost
order. The submission being that failure to adhere to the Court rules
should have
consequences, especially in circumstances where issues
could have been narrowed to the specific pages and all parties could
focus
on their preparations.
[35]
In response thereto, Counsel for the Applicant argued that the
Applicant had to file
the record as it is because of the relief it
seeks against the First Respondent. One of the prayers sought is for
the Court to
make a determination of the award and in that case the
Court would require the complete record in order to be able to do so.
[36]
It is trite that the awarding of costs is in the discretion of the
Court hearing
the matter. It is found that it was imperative for the
Applicant to file a complete record because of the specific relief it
sought
for this Court to replace the award with an order of this
Court. As such there is no need to mulcted the Applicant with costs
as
prayed for by the Third Respondent. The Third Respondent is
ordered to pay the costs of this application on a party and party
scale.
ORDER
[37]
The following order is made:
a.
The Condonation application is granted.
b.
The Arbitration Award delivered on 28 January 2022
by the Retired
Justice Lex Mpati, in his official capacity as the Arbitrator is
hereby reviewed and set aside.
c.
The matter is referred back to the Arbitration
Foundation of Southern
Africa to proceed
de nova
before another arbitrator.
d.
The Third Respondent is ordered to pay the
costs of this application
on a party and party scale.
E
M KUBUSHI
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION,
PRETORIA
Date
of hearing: 17 October 2023
Date
of judgment: 09 February 2024
APPEARANCES:
For
the Applicants:
Adv KA Wilson
instructed by Mpoyana Ledwaba
Incorporated.
For
the Third Respondent: Adv Lindelani Sigogo SC and
Adv Lindeni Kalipa
instructed
by Mathopo Moshimane Mulangaphuma Incorporated.
[1]
Act
42 of 1965.
[2]
See
Novick v Benjamin
1972 (2) SA 842
(A) at p857G and Willie's
Principles of South African Law 9th ed p882 - 883.
[3]
1926
TPD 367
at 379.
[4]
Sasson
v Harman 1904 TS at 100
sino noindex
make_database footer start
Similar Cases
Kgoano Consulting and Projects Management CC and Another v Business Partners Limited (30127/2021) [2024] ZAGPPHC 319 (4 April 2024)
[2024] ZAGPPHC 319High Court of South Africa (Gauteng Division, Pretoria)99% similar
Pengi Consulting Engineers & Land Surveyors v Minister of Water and Sanitation (15518/2019) [2022] ZAGPPHC 603 (22 July 2022)
[2022] ZAGPPHC 603High Court of South Africa (Gauteng Division, Pretoria)99% similar
Proserve Consulting (Pty) Ltd v RMV Engineering Projects (Pty) Ltd (A95/2022) [2024] ZAGPPHC 9 (15 January 2024)
[2024] ZAGPPHC 9High Court of South Africa (Gauteng Division, Pretoria)99% similar
LSO Consulting Engineers (Pty) Ltd and Another v Ndyamara and Others (56620/2021) [2022] ZAGPPHC 168 (23 March 2022)
[2022] ZAGPPHC 168High Court of South Africa (Gauteng Division, Pretoria)99% similar
Ingqwele Consulting and Projects Management (Pty) Ltd v Cummins South Africa (Pty) Ltd (27880/2022) [2025] ZAGPPHC 293 (17 March 2025)
[2025] ZAGPPHC 293High Court of South Africa (Gauteng Division, Pretoria)99% similar