Case Law[2022] ZAGPPHC 603South Africa
Pengi Consulting Engineers & Land Surveyors v Minister of Water and Sanitation (15518/2019) [2022] ZAGPPHC 603 (22 July 2022)
High Court of South Africa (Gauteng Division, Pretoria)
22 July 2022
Headnotes
of agreed fees plus site supervision follows, to wit:
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2022
>>
[2022] ZAGPPHC 603
|
Noteup
|
LawCite
sino index
## Pengi Consulting Engineers & Land Surveyors v Minister of Water and Sanitation (15518/2019) [2022] ZAGPPHC 603 (22 July 2022)
Pengi Consulting Engineers & Land Surveyors v Minister of Water and Sanitation (15518/2019) [2022] ZAGPPHC 603 (22 July 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2022_603.html
sino date 22 July 2022
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
REPUBLIC
OF SOUTH
AFRICA
Case
Number:
15518/2019
REPORTABLE:
NO
OF
INTEREST TO OTHER JUDGES: /NO
REVISED:
YES
22
July 2022
In
the matter between:
PENGI
CONSULTING ENGINEERS & LAND
SURVEYORS
Plaintiff
and
MINISTER
OF WATER AND SANITATION
Defendant
JUDGMENT
JANSE
VAN NIEUWENHUIZEN J:
[1]
The plaintiff’s action emanates from engineering services it
rendered to the defendant on a project known as the Emergency Upgrade
of Thukela Goedertrouw Transfer Scheme: Contract WP 0485-WET
(“the
project”) in Kwa-Zulu Natal.
[2]
The plaintiff’s claim is based on an oral contract
alternatively
unjustified enrichment.
[3]
The defendant defended the matter and also filed a counterclaim in
terms
of which it seeks an order that, in the event of the court
finding that an oral agreement was concluded between the parties, the
agreement be declared invalid in terms of section 172 (1) (a) of the
Constitution.
Oral
contract
# Plaintiff’s case
Plaintiff’s case
[4]
Mr Msengi (“Msengi”), a civil engineer and director of
the plaintiff, Pengi Consulting Engineers and Land Surveyors
(“Pengi’), testified that he was contacted by a certain
Mr Muneka (“Muneka”) on or about 30 November 2017. Muneka
indicated that he was an officer in the defendant department
(“the
department”) and that the department wishes to utilise the
plaintiff’s expertise on the project.
[5]
The parties met on 1 December 2017 to discuss the details of the
project.
During
the meeting Muneka explained that he was not registered with the
Engineering Council of South Africa and thus not qualified
to act as
the independent engineer on the project. The department, furthermore,
lacked the capacity and competence required for
the project.
[6]
Munera told Msengi that Pengi must be able to commence with the work
immediately.
When Msengi asked Munera what Pengi’s involvement
would be, Munera answered that Pengi will be appointed as Employer’s
Agent and to provide the department with technical support. The
department expected
Pengi
to inspect AECON’s work and to review and advise on AECON’s
designs. AECON was the contractor on the project.
[7]
As a result, an agreement in the following terms were reached:
7.1
Pengi was appointed as an independent engineer for the purposes of
being the
departments’ agent on the project and/or to act on
behalf of the department;
7.2
the date of commencement of the agreement was 1 December 2017 and
would thereafter
continue for the duration of the project with an
additional 12 month defects period;
7.3
the services to be rendered by Pengi included project supervision /
adjudication
as well as technical support for the review of all
design services which included the following stages:
7.3.1
inception;
7.3.2
concept and viability;
7.3.3
design and development;
7.3.4
documentation and procurement;
7.3.5
contract and administration; and
7.3.6
close out;
7.4
the contract price was R 15 million.
[8]
In confirmation of the aforesaid appointment, Muneka send a letter
dated 4 December 2017 to Mr G Truyens (“Truyens”),
AECONS’s project manager. on the project.
[9]
The services of the plaintiff were urgently needed and to this end a
certificate
to access the project site was issued by Muneka on 6
December 2017 to Pengi for the period 1 December 2017 to 31 March
2020.
[10]
In pursuance of Pengi’s obligations in terms of the contract,
Msengi attended
a senior management meeting on 22 January 2018. The
meeting was chaired by the Deputy Director – General of the
department,
Zandile Makhathini (“the DDG) and attended by
officials of the department and employees of AECON. From the minutes
of the meeting, it is clear that Pengi received instructions to
perform certain work within a certain time frame.
[11]
Under the heading
Claim 1
, Pengi was allocated six out of the
seven tasks. These tasks had to be finalised by 24 January 2018. In
addition, and under the
heading
Other matters of concern
, the
following was minuted:
“
Understanding
of re-measurable contract and approval of BOQ.
A discussion was
held regarding the nature of the contract and that currently there is
not an approved BOQ which is required to
administer the contract. ZM
(Zandile
Makhathini, the DDG)
stated
that although she does not agree with a re-measurable turnkey project
that is the contract that has been signed and as such
the BOQ needs
to be approved in order to re-measure the Works. Pengi Consulting to
review the BOQ and C&V report and provide
approval by 2 February.
Monthly progress
to be verified and approval of the Statement provided at site level.
When the IPA arrives at DWS H/O there should
be no stoppage or
further verification required prior to the processing of the relevant
invoices.”
“
Approval
of the C&V Report
GT explained
that the design component and ultimately the completion of the
construction phase are starting to be affected by lack
of approvals
and decisions from the department’s technical team. ZM
requested that Pengi makes this a priority. CM assured
the meeting
that all reviews and approvals would be completed by 2 February
2018.”
[12]
Msengi was also referred to a letter dated 24 January 2018, which
letter was emailed to
Muneka on even date. The letter is in response
to an opinion that was sought by Muneka. It transpired that the
request for an opinion
actually originated from AECON and that Muneka
forwarded Msengi’s response on the department’s
letterhead and under
his own name to AECON.
[13]
Lastly, Msengi was referred to a letter addressed by the DDG to AECON
on 12 February 2018.
The introductory portion of the letter informed
AECON that the department had recommended Pengi to undertake the
duties of the
Independent Engineer. The scope of work is defined as:
“
Project Adjudication and technical support for review of
all design services which includes the following stages: Inception,
Concept
and viability, design and procurement, contract
administration.”
[14]
The letter set out the scope of Pengi’s duties in detail and in
respect of payment,
the following was recorded:
“
4.
Further note that Pengi Consulting Engineers & Land Surveyors
will be paid in accordance to the principles set out by Gazette
No.
39480 Engineering Professions Act (46/2000): Guidelines for services
and process for estimating fees for persons registered
in terms of
the
Engineering
Professions Act. The all-inclusive Professional Costs will be as per
statutory percentage fee scale (Refer to 4.3.2
Category M) but will
not exceed the amount.”
[15]
A summary of agreed fees plus site supervision follows, to wit:
Item
Gazette Ref Description
Amount
1.
3.3.6 (1) Inception Stage (5%)
R
495 668, 90
2.
3.3.6 (2) Concept and Viability
Stage
2 (25%) R 2 477 844, 61
3.
3.3.6 (3) Design Development
Stage 3
(25%) R 2 477 844, 61
4.
3.3.6 (4) Documentation Stage
4 (15%)
R
1 486 706, 71
5.
3.3.6 (5) Contract Administration
Stage 5 (25%) R 2 477 8 44, 61
6.
3.3.6 (6) Close Out Stage 6 (5%)
R
495 668, 90
6.
3.3.2 Construction Monitoring
R 3 246 516, 70
Sub
Total R
13 157 894, 73
14%
VAT R
1 842 195, 26
# GRAND
TOTAL R15
000 000, 00
GRAND
TOTAL R15
000 000, 00
[16]
In pursuance of Pengi’s duties, Msengi attended at the offices
of Triyans, a representative
of AECON on 20 December 2017. Triyans
presented an overview of the project and as the project was at
inception stage, a large volume
of documents was given to Msengi to
work through. Once Msengi and his team had perused the documents they
had to report to Munera.
[17]
Msengi testified that Pengi was satisfied with the technical side of
the inception stage.
[18]
During January / February 2018, Msengi, Mr Sibuyi (“Sibuyi”),
Pengi’s
project leader on the project and an engineer in
Pengi’s employment held a meeting with AECON. At the meeting
the concept
and viability (CMV) of the project was discussed. Pengi
had to give its approval of the CMV for the project to move to the
next
stage.
[19]
Several site meetings were thereafter attended by Pengi’s team.
Msengi explained
that Pengi did level 3 supervision, which entailed
that its engineers were on site every day to work with the employees
of the
department.
[20]
On 10 July 2018 Pengi presented its first invoice to the department
for payment. The invoice
was not paid and upon enquiries made by
Msengi, he was told that payment is delayed because the department
did not have a budget
for the project. Msengi was, however, given the
assurance that the department is busy finalising the payment
processes and that
Pengi will be paid in due course.
[21]
The invoice remained unpaid. On 28 September 2018 Pengi presented its
second invoice. No
payment was, however, forthcoming and when Msengi
enquired as to when payment will be made, he was told that the
department does
not have a contract with Pengi and that Pengi must
leave the site.
[22]
Pengi’s two engineers that were on site daily, were refused
access to the site
and their internet access was cut off.
[23]
Pengi accepted the termination of the contract and left the site.
[24]
With reference to the amount claimed by Pengi, Msengi testified that
R 8 940 681, 80 was
in respect of fees due and payable to Pengi for
the services it rendered and the further amount of R 6 059 381, 20 is
in respect
of future loss of income.
[25]
The department’s version will be dealt with
infra
. An
aspect that was, however, relevant during cross-examination, was the
computation of Pengi’s claim. It was put to Msengi
that Pengi
has not provided any proof that the services claimed for, were
rendered.
[26]
Pengi’s invoice details is as follows:
Description
%
Work done
Amount
1. Inception
Stage (5%)
100%
R
495 668, 90
2. Concept
and Viability
Stage (25%)
100%
R
2 477 844, 61
3. Design
Development
Stage (15%)
60%
R
1 486 706, 71
4. Documentation
Stage
(15%)
35%
R
520 347, 35
5. Contract
Administration
and Inception (25%)
50%
R
1 238 922, 25
6. Close
Out and As
Built Drawings (5%)
0%
R 0.00
7. Additional
Duties for site plus supervision plus other Special Services
and Disbursements
50%
R 1 623 258, 35
Subtotal
R 7 842
648 , 07
Plus 15% VAT
R 1
079 970, 73
Grand Total
R 8
940 618, 80.
[27]
With reference to the amount claimed in respect of the inception
stage, Msengi explained
that the inception stage was completed and
given to the department. Msengi, further, explained that the concept
and viability stage
could not have proceeded without the finalisation
of the inception stage.
[28]
In respect of the concept and viability stage, Msengi testified that
a concept and viability
report was finalised and submitted to the
department.
[29]
Insofar as the design development stage is concerned, Msengi
explained that Pengi
did not do the design, but was appointed to
review the design.
[30]
It was denied on behalf of the department that Pengi rendered any
services in respect of
the documentation and procurement stage as
well as the contract administration stage. Mr Msengi confirmed that
the percentage claimed
in respect of the two items represent the
services that were rendered in respect thereof.
[31]
Msengi emphasised that the fees charged were prescribed in the
Government Gazette and agreed
upon by the parties, which agreement is
recorded in the letter of the DDG dated 19 February 2018.
[32]
Mr Sibuyi, a professional engineer with almost 40 years’
experience in the profession
testified next. Sibuyi was employed by
Pengi and was appointed as the project leader on the project.
[33]
Sibuyi was referred to the minutes of a Commencement / Start-Up
Meeting held on 1
March 2018, which meeting was chaired by him.
Sibuyi explained that when he arrived on site, there were no formal
site hand-over
documents and that he called the meeting to rectify
the situation. The minutes contain detailed information in respect of
the various
aspects and stages of the project.
[34]
Sibuyi confirmed that he executed his duties in terms of the
agreement between the parties
by
inter alia
appointing site
staff, to wit, Blaster Kapisa (“Kapisa”) as resident
engineer and James Edeldast as assistant resident
engineer.
[35]
The two engineers managed the day to day running of the project and
reported directly
to him.
[36]
Further proof that was discovered by Pengi in respect of the work it
performed on the project,
includes:
36.1
a letter dated 9 March 2018 from Msengi to Truyens in respect of auto
closing spherical ball
valves;
36.2
a letter dated 13 March 2018 from Msengi to Truyens in respect of
isolation valves;
36.3 an email
dated 14 March 2018 from Kapisa to Mkile Ntobeko, the department’s
representative (Ntobeko) in respect
of a proposed rerouting;
36.4 an email
dated 22 March 2018 from Kapisa to Ntobeko in respect of standard
details, P&IDs and Flow Meter Chambers
and a further email on the
same day wherein Kapisa requested the drawings for reinforcement
details from Ntobeko; and
36.5
an email dated 19 April 2018 from Kapisa to Mark Harris from AECON in
respect of an inspection
report.
[37]
Mr Edeldast (“Edeldast”) was Pengi’s third and last
witness. Edeldast
testified that he has a national diploma in civil
engineering and some 20 years’ experience in design work.
Edeldast was
appointed on 1 January 2018 by Pengi as assistant
resident engineer on the project. He worked with Kapisa in managing
the project
and they also did quality and quantities control.
[38]
In order to perform their duties, the department allocated a site
office and internet
access to them. Edelgast and Kapisa were on site
from 7:00 until 17:00 / 18:00 and attended meetings with the
department’s
officials on Mondays.
[39]
They rented accommodation in Greytown and commuted to the site in
order to fulfil their
duties. Edelgast testified that the officials
of the department were not full time on site, but visited the site
from time to time,
as they had other projects to attend to.
[40]
The department informed them in September 2018 that they are no
longer part of the project
and had to leave the site, which they
did.
# Defendant’s case
Defendant’s case
[41]
In order to traverse the evidence of Pengi’s witnesses, Muneka
and Mr Xolani
Mdletsa (“Mdletsa”) were called to testify
on behalf of the department.
[42]
In essence Muneka denied that he, on behalf of the department,
entered into an oral agreement
with Msengi, the representative of
Pengi. Muneka testified
that in terms of the
contract between the department and AECON read with the General
Conditions of Contract for Construction
Works as issued by the South
African Institution of Civil Engineering, Third Edition (2015) an
independent engineer for the project
could only be appointed by the
parties jointly. Muneka, furthermore, stated that he was not
empowered to enter into a contract
with Pengi. It was only the
Director-General of the Department that had the capacity to enter
into contracts on behalf of the department.
[43]
It was also not possible in terms of the contract between the
department and AECON
to appoint Pengi as Employer’s agent,
because the contract provided that an employee of the department must
be appointed
as Employer’s agent.
[44]
When Muneka was confronted with the contents of the letter dated 4
December 2017,
in which he informed AECON that Pengi was appointed by
the department as the department’s independent engineer, he
stated
that the letter was only a recommendation to appoint Pengi.
[45]
I pause to mention that the contents of the letter do not support
Muneka’s version.
The letter reads as follows:
“
Subject:
APPOINTMENT OF THE INDEPENDENT ENGINEER
This letter serves to
inform AECON that Department of water and sanitation (DWS)
will
use Pengi Consulting Engineers (PCE) as
our
Independent Engineer. It’s for the
duration
of the works plus an additional year of for 12 months defects
period.
” (own emphasis)
[46]
When asked to explain the issuing of the access certificate, Muneka
stated that the department
was under pressure to commence with the
project and therefore it was urgent for Pengi to access the site to
familiarise itself
with the project and to obtain information. Muneka
was adamant that the granting of access to the site was not proof
that Pengi
was appointed by the department.
[47]
Noteworthy is the fact that the certificate issued by Muneka to
Pengi, granted access to
Pengi for the total period of the project
and thus confirms the contents of the letter of 4 December 2017
quoted
supra
.
[48]
Muneka was, furthermore, referred to an email he had send to the
officials of the
department and AECON on 16 January 2018. The
contents read as follows:
“
May I
request that Peng consultants be copied in all instructions, circular
of project documents and emails. Official work done
by Pengi will be
done through instructions from DWS. This is for
our
Independent
engineer to be aware of the project.”
(own
emphasis)
[49]
Muneka, once again, stated that he was under pressure and further
stated that Pengi had
to be aware of “
these things”
.
[50]
In respect of the letter by the DDG to AECON on 19 February 2018,
Muneka stated that the
letter only recommended Pengi as the
department’s choice for the appointment of an independent
engineer.
[51]
The letter, however, does not merely “
recommend”
Pengi, but give precise details in respect of the scope of work
and the contract price. One would not expect to find such details
in
a letter that contains a mere recommendation.
[52]
When confronted with the contents of the minutes of the management
meeting on 22
January 2018, Muneka agreed that work was allocated to
Pengi, but stated that it was on the understanding that AECON will
consent
to Pengi’s appointment as independent engineer. Muneka
further stated that the minutes were prepared by AECON and did not
reflect all the items that were discussed at the meeting. An
important issue that was, according to Muneka, discussed was the
undertaking by Mr Green from AECON that the appointment of Pengi will
be fast-tracked.
[53]
This explanation is in stark contrast with the following item in the
minutes:
“
Appointment of
an Independent Engineer/Adjudicator
The
benefits of having an Independent adjudicator appointed for the
duration of the project were explained by JS and agreed to by
the
department. CM of Pengi consulting to continue working with SAICE to
get appointment made.”
[54]
The department’s confusion in respect of the capacity in which
Pengi was appointed,
appears clearly from a letter of AECON dated 2
March 2018:
“
3.
Based on a site meeting that took place on 1 March 2018, we
understand that it is the Department’s intention
that Pengi
Consulting provides technical support services to the Department in
relation to the Project. More specifically, the
services which are
envisaged for Pengi Consulting are similar to the services envisaged
for the Employer’s Agent in the Agreement.
4.
As you will recall, AECON raised various concerns, during the
negotiation of the Agreement, in relation to the position of the
Department
that the Employer’s Agent should be an employee of
DWS and not an independent third party expert. After various
discussions,
it was ultimately agreed that the Employer’s Agent
role be fulfilled by an employee of the Department – but
subject
thereto that an independent and objective person be jointly
appointed by the Parties to act as an Independent Engineer. More
specifically,
the Agreement provides that the Independent Engineer
will be required to rule on any disputes between the Department and
AECON
in relation to a determination by the Employers ‘Agent.
5.
We have already agreed with the Department that Adv Hubert
Thompson will fulfil the role of an Independent Engineer. We also
wish
to emphasise that the role of the Independent Engineer is very
specific, narrow and regulated in detail in the Agreement. More
specifically, the Parties have agreed (in clause 3A of the Contract
Data) that the Independent Engineer:
a.
should be impartial and objective;
b.
shall be a person acceptable to both Parties; and
c.
shall be solely responsible to consider any dispute between the
Parties if the Contractor is dissatisfied by a decision of the
Employer’s
Agent.
7. We note that the
Department envisages that Pengi Consulting should perform, amongst
other things, project adjudication and technical
support in relation
to the design services of the Project. Kindly note that these
envisaged services are in line with the services
which are required
to be performed by the Employer’s Agent within the meaning of
the Agreement.
9.
The Contractor does not have an objection if Pengi Consulting be
appointed by the Department to perform technical support services
to
the Department. Similarly, the Contractor would not object if Pengi
Consulting acts as Employer’s Agent within the meaning
of the
Agreement. However, the Contractor does not agree to the appointment
of Pengi Consultants as Independent Engineer within
the meaning of
the Agreement.
10.
In addition, should Pengi Consulting be appointed as service
provider for technical support and or as Employer’s Agent, the
Contractor would like to understand who will be responsible to
renumerate Pengi Consulting. Kindly take note that the Contractor
did
not budget for these costs in its price. ….
11.
Accordingly, should the Department request that its technical
support service provider be paid directly by the Contractor, the
Contractor
would first required the following:
a.
That the parties enter into good faith discussions to discuss
increases to the price as these costs were not included in the price
of the Contractor;
b.
That the preferred service provider be screened, and be approved,
pursuant to the Contractor’s internal due diligence procedures.
12.
Please let us know if you would like amplification on any of the
issues raised.”
[55]
Muneka’s only response to the contents of the letter was that
Pengi was informed
at the end of March 2018 that they will not be
appointed as Independent Engineer on the project.
[56]
When asked to explain why Pengi would do all the work if there was no
agreement between
the parties, Muneka responded that Pengi did the
work well knowing that AECON has not consented to their appointment
and that they
would not be paid for the work if AECON did not consent
to their appointment. I pause to mention, that this version was never
put
to Msengi.
[57]
During cross-examination Muneka had difficulty in explaining:
57.1
why he used the words “
will use Pengi”
in the 4
December 2017 letter to AECON, if Pengi was not already appointed at
that stage; and
57.2 why he
stated in the 16 January 2018 email to AECON that “
Official
work done by Pengi will be done
through instructions
from
DWS. This is four
our
Independent Engineer …..”,
if Pengi was at that stage not already been appointed by the
department.
[58]
With reference to paragraph 4 of the letter dated 19 February 2018,
where it is stated
that Pengi “
will be paid”,
Muneka
agreed with Mr Mpshe SC, counsel for Pengi, that one would only state
that you
will
pay a person, if that person has already been
appointed.
[59]
Munera was referred to the contents of an email Kapisa send to Mark
Harris from AECON on
19 April 2018, to wit:
“
Hi Mark
The results
presented in your Contractor’s report are unacceptable. Only
test results by an accredited laboratory (on their
letter head)
should be presented. Also where are the test results for the material
that you are compacting as
G5??
Please make
clarifications on this thread and make proper submissions.”
[60]
Mr Mpshe asked Munerk to explain how it was possible that Pengi’s
engineers
still did work on 19 April 2018, if Pengi was told at the
end of March 2018 that they will not be appointed. Munera could not
provide
any explanation for the clear contradiction in his evidence.
[61]
Muneka was also referred to the minutes of the second and third site
meetings that were
respectively held on 19 March 2018 and 16 April
2018. On the front page of the minutes, Pengi is still described as
“
Employer’s Technical Support”
and from the
minutes it is clear that Kapisa attended the meeting in such
capacity. Muneka could not explain why Pengi attended
the 16 April
2018 meeting when their services, according to Muneka, was already
terminated at the end of March 2018.
[62]
In respect of the second site meeting, which was chaired by Kapisa,
Mr Mpshe wanted
to know why Pengi was still allowed to do work at
that stage, when the department already knew that AECON does not
agree to Pengi’s
appointment as Independent Engineer. Muneka
replied that, in view of AECON’s earlier undertaking to
appoint Pengi,
the department was still seeking clarity on the issue.
[63]
I pause to mention, that the department did not present any evidence
of their response
to AECON’s letter.
[64]
When it was pointed out to Muneka that the letter from AECON dated 2
March 2018 did
not tell the department to terminate Pengi’s
appointment, Muneka agreed.
[65]
Mdletsa’s evidence did not take the matter any further.
# Discussion
Discussion
[66]
In analysing the evidence presented on behalf of the parties, it is
clear that the evidence
pertaining to the conclusion of the oral
agreement is irreconcilable. The approach to be followed when faced
with two irreconcilable
versions, has been formulated in
Stellenbosch
Farmers’ Winery Group Ltd and another v Martelle et Cie and
Others
2003 (1) SA 1
(sca) at par [5] as follows:
“……
The
technique generally employed by courts in resolving factual disputes
of this nature may conveniently be summarised as follows.
To come to
a conclusion on the disputed issues a court must make findings on (a)
the credibility of the various factual witnesses;
(b) their
reliability; and (c) the probabilities. As to (a), the court's
finding on the credibility of a particular witness will
depend on its
impression about the veracity of the witness. That in turn will
depend on a variety of subsidiary factors,
not necessarily in
order of importance, such as (i) the witness' candour and demeanour
in the witness-box, (ii) his bias, latent
and blatant, (iii) internal
contradictions in his evidence, (iv) external contradictions with
what was pleaded or put on his behalf,
or with established fact or
with his own extracurial statements or actions, (v) the probability
or improbability of particular
aspects of his version, (vi) the
calibre and cogency of his performance compared to that of other
witnesses testifying about
the same incident or events. As to (b), a
witness' reliability will depend, apart from the factors mentioned
under (a)(ii), (iv)
and (v) above, on (i) the opportunities he had to
experience or observe the event in question and (ii) the quality,
integrity and
independence of his recall thereof. As to (c),
this necessitates an analysis and evaluation of the probability or
improbability
of each party's version on each of the disputed issues.
In the light of its assessment of (a), (b) and (c) the court will
then,
as a final step, determine whether the party burdened with the
onus of proof has succeeded in discharging it. The hard case, which
will doubtless be the rare one, occurs when a court's credibility
findings compel it in one direction and its evaluation of the
general
probabilities in another. The more convincing the former, the less
convincing will be the latter. But when all factors
are equipoised
probabilities prevail.”
[67]
Bearing the aforesaid in mind, I proceed to analyse the evidence of
the respective witnesses.
[68]
Msengi, Sibuyi and Edelgast were impressive witnesses who did not
contradict themselves
during evidence. Their evidence is,
furthermore, in all respects confirmed by the documentary proof.
[69]
The same cannot be said of Muneka’s evidence. Muneka was
visibly uncomfortable
in the witness stand. His evidence was in all
material respects contradicted by the documentary proof.
Muneka’s feeble
attempt to justify the letters and emails
written by him is wholly unsatisfactory. The contents of his various
letters and emails
speak for themselves and his attempt to attribute
a different meaning to the contents thereof is disingenuous.
[70]
Insofar as his evidence differ from that of Pengi’s witnesses,
I have no hesitation
in rejecting his evidence.
[71]
The evidence established that the department did not have the
necessary expertise
to manage the project and that it required the
professional engineering services of Pengi. It, however, seems, that
both Muneka
and the DDG, were under the mistaken impression that
Pengi’s appointment will be financed from the project costs.
The impression
Muneka attempted to create that Pengi was
recommended
by the department as their preferred Independent Engineer is
convincingly dispelled by the documentary evidence. Both Muneka and
the DDG were present at the meeting on 22 January 2018 where
the appointment of an Independent Engineer/Adjudicator was discussed.
It is common cause that advocate Thompson was appointed to the
position by agreement between the department and AECON.
[72]
The fact that the contract between the department and AECON provided
that an employee of
the department will be appointed as Employer’s
Agent apparently only dawned on the department upon receipt of
AECON’s
letter on 2 March 2018. AECON did not object to the
appointment but made it clear that Pengi’s fees will not be
paid from
the contract amount.
[73]
Notwithstanding the aforesaid, Pengi’s services were retained
by the department until
the end of September 2018. The most probable
reason for the termination of Pengi’s services is the reason
advanced by the
department when Msengi enquired in respect of the
payment of the first invoice, to wit the department did not have a
budget to
pay Pengi.
[74]
Muneka’s version that Pengi would render services at no costs
for a period of eight
months, is far-fetched and rejected. Muneka’s
inability to explain why Pengi would continue to render services
until the
end of September 2018, when it was allegedly informed at
the end of March 2018 that it will not be appointed, is significant.
Muneka
could not explain the anomaly because Pengi’s services
were clearly only terminated at the end of September 2018.
[75]
It is highly improbably that Msengi, a registered engineer, will send
invoices in July
and September 2018, if he knew that Pengi did not
have a contract with the department.
[76]
In the result, I am satisfied that Pengi proofed on a balance of
probabilities that an
oral agreement was concluded between Pengi and
the department on the terms contained in the letter dated 19 February
2018 by the
DDG.
# COUNTERCLAIM
COUNTERCLAIM
[77] In
view of the aforesaid finding, the department’s counterclaim
must be considered.
[78] The
department’s counter claim is based on the following
allegations:
“
7. In terms of
section 217(1) of the constitution and the SCM Policy of the
Department of Water and Sanitation, contracting of service
providers
such as the Plaintiff can only be made subject to a bidding that is
transparent, competitive, fair and cost-effective.
8.
No such bidding was conducted in the alleged appointment of the
Plaintiff.
9.
In addition, and in terms of paragraph 12.2.6 of the SCM Policy,
no Professional Service Provider will provide any services until
a
contract is signed. No such contract was signed between the Plaintiff
and the Defendant.
10.
Consequently, the alleged agreement is irregular and ought to be
declared invalid in terms of section 172(1)(a) of the Constitution.”
[79]
The evidence established that the oral agreement between the parties
is in conflict with
both the provisions of section 217(1) of the
Constitution and paragraph 12.2.6 of the Supply Chain Management
Policy of the department.
[80]
In the result and in terms of section 172(1)(a) of the Constitution,
the department
is entitled to an order declaring the agreement
invalid.
[81]
A remedy that is just and equitable in the circumstances should then
be considered in terms
of section 172(1)(b) of the Constitution.
[82] In
Buffalo City Metropolitan Municipality v Asla Construction (Pty)
Ltd
2019 SA 331
CC
,
the Constitutional Court held as
follows at para [104] and [105]:
[104]
When the Municipality took the view that the Reeston contract was
invalid, the implementation of the contract had commenced and was
continuing. The Municipality was content for the respondent to
complete the contract (building lowcost houses) to the benefit of
the
Municipality and residents of Reeston. It was common cause that the
work has been practically completed.
[105]
In these circumstances, justice and equity dictate that the
Municipality should not benefit from its own undue delay and in
allowing
the respondent to proceed to perform in terms of the
contract. I therefore make an order declaring the Reeston contract
invalid,
but not setting it aside so as to preserve the rights to
that the respondent might have been entitled. It should be noted that
such an award preserves rights which have already accrued but does
not permit a party to obtain further rights under the invalid
agreement.”
[83]
In
casu
the department was more than willing to utilise the
services of Pengi until the end of September 2018. Had the department
not raised
the invalidity defence for the first time in its plea and
counter claim, Pengi would have been entitled to payment for the
services
it rendered in terms of the agreement.
[84]
I find the conduct of the department despicable, to say the least. It
would be a travesty
of justice to allow the department to utilise the
professional engineering services of Pengi without paying a cent for
the services
rendered.
[85]
The services pertained to a water crisis that had to be resolved
urgently and Pengi’s
services no doubt benefitted the community
in the area where the services were rendered.
[86]
In the result, I am of the view a just and equitable order would
dictate that the agreement
by the parties should not be set aside.
[87] The
question as to how much fees Pengi is entitled to remains.
[88] I
am satisfied on the evidence that Pengi rendered the services in
respect of the inception stage. This much
is clear from the emails
that were exchanged between Pengi’s employees and the employees
of AECON.
[89] In
respect of the concept and viability stage, Msengi testified that a
concept and viability report
was submitted to the department.
Although the report was not presented in evidence, Mr Manchu, counsel
for the department, did
not deny the existence of the report during
his cross-examination of Msengi.
[90]
It is clear from Msengi’s evidence and the emails that were
exchanged between the parties,
that Pengi did review the work done by
AECON.
[91]
I am, however, unable to determine on the evidence how much of the
design development work was
done. The same applies to the
documentation stage, the work performed in respect of contract
administration and the additional
duties special services and
expenses.
[92]
In the result, I am satisfied that Pengi has established on a balance
of probabilities
that it has rendered services in the amount of R 2
973 513, 51.
# COSTS
COSTS
[93]
Although Pengi was unsuccessful in its claim due to the validity
point raised by the department in its counter claim and in
order to
express my dismay with the conduct of the department, no cost order
will be granted in respect of the counterclaim.
ORDER
The
following order is issued:
1.
The agreement concluded between the plaintiff and defendant is
declared invalid.
2.
The defendant is ordered to pay to the plaintiff an amount of of R 2
973 513,
51.
3.
The defendant is ordered to pay interest on the aforesaid amount at a
rate of
7, 25% per annum from date of judgment to date of payment.
4.
No order as to costs.
N.
JANSE VAN NIEUWENHUIZEN
JUDGE
OF THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
DATE
HEARD PER COVID19 DIRECTIVES:
31
May 2022, 1 – 3 June 2022, 6 June 2022
DATE
DELIVERED PER COVID19 DIRECTIVES:
22
July 2022
APPEARANCES
For
the Plaintifft:
Advocate M Mpshe SC
Advocate F Mzilikazi
Instructed
by: Baloyi-Ntsako
Attorneys
For
the Defendant: Advocate
T Manchu
Advocate M Mpakanyane
Instructed
by:
The
State Attorney
sino noindex
make_database footer start
Similar Cases
LSO Consulting Engineers (Pty) Ltd and Another v Ndyamara and Others (56620/2021) [2022] ZAGPPHC 168 (23 March 2022)
[2022] ZAGPPHC 168High Court of South Africa (Gauteng Division, Pretoria)99% similar
Gcwabe Consulting (Pty) Ltd v South African Police Services (46817/2015) [2022] ZAGPPHC 601 (10 August 2022)
[2022] ZAGPPHC 601High Court of South Africa (Gauteng Division, Pretoria)99% similar
Gcwabe Consulting (Pty) Ltd v South African Police Service (46817/2015) [2022] ZAGPPHC 993 (17 August 2022)
[2022] ZAGPPHC 993High Court of South Africa (Gauteng Division, Pretoria)99% similar
Kgoano Consulting and Projects Management CC and Another v Business Partners Limited (30127/2021) [2024] ZAGPPHC 319 (4 April 2024)
[2024] ZAGPPHC 319High Court of South Africa (Gauteng Division, Pretoria)99% similar
Sezigen Consulting Engineers And Project Managers (Pty) Ltd v Mpati N.O and Others (25428/22) [2024] ZAGPPHC 193 (9 February 2024)
[2024] ZAGPPHC 193High Court of South Africa (Gauteng Division, Pretoria)99% similar