Case Law[2024] ZAGPPHC 868South Africa
Hoshoza Resources Vryheid (Pty) Ltd v Julovista (Pty) Ltd and Others (2024/080004) [2024] ZAGPPHC 868 (16 August 2024)
High Court of South Africa (Gauteng Division, Pretoria)
16 August 2024
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2024
>>
[2024] ZAGPPHC 868
|
Noteup
|
LawCite
sino index
## Hoshoza Resources Vryheid (Pty) Ltd v Julovista (Pty) Ltd and Others (2024/080004) [2024] ZAGPPHC 868 (16 August 2024)
Hoshoza Resources Vryheid (Pty) Ltd v Julovista (Pty) Ltd and Others (2024/080004) [2024] ZAGPPHC 868 (16 August 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2024_868.html
sino date 16 August 2024
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, PRETORIA
Case
number: 2024/080004
Date
of hearing: 30 July 2024
(1)
REPORTABLE
: YES/NO
(2)
OF INTREST TO OTHER JUDGES : YES/NO
(3)
REVISED
16/8/24
In
the
matter of:
HOSHOZA
RESOURCES VRYHEID (PTY) LTD
Applicant
and
JULOVISTA
(PTY)
LTD
First
Respondent
TRIPALEX
(PTY) LTD
Second
Respondent
SVERREYNNE
Third
Respondent
M
DE
BRUYN
Fourth
Respondent
JUDGMENT
SWANEPOEL
J:
INTRODUCTION
[1]
In this
application the applicant ("Hoshoza") seeks an urgent order
interdicting
the first
respondent ("Julovista") from conducting any mining
activities under and in terms of
the
mining right
issued to applicant with DMRE number KZN 10081 (223) MR ("the
mining right"), save for activities related
to Julovista's
rehabilitation obligations in terms of an agreement between the
parties dated 23 August 2022.
[2]
The applicant
seeks an interdict
against
the second
respondent ("Tripalex") that it must take all reasonable
steps to prevent Julovista or anyone acting on its
behalf, from
conducting mining
activities
contemplated
by the mining right, on Portions 1, 4, 8, 9
and
O of the Farm
Zoetmelksrivier. The applicant also seeks unrestricted access to the
aforesaid land. Nothing more
is
needed to be
said in respect of
the
relief
sought
against Tripalex, save that no case whatsoever was made out against
it
and
that the application against Tripalex should be dismissed.
[3]
The applicant
is the holder of the mining right over what is known as the Kariboo
Mining Area. Portions 1,
4,
8, 9 and O of
the Farm Zoetmelksrivier comprise the
''Tripalex
properties".
On 23 August
2022
Hoshoza and
Julovista entered into a written
agreement
in terms
of
which Julovista obtained the right
to
continue with
the processing and reclamation of certain discard and slurry dumps
on
the Soetmelks
section of the
Kariboo Colliery, against payment to Hoshoza of R 30 per tonne of
coal mined.
[4]
The third and
fourth respondents were joined in the proceedings
as
directors of
Julovista
and
Tripalex,
inasmuch as they may have an interest in
the
matter
(although it
later
emerged
that
the
third
respondent
is
the sole
director of both companies). No relief
is
sought
against
them.
[5]
The only
controversial
clause in the
agreement is Clause 2, which reads:
"2.
Duration
2.1
This
agreement
shall
endure
from the
Signature Date and shall terminate on 30 June 2024, unless an
extended period
is
agreed to in
writing between
the
Parties.
"
BRIEF
HISTORY OF THE MATTER
[6]
The
relationship between Hoshoza and Julovista has become acrimonious,
and has devolved into a tussle between them for the control
of the
mining right. Hoshoza alleges that the agreement terminated on 30
June 2024, thereby terminating Julovista's right to mine
under the
mining right, whilst Julovista alleges
that
the agreement
stands to be rectified, to reflect a termination date of 4 December
2033, the same date on which the mining right
lapses.
[7]
On
5
September
2023
Hoshoza's
attorney
wrote
to
Julovista's
attorney. In the letter he addressed certain issues relating to
Julovista's alleged purchase of Hoshoza shares
.
The letter
then records the following:
"Take
note that the
agreement relating to the beneficiation of the dumps expires on
30
June 2024
without further notice."
[8]
In response
Julovista's attorney wrote that
"
We
regard this statement to be a veiled threat.
"
Significantly,
the letter did not deny the factual statement that the agreement was
due
to
terminate on
30 June 2024. On
1
November 2023
Julovista issued summons against Hoshoza seeking
two
alternative
orders.
The first
was
an
order
declaring
clause
4.1.3
.
6.1
of the agreement invalid and unenforceable, and in the alternative,
rectification of clause 4.1.3.6.1. The exact dispute related
to
this
clause is irrelevant to this application. However, what is
significant is that when this action was launched, after Julovista
had been warned that the agreement was due to terminate on 30 June
2024, there was no mention by Julovista that the agreement
incorrectly recorded the termination date. In fact, Julovista itself
pleaded that the agreement was due to terminate on 30 June
2024.
[9]
Hoshoza duly
defended the action, and it delivered an exception to the particulars
of claim. On 30 April 2024 Julovista delivered
an amendment to its
particulars of claim. The particulars of claim contained the
following new Claim 3:
"14.1
The plaintiff avers
that
14.1.1
clause 2 of
the agreement does not correctly and accurately reflect the true and
continuing intention of the parties, as the parties
always intended
that the agreement wou!d
endure
!.ff!ti!
the
expiratlon of
the
defendant's
mining right on 4 December 2033;
14.1.2
the incorrect
recordal of the true and continuing intention of
the
parties was
brought about as a result of an error common to the parties,
alternatively a mutual error;
14.1.3
The agreement
thus falls to be rectified by substituting clause 2.1 of the
agreement with
the following:
'2.1
This
agreement shall endure from the signature date and shall terminate on
4 December 2033 unless otherwise agreed to between the
parties in
writing."
[10]
Julovista delivered amended pages prematurely on 14 May 2024. Hoshoza
opposed the amendment and delivered notice of an irregular
step. I
have been advised that the proposed amendment was withdrawn shortly
before this application was argued.
[11]
On 28 June
2024 Hoshoza wrote to Julovista reminding it that the agreement was
due to terminate on 30 June 2024. Julovista was also
reminded of its
rehabilitation obligations, and
it
was called
upon not to conduct further mining activities
.
On 1 July 2024
Julovista
'
s
attorneys replied to the letter. Julovista
'
s
stance was that clause 2 was the subject of litigation, and any
attempt to
'
disturb
the current status quo
'
would be met
with an application.
[12]
Hoshoza also
disseminated
a
circular to the community
in
which it
reiterated that the contract was coming
to
an end. The
circular was met with a response from the fourth respondent in which
he stated that Julovista was
"
going
nowhere"
.
[13]
Hoshoza contends that
the belated attempt at the rectification of the agreement is a ploy
to extend the term of the contract longer
than the parties had
intended. Julovista says that
there
is a factual
dispute on the papers regarding the termination date that cannot be
determined on the papers. For that reason, says
Julovista, the
application should be dismissed
.
PRELIMINARY
ISSUES
[14]
Before I deal
with the aforementioned issue
,
there
are
some preliminary issues to consider
.
Firstly
,
Julovista says
that Hoshova has made unfounded allegations in the founding
affidavit
,
allegations
that do not find support
in
the facts of
the matter
.
It
is so that Hoshova has made allegations relating to Julovista
'
s
alleged unlawful conduct. However, those allegations are not the sum
total of the case against Julovista
.
The core facts
are in fact not in dispute, in other words, the parties are agreed
that there
is
a written
agreement between them that reflects the termination date as being 30
June 2024. The simple question to be determined
is
whether there
is a real factual dispute regarding the date of termination.
[15]
Julovista's
further contention is that the application is an abuse of Court
processes. It says so because of the lengthy annexures
that were
attached to the founding affidavit. Hoshoza attached the entire
Mining Work Programme, the Water License, and the Environmental
Impact Assessment Report to the founding affidavit. None of these
documents had any discemable relevance to the issues to be decided
in
the application, and they spanned a substantial number of pages.
Hoshoza also did not, with some exceptions, state clearly which
part
of the documents were being relied upon, as is required of a party in
motion proceedings.
[1]
Julovista
urged me to dismiss the application for these reasons alone
.
Although
the decision to attach these documents was an error, I do not believe
that it justifies dismissing the entire application
.
However,
the respondents
should
not have to bear the costs of perusal of these"documents, and !
sha!!
make
an appropriate
order
hereunder
[16]
Julovista
further
contends
that
the
application
is
not
urgent.
Hoshoza says that Julovista's continued mining activities in.
circumstances where its entitlement to mine has ended is an
ongoing
wrong that cannot be rectified if the application were to be heard in
the normal course. Julovista argues that even if
its mining
activities are later found to have been unlawful, and that the
agreement
in
fact
terminated
on
30 June 2024, Hoshoza would not have suffered prejudice because it
would have received the contractual payment due to it in terms
of the
agreement. Hoshoza could also institute a damages claim if it so
wished, argues Julovista.
[17]
The difficulty that I
have with these arguments is that, if Julovista's entitlement
to
mine
has
ended,
and
it
continues
to
mine,
it
prevents•
Hoshoza from exploiting the mine for its own purposes, as it is
entitled to do. As Julovista
continues
to mine,
it
continues to
reduce the ore body available for mining
.
If
Julovista is
allowed to
continue mining whilst its entitlement
to do
so
has
ended,
it
is
cold
comfort
to
say
that
Hoshoza
should
seek damages that may or may not be paid at some stage in future. In
my view, an ongoing wrong should in principle be dealt
with as
speedily as possible.
[18]
Julovista says
that Hoshoza should have known on 30 April 2024
,
when the
proposed amendment was delivered, that Julovista did not intend to
vacate the mine on 30 June 2024. It must be noted that
the first time
that Julovista
expressed
its intention
to remain on the mine was in its attorney's letter of 1 July 2024,
when it intimated that it would resist a change
to the status quo
.
I daresay that
if Hoshoza had brought the application in May, for instance, it would
have been met with the defence that the application
was premature.
[19]
In my view the
application is clearly urgent.
CLEAR
RIGHT
[20]
Julovista has
argued that Hoshova has not demonstrated a clear right to the relief
sought. It contends that Hoshova has not shown
that it owns the
mining right because it did not attach the original mining right to
the papers. Instead, Hoshova attached a mining
right renewal document
that shows that the mining right was extended to 4 December 2033.
[21]
Julovista
itself
says
that
its
right
to
mine
derives
from
the agreement.
The agreement records that Hoshosa is the holder of the mining right,
and that it has given the right to mine in
terms of that mining
license to Julovista. Julovista cannot blow hot and cold. If the
mining right does not exist, then neither
party is entitled to mine.
In fact, Julovista says expressly that it is Hoshova·s
contractor in respect of the mining right.
[22]
In any event, at
Julovista's instance the Department of Mineral Resources and Energy
inspected the mine specifically to determine
whether
there
was
illegal
mining
being
conducted.
The
department
reported that the mining
activities were being conducted on the strength of valid
documentation
.
There is no
merit to this argument.
FACTUAL
DISPUTE
[23]
The final
issue is whether there is a real factual dispute between the parties
relating to the termination
date of the
agreement.
[24]
Julovista said
in its answering affidavit that there is an action pending between
the
parties,
and that the relief sought in the action included a claim for
rectification to reflect the date of termination as 4 December
2033.
The mere existence of this fact, says Julovista, means that there is
a factual dispute that cannot be resolved on the papers.
[25]
Julovista says
that when the parties entered into the agreement, their intention was
not only to allow Julovista
to generate
profit, but
also for it to earn sufficient money to enable it to purchase the
shareholding in Hoshova. It is impossible,
it
says
,
to generate
sufficient money in two years to purchase the mining right, and so
the intention was always that the agreement would
endure for a longer
period
.
Julovista
says, furthermore, that the input costs associated with the
commencement of such a project are such that it takes at least
five
years
to
recover those
costs.
[26]
Julovista says
that
"several
questions
would need to be answered by the parties in order to establish that
this was the intention of the parties at the conclusion
of the
agreement
,
and
this is not possible on affidavit."
[27]
The
question is whether there is a true dispute of fact relating to the
date upon which the agreement
terminates
on
these papers. In
Wightman
t/a
JW
Construction
v Headfour (Pty)
Ltd
[2]
the
Court considered when there can be said to be a true dispute of fact:
"A
real, genuine
and bona fide dispute of fact can exist only where the court is
satisfied that the party who purports to raise the
dispute has in his
affidavit seriously an unambiguously
addressed
the fact said
to be disputed. There will of course be instances where a bare denial
meets the requirement because there is no other
way open to the
disputing party and nothing more can therefore be expected of him.
But even that may not be sufficient if the fact
averred lies purely
within the knowledge of the averring party and no basis is laid for
disputing the veracity or accuracy of the
averment.
When
the facts averred are such that the disputing party must necessarily
possess knowledge of them and be able to provide an answer
(or
countervailing
evidence) if they be not true or accurate but, instead of doing so,
rests his case on a bare or ambiguous denial
the court will generally
have difficulty in finding that the test is satisfied."
(my emphasis)
[28]
Is it
sufficient for Julovista to say that it has sought rectification of
the agreement (belatedly) in other proceedings, when the
basis for
the rectification is not pleaded either in those proceedings, nor in
this application? I think not. I note Julovista's
allegation that a
short-term agreement of this kind does not make business sense. That
may well be
true.
However, when
did Julovista realize this fact? Was it discussed between the parties
when the agreement was negotiated? How did the
allegedly incorrect
date make its way into the agreement?
Why did Mr. Du
Bruyn sign the agreement with an incorrect termination date?
[29]
None of these
questions are answered in the answering affidavit. Julovista has
unique knowledge of the circumstances under which
the negotiations
were held, and what was discussed. It has chosen not to disclose
those facts to this Court. In the absence of
a factual basis for the
contention that the termination date is incorrect and does not
reflect the will of the parties, I cannot
find that there is a live
dispute raised in the papers.
[30]
I am satisfied that Hoshova has established a clear right to the
relief sought. Should the order not be granted, the ore body would
continue to be reduced, which would cause Hoshoza irreparable harm.
Finally, the balance of convenience favours the granting of
the
order. It is also, in my view, important to hold parties to the terms
of the agreements that they have concluded.
[31]
In
the
premises I make the following order:
[31.1]
The
application is dismissed as against the second respondent.
[31.2]
The applicant
shall pay the costs of the second
respondent,
including the
cost of two counsel, on Scale
B.
[31.3]
The first respondent is interdicted and restrained from
conducting
any form of
mining activity under and in terms of the mining right issued and
granted to the applicant
under DMRE
reference
number KZN
10081
(233)
MR ("the Kariboo mining
right")
save for the
mining activities
related
to the
performance of the first
respondent's
rehabilitation
obligations under and in terms of the written agreement concluded by
and between
the
applicant and
the first respondent on 23 August 2022.
[31.4]
The applicant shall pay the
first
respondent's
cost of perusal of Annexures FA 5, FA 6, FA 8, FA 8 A, and FA 21 on
Scale B.
[31.5]
The first respondent shall pay the applicant's costs,
including
the
costs
of
two
counsel
where
so
employed,
excluding the costs of the
Annexures
listed in paragraph 31.4
above, on
Scale B.
SWANEPOELJ
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION ,PRETORIA
Counsel
for the
applicant:
Adv.
NGD Maritz
SC
Adv.
PWT Lourens
Instructed
by:
Krone
and
Associates
Counsel
for
first
and second respondents:
Adv
SG Maritz SC
Adv.
JF
van der
Merwe
Instructed
by:
Venter
de
Villiers Attorneys
Date
heard:
30
July 2024
Date
of
reasons:
16
August 2024
[1]
See:
Swissborough Diamond Mines (Pty) Ltd
and
Others
v
Government
of
the
Republic of South Africa
and
Others
1999
(2)
SA
279
(T)
[2]
[2008] ZASCA 6
;
2008
(3)
SA 371
(SCA)
sino noindex
make_database footer start
Similar Cases
Hoshoza Resources Vryheid (Pty) Ltd v Julovista (Pty) Ltd and Others (2024/080004) [2025] ZAGPPHC 103 (3 February 2025)
[2025] ZAGPPHC 103High Court of South Africa (Gauteng Division, Pretoria)100% similar
Makole Resources (Pty) Ltd v Wessels (26690/2016) [2022] ZAGPPHC 630 (18 August 2022)
[2022] ZAGPPHC 630High Court of South Africa (Gauteng Division, Pretoria)98% similar
South African Reserve Bank and Others v Ibex RSA Holdco Limited and Others (Leave to Appeal) (2023-126938) [2024] ZAGPPHC 1125 (7 November 2024)
[2024] ZAGPPHC 1125High Court of South Africa (Gauteng Division, Pretoria)98% similar
Mogashoa and Others v Zwavel's Nest Homeowners Association (Pty) Ltd and Others (30715/2021) [2024] ZAGPPHC 986 (26 September 2024)
[2024] ZAGPPHC 986High Court of South Africa (Gauteng Division, Pretoria)98% similar
Hossein N.O and Others v Adinolfi and Others (A390/2019) [2022] ZAGPPHC 857 (8 November 2022)
[2022] ZAGPPHC 857High Court of South Africa (Gauteng Division, Pretoria)98% similar