Case Law[2024] ZAWCHC 206South Africa
CMED (Pty) Ltd v Noord Civils (Pty) Ltd and Another (21521/2022) [2024] ZAWCHC 206 (13 August 2024)
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: Western Cape High Court, Cape Town
South Africa: Western Cape High Court, Cape Town
You are here:
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2024
>>
[2024] ZAWCHC 206
|
Noteup
|
LawCite
sino index
## CMED (Pty) Ltd v Noord Civils (Pty) Ltd and Another (21521/2022) [2024] ZAWCHC 206 (13 August 2024)
CMED (Pty) Ltd v Noord Civils (Pty) Ltd and Another (21521/2022) [2024] ZAWCHC 206 (13 August 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAWCHC/Data/2024_206.html
sino date 13 August 2024
IN
THE HIGH COURT OF SOUTH AFRICA
WESTERN
CAPE DIVISION, CAPE TOWN
Case
Number: 21521/2022
In
the matter between:
CMED
(PTY) LTD
Plaintiff
and
NOORD
CIVILS (PTY) LTD
First Defendant
C-T-P
CONSULTING ENGINEERS CC
Second Defendant
JUDGMENT
MAGARDIE AJ:
1.
This is an exception by the second
defendant to particulars of claim in an action where the plaintiff
claims payment of damages
from both defendants in the amount of R
4 948 307.15. The plaintiff’s claims relate to separate
breaches of contract
by the defendants in respect of the construction
and development of 52 residential erven on land owned by the
plaintiff in Langebaan,
Western Cape (‘the project’). The
project was to be known as the ‘The Oyster Catcher Phase 1
Development, Langebaan.’
2.
The plaintiff’s claim against the
second defendant is based on a professional services engineering
contract in terms of which
the second defendant was appointed as the
consulting engineer for the project. The exception is advanced on two
grounds. Firstly,
it is contended that the plaintiff’s reliance
on a tacit term of the engineering contract is precluded by a
so-called ‘whole
agreement’ clause in the latter.
Secondly, it is contended that the plaintiff’s claim seeking to
hold both defendants
jointly and severally liable, is not legally
sustainable. The exception so advanced does not raise a substantive
question of law
which may effectively settle the dispute between the
parties. In such cases, an exception taken on the basis that a
pleading lacks
the averments necessary to sustain a cause of action,
requires the excipient to make out a very clear and strong case for
it to
succeed. I conclude that the second defendant’s exception
does not meet this test. The exception accordingly fails on both
grounds.
Background
3.
On 24 March 2022 the plaintiff and the
first defendant concluded a written agreement in terms of which the
first defendant was appointed
as the contractor in respect of the
construction of the internal roads, engineering services and related
infrastructure for the
project (‘the building contract’).
The building contract comprised of three documents. The first was the
plaintiff’s
written acceptance of the first defendant’s
tender for the project. The first defendant’s tender had been
prepared
and submitted to the plaintiff by the second defendant on
behalf of the first defendant. The second component of the building
contract
was the General Conditions of Contract for Construction
Works (Third Edition, 2015) (‘GCC’). The GCC sets out
standard
conditions of contract which are generally used for building
contracts of this nature. The third component of the building
contract
were certain agreed written amendments to relevant
provisions of the GCC, which were entitled ‘Contract Data’.
The
total price for the construction of the works in terms of the
building contract was R 6 480 715.70.
4.
At approximately the same time that the
building contract was concluded, the plaintiff and the second
defendant concluded a professional
services engineering contract. The
engineering contract was compromised of the second defendant’s
Standard Terms and Conditions
and its quote, submitted in October
2021, for the rendering of the services in terms of the project. The
services to be provided
by the second defendant were recorded to be
‘…
consulting engineering
services pertaining to the design and construction supervision for
the domestic roads and civil engineering
services
’
in respect of the project.
5.
The GCC provided for interim payments to be
made to the first defendant to finance the cost of the construction
work. Interim amounts
would be determined and certified by the second
defendant having regard to inter-alia the estimated value of the
completed construction
work at that stage. The amount of these
interim payments was to be determined by the second defendant in its
capacity as
‘
Employer’s
Agent
’ as defined in clause
1.1.1.6 of the GCC. This clause defines the term ‘
Employer’s
Agent
’ as “…
the
person named as the Employer’s Agent in the Contract Data or
any other person appointed from time to time by the Employer
and of
whom the Contractor is notified, in writing to act as the Employer’s
Agent for the purposes of the Contract as substitute
for the
Employer’s Agent so named
.’
Clause 3.2.21 of the GCC recorded that the function of the Employer’s
Agent was to ‘…
administer
the Contract as agent of the Employer, in accordance with the
provisions of the Contract
.’
6.
The plaintiff pleads in its particulars of
claim that at the time of the preparation and submission of the
tender, both the first
and second defendants knew that in the event
of the tender being accepted by the plaintiff, the second defendant
would in terms
of the relevant provisions of the GCC, be appointed by
the plaintiff as its agent to manage and oversee the project,
particularly
the execution of the building work. In this regard,
clause 5 of the second defendant’s Standard Terms of Agreement
provided
that the second defendant would carry out the services
‘…
with reasonable skill,
care and diligence, for the use of the Client
.’
Similarly, clause 4 of the second defendant’s quote required
the civil engineering services to be designed in accordance
with
‘…
relevant good engineering
practices
.’
7.
The site was made available to the first
defendant on or about 17 August 2022. Construction of the works
commenced immediately.
This promising start to the however proved to
be short-lived.
8.
According to the plaintiff, the first
defendant breached its obligations in terms of the building contract
in numerous material
respects relating to the construction of the
roads in respect of the project. These included construction of the
roads without
adequate compaction tests having been performed in
accordance with SANS1200 specifications. This defect resulted in
substantial
movement of the interlocker pavers in the road surface in
both horizontal and vertical directions. Additional material breaches
of the building contract by the first defendant are alleged to
include deviation from design and material specifications in the
construction of the roads, non-compliance with specification
regarding manhole paving and covers, construction of defective
junction
draw boxes, communication ducts not being built to
specification, failure of the barrier kerbs to comply with
engineering design
specifications and incorrect installation of the
saddles on waterpipes.
9.
In respect of the certification of interim
payment certificates by the second defendant, the plaintiff pleads
that the first defendant
deliberately inflated claims and submitted
claims for work allegedly executed for additional stormwater and
sewerage installations
outside the project site. The plaintiff’s
cause of action against the second defendant is based on breach of
contract by
virtue of the second defendant’s failure to
properly supervise the first defendant’s building work.
According to the
plaintiff, the second defendant was not only aware
of the defective workmanship of the first defendant, but deliberately
failed
to intervene and stop the defective building work
alternatively failed to demand that manifest defective building work
by the first
defendant be remedied forthwith.
10.
The damages in the amount of R 4 948 307.15
claimed by the plaintiff from the first defendant represent the costs
to re-build
the road, the costs to repair the defective work, the
aggregate amount by which interim payment certificates are alleged to
have
been inflated and the amount claimed by the first defendant for
work which did not form part of the project. Payment of this amount
is also claimed from the second defendant on the basis that the
breach of contract of each defendant caused the plaintiff to suffer
damages and that consequently the first and second defendant are
jointly and severally liable to pay the plaintiff the amount claimed.
In the alternative, the plaintiff pleads that the first and second
defendant are jointly liable for it its damages as such damages
arose
as a direct result of the cumulative effect of each defendant’s
breach of contract.
11.
Three grounds of exception were taken in
the second defendant’s notice of exception dated 12 July 2023
but only two were ultimately
advanced at the hearing. Before
considering these grounds, it would be useful to restate some of the
salient principles which apply
to an exception taken on the basis
that a cause of action is legally unsustainable.
Legal principles
12.
The
exception procedure is by design an expeditious procedural mechanism
aimed at sifting out, at an early stage, claims which lack
legal
merit. The bar for an exception to succeed on the basis that a claim
is bad in law, is high. An exception advanced on this
basis may only
succeed w
here
the excipient satisfies the court that the cause of action or
conclusion of law in the pleading cannot be supported on every
interpretation that can be put on the facts.
[1]
On this score and unless they appear to be manifestly false, the
factual averments by the plaintiff must be accepted as correct.
It is
not open to the court to question their efficacy.
[2]
13.
An
overly technical approach to exceptions should not be adopted lest it
destroys the benefits of the exception procedure, which
itself
requires a sensible approach.
[3]
As advised in the oft quoted words of Davis J with Sutton J
concurring in
Kahn
v Stuart
,
in considering an exception, the evaluation of pleadings ‘..
through
a magnifying glass of too high power
’,
is to be avoided.
[4]
14.
To
this must be added two further well established principles relating
to the forensic utility of the exception procedure. The first
is that
an exception to a legally unsustainable cause of action is designed
to dispose of the case in whole or in part by obtaining
a decision on
a point of law and thereby avoid the leading of unnecessary evidence
at the trial.
[5]
The second is
that courts are reluctant to decide on exception questions relating
to the interpretation of a contract or disputes
concerning the terms
of agreements which are disputed, ambiguous or uncertain.
[6]
The first ground of
exception
15.
The plaintiff pleads at paragraph 45 of its
particulars of claim that it was a tacit alternatively a legally
implied term of the
engineering contract that the second defendant
would perform the functions and services of the ‘
Employer’s
Agent
’ as defined and described
in the GCC, in respect of the project.
16.
The first ground of the exception is that
the plaintiff’s reliance on the tacit term pleaded at paragraph
45 of its particulars
of claim is precluded by what the second
defendant describes as a ‘
whole
agreement
clause
’,
embodied by clause 4 of the second defendant’s Standard Terms
of Agreement. This clause states ‘
This
would set out the entire agreement between us
.’
The second defendant contends that it is therefore not open to the
contracting parties to rely on terms such as tacit terms,
which are
not contained in the written contractual documents. Accordingly, the
second defendant contends that insofar as the plaintiff
pleads that
it relies on a tacit term and the breach thereof, the plaintiff’s
cause of action is incomplete and therefore
excipiable.
17.
Having
regard to the factual matrix set out above and in the particulars of
claim, which at the exception stage must be accepted
as correct, one
may immediately think it obvious that it is the second defendant who
falls squarely within the definition of ‘Employer’s
Agent’ as defined in the GCC. After all, who else would fulfill
the functions of the ‘
Employer’s
Agent
’
for the project other than the consulting engineers whose very
appointment was for the purpose of construction supervision
for the
domestic roads and civil engineering services? Indeed, it is that
very obviousness which goes to the nature of a tacit
term. A tacit
term in essence is a term that is so self-evident that is goes
without saying and where it is an actual and not an
imputed tacit
term, it is one which arises ‘…
if
both parties thought about a matter which is pertinent but did not
bother to declare their assent
.’
[7]
18.
Mr.
Coetsee, who appeared on behalf of the second defendant, however
submitted that the terms of the whole agreement clause in the
engineering contract were clear and unambiguous. He contended, based
on
Union
Government (Minister of Railways) v Faux Ltd
[8]
and
Cassim
v Kadir
[9]
,
that reliance on a tacit term is impermissible where the contract is
complete and detailed and needs no addition in the form of
an implied
term. The plaintiff’s reliance on an alleged tacit term, so it
was argued by the second defendant, was therefore
not sustainable in
law. The submission advanced was that whole agreement clause
precluded the plaintiff from relying on tacit terms
which, according
to the second defendant, by their very nature were not contained in
the written contract documents. The argument
is without merit.
An established tacit term, actual or implied, forms a part of and not
a conceptually separate component
divorced from the written contract
itself. As is apparent from
Wilkens
NO v Voges
[10]
,
a tacit term once found to exist, ‘…
is
simply read or blended into the contract: as such, it is contained in
the written deed
.
19.
I
am in any event unpersuaded that the whole agreement clause called in
aid by the second defendant, is dispositive of the tacit
term relied
upon in the plaintiff’s cause of action against the second
defendant. Firstly, the SCA has held that a ‘
whole
agreement
’
or ‘
sole
testimonial
’
clause does not necessarily, of itself, exclude the existence of a
tacit term.
[11]
Secondly, I am
in agreement with the submissions advanced by Mr. Vivier SC, for the
plaintiff, that far from the whole agreement
clause being as clear
and unambiguous as contended by the second defendant, a number of
other provisions of the constituent documents
comprising the
engineering contract, in fact suggest the opposite.
20.
It is apparent in this regard that the
nature and extent of the consulting engineering services to be
performed by the second defendant,
are not detailed and circumscribed
in the component documents which constitute the engineering contract.
Similarly, a determination
of the standards according to which the
second defendant was to perform its services, would by virtue of the
second defendant’s
quote, have to have regard to inter-alia the
requirements of the Saldanha Bay Municipality, ‘relevant SANS
codes’ and
‘relevant good engineering practices.’
21.
The
determination of these aspects would necessarily involve evidence and
a determination by the trial court of the question whether
the words
used in the whole agreement clause, that the Standard Terms of
Agreement ‘…
would
set out the entire agreement between us’,
ought
to bear their ordinary grammatical meaning. It is well established
however that questions concerning the interpretation of
a contract
are not appropriately resolved by way of exception.
[12]
22.
A
further submission was advanced by Mr. Vivier SC that the first
ground of exception would not dispose of the case in either whole
or
part, as the plaintiff would still be able to rely on the same
provision but on the basis that it is a legally implied term
of the
engineering contract. To that extent, so it was argued, the first
exception, if upheld, would not achieve the purpose of
an exception.
That purpose is to avoid the leading of unnecessary evidence at the
trial by disposing of the claim on a point of
law.
[13]
The submission is in my opinion well-founded. It means that upholding
of the second defendant’s exception would make no difference
to
the evidence to be led at the trial as the plaintiff would merely
rely on the same provision which it has pleaded in the alternative
as
a term of the engineering contract implied by law. A term implied by
law is not excluded by a clause stating that the written
contract
constitutes the sole record of the agreement between the parties.
[14]
23.
An exception which fails to expose the
assailed cause of action as being bad in law and which fails to end
the case advanced on
that basis, does not achieve the purpose for
which the procedure was designed. The first ground of exception in my
view falls within
this category.
The second ground of
exception
24.
As to its claim for joint and several
liability in respect of the first and second defendants, as stated
above, the plaintiff pleads
that the damages which it has suffered
were caused individually by the first defendant’s breach of the
building contract
and the second defendant’s breach of the
engineering contract. The plaintiff pleads that although it entered
into separate
and individual contracts with each defendant, it was
the breach of contract by each defendant which caused the plaintiff
to suffer
damages and that consequently the first and second
defendants are jointly and severally liable to pay the amount of R 4
948 307.15
to the plaintiff.
25.
Alternatively, the plaintiff pleads that
the first and second defendants are jointly liable by virtue of its
damages being resulting
from the cumulative effect of each
defendant’s breach of contract.
26.
By its second ground of exception, the
second defendant contends that the claim for joint and several
liability is legally unsustainable
as there is no valid legal basis
for holding the defendants jointly and severally liable for their
respective breaches of separate
contracts. The second defendant
submits that absent an express contractual term to that effect or a
legal principle recognizing
joint and several liability, such claims
against the defendants are excipiable.
27.
The
nature and extent of the duty of an engineer party to a professional
services engineering contract was addressed by the Supreme
Court of
Appeal per Farlam JA in
Van
Immerzeel & Pohl and Another v Samancor
.
[15]
In that case as in the present, the employer had concluded a contract
with a firm of consulting and civil engineers to render professional
services required for the supervision of the installation of works in
terms of a construction contract. The court held that the
engineer
had failed
to
perform its supervisory function in a proper and professional manner
and that it failed to take reasonable steps to ensure that
the
construction work was performed in accordance with the provisions of
the construction contract. In the context of this case,
the following
statement by Farlam JA in
Van
Immerzeel
is in my view apposite with regard to joint liability of a builder
and an engineer for damages caused by virtue of their independent
breaches of contract:
‘…
The
correct position is that the engineer and the firm are independently
liable for the same or similar damage. The plaintiff’s
causes
of action against them are separate and independent based upon two
separate if inter-connected contracts.’
[16]
28.
The
Court went on to quote with approval, as being a correctly reasoned
principle of our law, the following passage from the judgment
of the
Court of Appeal in
Hutchinson
v Harris
[17]
:
‘…
.w
here
the duty of a contracting party is to supervise the work of another
contracting party, it seems to me there is a direct casual
connexion
between the supervisor’s negligent failure to prevent negligent
work, and the damage represented by that negligent
work. No doubt the
builder is also liable. It is a case of concurrent breaches of
contract producing the same damage. In my judgment
the plaintiff has
an action against both, although she cannot obtain damages twice
over.’
29.
The
second defendant’s focus on the separate nature of the two
contracts fails to take into account the inter-connected nature
of
the contracts. This includes the nature of the second defendant’s
obligation in terms of the engineering contract, which
was to
supervise and manage the execution of the works required for the
project. The joint liability of a building contractor for
defective
building work and a professional engineer for failing to detect or
prevent such damage in accordance with his supervisory
functions, has
in my view been established by the principles set out by the SCA in
Van
Immerzeel
.
They are both liable for the same or similar damage resulting
from independent breaches of separate but inter-connected
contracts.
This recognition of liability is in my view consistent with public
policy, constitutional values and the important responsibilities
and
duties of professional engineers, a profession which is itself
subject to statutory regulation.
[18]
30.
The
second defendant’s contention that the law and the contractual
setting pleaded by the plaintiff precludes a claim for
joint and
several liability or joint liability against the defendants, is for
these reasons without merit. The second ground of
exception
accordingly fails as well.
Order
31.
The
second defendant’s exception is dismissed.
32.
The
second defendant is ordered to pay the plaintiff’s costs on
scale C.
-----------------------------
S
G MAGARDIE
Acting
Judge of the High Court
APPEARANCES
For
Plaintiff:
P de B Vivier SC
Instructed
by:
Lucas
Dysel Crouse Inc
For
Second Defendant: D
J Coetsee
Instructed
by:
Everinghams
Inc
Date
of hearing: 3 May 2024
Date
of judgment: 13 August 2024
[1]
Pretorius and Another v Transport Pension Fund and others
2019 (2)
SA 37
(CC) at para 15.
## [2].W
v G.T (867/2021) [2023] ZASCA 23 (13 March 2023) at para 33 to
34.
[2]
.W
v G.T (867/2021) [2023] ZASCA 23 (13 March 2023) at para 33 to
34.
[3]
Telematrix
(Pty) Ltd v Advertising Standards Authority SA
2001 (1) SA 461
(SCA)
at para 3
[4]
Kahn v Stuart
1942 CPD 386.
[5]
Marais v Steyn and Another
1974 (3) SA 479
(T) at 486H-487G.
[6]
Sun Packaging (Pty) Ltd v Vreulink
[1996] ZASCA 73
;
1996 (4) SA 176
(A) at 186J ;
Francis v Sharpe & Others 2004 (3) SA 230 (C) at 237F.
[7]
Wilkens
NO v Voges
[1994] ZASCA 53
;
1994 (3) SA 130
(A) at 136H.
[8]
Union
Government (Railways) v Faux Ltd
1916 AD 105
at p 112.
[9]
Cassim
v Kadir
1962 (2) SA 473
(N) at 475B.
[10]
Wilkens NO v Voges
[1994] ZASCA 53
;
1994 (3) SA 130
(A) at 136H.
[11]
Alfred
McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration
1974 (3) SA 506
(A) at 144, quoted with approval in
Adhu
Investments CC and Others v Padayachee (1410/2016)
[2019] ZASCA 63
(24 May 2019) at para 17.
[12]
Sun
Packaging (Pty) fn 6 above at 186J.
[13]
Marais
v Steyn and Another
1974 (3) SA 479
(T) at 486H-487G.
[14]
Van Nieuwkerk v Mcrae
2007 (5) SA 21
(W) at 28H.
[15]
Van
Immerzeel & Pohl and Another v Samancor
2011 (2) SA 90
(SCA).
[16]
Van
Immerzeel at para 76.
[17]
Hutchinson
v Harris 1978 10 (BLR 19.
[18]
In
terms of the
Engineering Profession Act 46 of 2000
.
sino noindex
make_database footer start
Similar Cases
C.R.W v L.M.W and Another (12866/2014) [2025] ZAWCHC 279 (2 July 2025)
[2025] ZAWCHC 279High Court of South Africa (Western Cape Division)98% similar
L.M.W v C.R.W (12866/2014) [2025] ZAWCHC 395 (1 September 2025)
[2025] ZAWCHC 395High Court of South Africa (Western Cape Division)98% similar
C.B.C NO and Others v L.C (Reasons) (2025/229199) [2026] ZAWCHC 22 (2 February 2026)
[2026] ZAWCHC 22High Court of South Africa (Western Cape Division)98% similar
L.M.M v M.A.L and Others (Reasons) (23156/24) [2025] ZAWCHC 474 (14 May 2025)
[2025] ZAWCHC 474High Court of South Africa (Western Cape Division)98% similar
Webram Four (Pty) Ltd v Transformation Capital Group (Pty) Ltd and Others (7742/2021) [2025] ZAWCHC 390 (27 August 2025)
[2025] ZAWCHC 390High Court of South Africa (Western Cape Division)98% similar