Case Law[2025] ZAGPJHC 824South Africa
Development Bank of Southern Africa v Fusion Guarantees (Pty) Ltd and Another (37332/2018) [2025] ZAGPJHC 824 (26 August 2025)
Headnotes
an amount of R762,852.90 as retention in terms of the Contract. The contract value of the replacement contract to complete the Works was R31,627,823.04. The plaintiff states that it thus suffered damages of R12,237,633.67, being the difference between the replacement contract value of R31,627,823.04 and the available amount of R19,390,189.37. [10] The first defendant opposes the action. Fusion Guarantee claims it never issued the guarantee to the second defendant; therefore, it is not liable to the plaintiff. [11] During the trial, the plaintiff called several witnesses to testify on its behalf. Fusion called its managing director, Mrs. Becker, to testify and support its case.
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2025
>>
[2025] ZAGPJHC 824
|
Noteup
|
LawCite
sino index
## Development Bank of Southern Africa v Fusion Guarantees (Pty) Ltd and Another (37332/2018) [2025] ZAGPJHC 824 (26 August 2025)
Development Bank of Southern Africa v Fusion Guarantees (Pty) Ltd and Another (37332/2018) [2025] ZAGPJHC 824 (26 August 2025)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2025_824.html
sino date 26 August 2025
REPUBLIC OF SOUTH
AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
Case
no.
37332/2018
(1)
REPORTABLE:
NO
(2)
OF INTEREST TO OTHER JUDGES:
NO
(3)
REVISED
:
NO
Date:
26
August
2025
In
the matter between:
DEVELOPMENT
BANK OF SOUTHERN AFRICA
PLAINTIFF
And
FUSION
GUARANTEES (PTY) LTD
1
ST
DEFENDANT
REITY
TRADING ENTERPRISES CC
2
ND
DEFENDANT
Coram
:
Dlamini J
Date
of hearing:
10 April 2025
Delivered
:
26 August 2025 – This judgment was handed down electronically
by circulation to the parties' representatives
via
email, by
being uploaded to
CaseLines,
and by release to SAFLII. The
date and time for hand-down is deemed to be 10:30 in 26 August 2025
JUDGMENT
DLAMINI
J
Introduction
[1]
In this matter, the plaintiff, the
Development Bank of SA (“DBSA”), instituted action
against Fusion Guarantee, the
first defendant (‘Fusion”),
and Reity Trading, the second defendant, claiming payment of R3 370
640.74, from the first
defendant, based on the performance guarantee
issued by the first defendant, and a sum of R 12 237 633. 67 from the
second defendant.
The second defendant has not entered an appearance
to defend. The plaintiff seeks a default judgment against the second
defendant.
Background
[2]
The common cause facts are as follows:-
[3]
On 18 July 2014, the plaintiff awarded a
contract (the Contract) to a joint venture between the second
defendant and an entity called
Phumi HD Construction CC (‘the
Contractor’) for the demolition and additions of the new
administration block, dining
and nutrition center, computer room and
related works at the New Waban Senior Secondary School, in Libode,
Eastern Cape.
[4]
In terms of the aforementioned Contract,
the Contractor was required to secure a performance guarantee on
behalf of the Contractor
in favor of the plaintiff. The Contract
consisted of the following;-
4.1
The Agreement, Contract Data, and the Special Conditions of Contract.
4.2
The General Conditions of Contract, the JBCC Series 2000 Principal
Building Agreement ( Edition
4.1 of March 2005) ( the JBCC).
[5]
It seems that the Contractor was able to
secure a fixed guarantee from the first defendant in favour of the
DBSA as security for
the second defendant’s due fulfillment of
the Contract.
[6]
The plaintiff states that the Contractor
provided a fixed guarantee in terms of Clause 14 of the Contract,
issued by Fusion as security
for the due fulfillment of the Contract.
[7]
It appears that the Contractor struggled
with the timely completion of the scope of the Works. Consequently,
the plaintiff extended
the completion date to 6 August 2015. Despite
this extension, the Contractor failed to meet the revised practical
completion date
of 6 August 2015; therefore, the plaintiff cancelled
the Contract on 10 October 2015.
[8]
After the cancellation of the Contract,
DBSA issued a new tender and appointed a new service provider to
complete the project.
[9]
According to the plaintiff, on the date of
cancellation of the Contract, DBSA avers that it had already paid the
Contractor an amount
of R15,079,071.00 in the form of interim
payments. The balance of the contract value was R18,827,336.47. DBSA
had withheld an amount
of R762,852.90 as retention in terms of the
Contract. The contract value of the replacement contract to complete
the Works was
R31,627,823.04. The plaintiff states that it thus
suffered damages of R12,237,633.67, being the difference between the
replacement
contract value of R31,627,823.04 and the available amount
of R19,390,189.37.
[10]
The first defendant opposes the action.
Fusion Guarantee claims it never issued the guarantee to the second
defendant; therefore,
it is not liable to the plaintiff.
[11]
During the trial, the plaintiff called
several witnesses to testify on its behalf. Fusion called its
managing director, Mrs.
Becker, to testify and support its case.
Mr. Opolot
[12]
The witness testified that he was appointed
by LDM Consulting, a company designated by the plaintiff as the
principal agent on the
Project. He was responsible for engaging with
the Contractor and issuing interim payment certificates. One of his
tasks was to
ensure that the Contractor obtained a guarantee equal to
10 percent of the contract sum before commencing the Works.
[13]
He testified that he initially had
difficulty obtaining the guarantee from the Contractor. However, days
later, he received the
guarantee from the Contractor. He noted that
the guarantee had an expiration date, which, he said, was not
supposed to be included.
He stated that he then engaged Fusion to
remove the expiry date from the guarantee. He mentioned that he later
received the amended
copy of the guarantee directly from Fusion,
incorporating the necessary amendments. He subsequently handed the
amended copy to
DBSA.
[14]
Mr.Opolot advised that, despite being
afforded an extension to complete the Works, the Contractor failed to
complete the project
by the extended practical completion date. The
contract was then canceled, and DBSA appointed another contractor who
ultimately
completed the Works.
Mr. Maome
[15]
DBSA’s legal advisor, Mr. Maome,
testified that he was responsible for initiating and drafting the
Contract and was also present
when the contract was signed by both
the DBSA and the Contractor. He testified that the Contractor handed
him a copy of the Guarantee.
He conceded that he never had sight of
the original Guarantee.
[16]
In summary, the plaintiff’s witnesses
mainly appeared as fair and credible witnesses. They provided
reliable evidence regarding
the events leading up to the signing of
the contract, as well as its subsequent cancellation. In my view,
nothing significant came
out of the cross-examination of the
plaintiff’s witnesses.
[17]
The plaintiff then closed its case.
[18]
The defendant called Ms. Ilse Becker (Ms.
Backer) to testify on its behalf.
Ms. Becker
[19]
Ms. Becker, the general manager of Fusion,
testified about the nature and business of Fusion in the financial
and construction industries.
She explained the company's involvement
in the insurance industry. She testified at length about the events
leading up to the issuance,
signing, and handing over of the copy of
the Guarantee to the Contractor and DBSA. She does not dispute that
there was an engagement
between the Contractor and Fusion wherein the
Contractor sought a Guarantee relating to the construction contract
between DBSA
and the Contractor.
[20]
She confirmed that the Guarantee was
issued, signed, and embossed after the Contractor had paid a sum of R
97 000.00 to Fusion;
however, she speculates that a possibility
exists that the original was retained by Fusion because the
collateral had not been
paid in full by the Contractor.
[21]
Under cross-examination, Backer conceded
that she was not aware that the original Guarantee was never handed
over to the Contractor.
She admitted that she did not know who
cancelled the Guarantee and when the Guarantee was cancelled.
[22]
Overall, Mrs. Backer did not appear to be a
credible witness. Her evidence was, for the most part, misleading and
clearly insufficient.
For instance, it seems most unlikely that,
although she authorized and signed the Guarantee, she testified that
she was initially
unaware that the original Guarantee was never
handed over but was, for unknown reasons, kept at Fusion’s
office. Additionally,
she states that as the manager, she is unsure
who canceled the Guarantee and for what reasons. Significantly, and
more concerning,
she does not know when the Guarantee was canceled.
[23]
The first defendant then closed its case.
Issue for
determination
[24]
Two issues arise in determining this
matter. The first is whether the guarantee was issued at all. The
second is whether the plaintiff
may rely on the guarantee that was
not issued.
Was the guarantee
issued?
[25]
The focus in this regard is whether the
plaintiff’s rights and obligations between the guarantor and
the beneficiary can arise
at all in the absence of the issuing or
delivery of the original guarantee document.
[26]
The parties hold divergent and conflicting
views on how the issues that stand to be determined should be
answered.
[27]
According to DBSA, the determination of
this issue turns primarily on Fusion’s version that it did not
release the original
Guarantee, which is evidenced by its possession
of the original Guarantee with a “cancelled” stamp on the
Guarantee.
[28]
Fusion argues that the determination of
the issue under consideration is a matter of law. According to
Fusion, for a Guarantee to
establish rights and obligations between
the guarantor and beneficiary, the document must be issued and
delivered to the beneficiary.
Absent delivery of the original
document by the guarantor to the beneficiary, so the submission goes,
no transfer of the property
rights in and to the document is
effected.
[29]
Fusion avers that the delivery of the
original document is required for the constitution of an agreement
between itself and the
plaintiff. According to the first defendant,
guarantees are concluded by means of a formal, embossed original
document delivered
to the contractor who then submits it to the
employer, i.e, DBSA.
[30]
Furthermore, Fusion argues that the issue
concerns delivery. This means that, so the argument goes, it denotes
a document that must
be possessed before the party referred to
therein to be obligated to act in a certain way.That absent
possession, the contractor
has no right, and by implication,
the plaintiff also has no right. Therefore, Fusion submits that there
is no evidence that the
plaintiff acquired any rights without
receiving the original document.
[31]
I disagree with Fusion’s argument
in this regard. This is because it is common cause that the document
is a copy of the original.
This means that the document itself, the
signatures thereon, Fusion’s emblem, and embossment are not in
dispute. Therefore,
the only issue for determination is
whether, based on the probabilities, the Guarantee was issued by
Fusion?.
[32]
The
techniques generally employed by our courts in resolving factual
disputes of this nature are trite and are set out by the SCA
in
Stellenbosch
Farmers’ Winery Group
Ltd
and Another v Martell et Cie and Others
.
[1]
In order to determine the disputed issue and come to a conclusion,
the Court must make a finding on (a) the credibility of the
various
factual witnesses, (b) their reliability, and (c) the probabilities.
Finally, in light of its assessment of (a), (b), and
(c), the Court
must determine whether the applicant has succeeded in discharging its
onus.
[33]
The
proper test is not whether a witness is truthful or reliable in all
that he says but whether, on a balance of probabilities,
the
essential features of the story that he tells are true. See.
R
v Kristusamy
.
[2]
Santam
BPK v
Biddulp
.
[3]
[34]
The provision and requirement of the
guarantee is contained in clause 10 of the contract “
The
Tenderer shall deliver the security in terms of clause 14 of the JVCC
within the period stated in the Contract Data and he shall,
immediately after receiving a completed copy of this Agreement,
including the Shedule of Deviations (if any) , contact the Employer’s
agent (whose details are given in the Contract Data) to arrange the
delivery of any bonds, guarantees, proof of insurance and any
other
documentation to be provided in terms of the Conditions of Contract
indentified in the Contact Data, within 14 days of the
date on which
this Agreement comes into effect. Failure to fulfil any of these
obligations in accordance with those terms shall
constitute a
repudiation of this agreement.”
[35]
DBSA submits that this court must consider
the following objective facts. That apart from the fact that the
Guarantee is a copy,
there appears to be no dispute that it was
signed, stamped, and embossed on the same day that the Contractor
made payment of R97,000.00
to Fusion, in respect of an invoice
relating to the Guarantee. That Fusion signed the Guarantee. Fusion
emailed the aforementioned
Guarantee to the Contractor, who then
forwarded a copy of the Guarantee to DBSA. That, the Guarantee
emailed by Fusion to the Contractor
did not have the “cancelled
stamp” on it. The first time Fusion disputed the Guarantee was
after summons was issued.
[36]
DBSA asserts that, when it made a call on
the Guarantee, Fusion did not raise the issue of cancellation of the
Guarantee.
[37]
The plaintiff argues that it is no
coincidence that the Guarantee was prepared, signed, stamped,
embossed, and sent to the Contractor
on the same day the Contractor
paid R97 000.00 to Fusion.
[38]
DBSA asserts that Fusion’s defense
that the Guarantee was never issued based on the existence of the
“cancelled”
stamp should be rejected. This, the plaintiff
argues, is because Ms. Becker does not know who placed the
“cancelled”
stamp on the Guarantee, when it was placed,
or why it was placed. Therefore, the plaintiff insists, there is no
evidence that the
Guarantee was cancelled after it was emailed to the
Contractor.
[39]
The plaintiff submits that in assessing the
probabilities, the only conclusion that can be drawn is that the
Guarantee was not cancelled
as Fusion contends. According to the
plaintiff, the probability exists that the Contractor never collected
the original Guarantee
because it did not need the Guarantee once the
site was handed over, and payments were made after the DBSA received
a copy of the
Guarantee.
[40]
DBSA contends that the evidence of its
witnesses regarding the Guarantee and how they came into possession
of the Guarantee was
not disputed by Fusion, and that it is evident
the Contractor received the Guarantee from Fusion. Consequently, DBSA
argues that
this court should hold that it has discharged its duty of
proving that the Guarantee had been issued by Fusion in favour of
DBSA.
[41]
The first defendant argues that both the
prescribed Guarantee and the prepared Guarantee require the plaintiff
to possess the original.
That the original must be submitted when a
claim is made, and that the rights created by the Guarantee are
inextricably linked
to possessing the original document. Fusion
insists that the Guarantee boldly stipulates, "
Please
note that a claim under this guarantee will only be honored on
submission of the original guarantee document, which bears
the Fusion
embossed seal
.”
[42]
Fusion’s main contention is that it
did not issue the original document referred to by the plaintiff as
the Guarantee, and
as such, no agreement between the DBSA and Fusion
was established.
[43]
Having regard to the pleadings and evidence
presented in this court. The probabilities suggest that Fusion issued
the guarantee.
This is because the Contractor was fully aware that
delivery of the Guarantee was a material and essential requirement of
the agreement,
and the Contractor would not have been allowed to
commence with the Works unless or until it had provided the
Guarantee. The timeline
of events clearly shows that the Contractor
did approach Fusion to secure the Guarantee.
[44]
The indisputable evidence placed before
this court clearly indicates that the Contractor approached Fusion to
secure the Guarantee.
The evidence presented to this court indicates
that the Contractor paid Fusion a sum of R97,000.00 on 11 July 2014.
Soon after
the Contractor made this payment, Fusion prepared the
Guarantee on the same day, and both Mrs. Becker and Mr. Phillips duly
signed
it. Fusion does not dispute that the Guarantee was prepared,
signed, stamped, and embossed on the day Phumi made the above payment
to Fusion.
[45]
It is undisputed that on the same day
Fusion signed the guarantee, a copy was sent to the Contractor and
DBSA.
[46]
A sensible and reasonable conclusion is
that Fusion handed over the Guarantee to the Contractor, who then
passed it over to the
DBSA and/or the Engineer. An unreasonable
conclusion would be that the Guarantee simply grew legs and walked
out of the Fusion
offices and found its way to the Contractor and
DBSA offices.
[47]
In my view, at this stage, the question of
whether the Guarantee was an original or a copy is of no moment. This
is because Fusion,
at the time, knew that it had handed the
Contractor a copy and kept the original for reasons only known to it.
Fusion cannot, on
the one hand, issue a Guarantee, hand a copy to the
Contractor and DBSA, and at the same time keep the original, while
demanding
that DBSA produce the original it kept in its offices
without their knowledge.
[48]
Furthermore, Fusion cannot rely on the
submission that the Pumi did not fulfill the suspensive conditions;
therefore, there is no
valid agreement between Pumi and Fusion, and
by extension, no agreement between Fusion and the Joint Venture, nor
between Fusion
and the DBSA.
[49]
This is because Fusion prepared the
guarantee and handed a copy thereof to Pumi, who then gave the same
to DBSA. No legal duty was
placed upon DBSA to verify whether Fusion
and Phumi had fulfilled all their suspensive conditions. By all
accounts, Fusion does
not deny that it issued and handed a copy to
Phumi.
[50]
Additionally, Mrs. Becker did not dispute
that Fusion prepared the Guarantee. She conceded that, for all
intents and purposes, barring
the fact that it is a copy, the
document is essentially a duplicate of the original.
[51]
Significantly, while Fusion was aware that
it had sent a copy of the Guarantee to DBSA, Fusion does not explain
why it retained
the original after handing the copy to the Contractor
and DBSA. Strangely, Fusion does not know who canceled the Guarantee;
importantly,
Fusion does not explain why it canceled the Guarantee.
Fusion admits that it never notified DBSA or the Contractor about the
cancellation
of the Guarantee.
[52]
Fusion does not inform us when it canceled
the Guarantee. This leaves room for speculation that the Guarantee
was only canceled
after the summons was issued by the plaintiff. I am
satisfied that it is probable that DBSA believed that the Engineer
was in possession
of the original, and on the other hand, the
Engineer believed that DBSA had the original.
[53]
In my view, once Fusion had canceled the
Guarantee, Fusion had a legal duty to advise DBSA that it had now
canceled the guarantee
for whatever reason. This is because, first,
once notified of the cancellation, the DBSA would have been able to
request the Contractor
to provide alternative Guarantees or cancel
the agreement. This Fusion failed to do.
[54]
Fusion is in my view, estopped from relying
on its own misrepresentation that it had issued the Guarantee, whilst
the Guarantee
was lying in its safe and later on unilaterally
canceled by Fusion.
[55]
In light of all the circumstances alluded
to above, the probabilities indicate that Fusion issued the Guarantee
to the Contractor
and DBSA. Consequently, it is the finding of this
court that Fusion issued the Guarantee
Whether DBSA May
Rely on a Guarantee Not Issued
[56]
DBSA argued that it was not a requirement
of the Guarantee that the original document had to be produced for
payment to be made.
That the note cannot be interpreted as absolving
the first defendant from liability under the Guarantee. The plaintiff
maintains
that, once this court determines that the Guarantee was
issued, then in that event, Fusion is liable to DBSA.
[57]
For
these propositions, DBSA seeks reliance on the following decisions:
GLMB
Joint Venture V Constantia Insurance Co Ltd
[4]
Bakubung Platinum Mine (Pty) Ltd v Keletshepile Trading Enterprises
CC and Others
[5]
, and
Millennium Aluminum and Glass Services CC v Group Five Consulting
(Pty) Ltd
[6]
[58]
Fusion contends that in this case, it was
an express term of the Guarantee that it required the original to be
submitted before
payment could be made, and therefore, the use of a
copy was precluded by the Guarantee. As a result, Fusion insists that
the plaintiff’s
reliance on the aforementioned case law is
irrelevant.
[59]
DBSA, reliance on the aforementioned case
law is misplaced, this is because the facts therein are materially
different from those
in the present case. I have already made a
finding and held that the Guarantee was issued by the first
defendant. It follows, therefore,
as it should, that the copy of the
Guarantee is deemed to be the original Guarantee.
The Guarantee
[60]
DBSA argues that the guarantee lapses on
the date of the last Certificate of Completion of Works, not on the
date of cancellation.
The plaintiff insists that Fusion is liable
under the Guarantee for the guaranteed amount, both during the
subsistence of the construction
Contract and after cancellation,
subject to the proviso that the plaintiff has a right of recovery
against the Contractor in terms
of Clause 33.0 of the Contract.
[61]
The plaintiff avers that clause 33.0 is not
confined to recovery during the subsistence of the contract. In sum,
DBSA insists that
the contract between itself and the Contractor was
validly concluded. That, significantly, Ms Backer testified that the
letter
of acceptance by the DBSA to the Contractor was used to
prepare the Guarantee.
[62]
Therefore, DBSA concludes that it has a
right of recovery against the Contractor in the sum of R 6 366 994.93
in terms
of clause 33.0, made up as follows: R 12 237 633.67,
less
R2 500 000 (
claim for additional bulk earthworks )
Less; R 3 370 640
.74 ( value of the Gaurantee)
Accordingly, Fusion is
liable to DBSA in the sum R 3 370 640.74, which is the
value of the Guarantee.
[63]
For
this proposition, the plaintiff relies on the decision
Granbuild
(Pty) Ltd v
Minister
of Transport and Public Works, Western Cape
[7]
(5021/2015)
[2015] ZAWHCH 83 (5 June 2015)
[64]
Fusion denies that it is liable to the
plaintiff in terms of the Guarantee on the basis that it insists it
never issued and delivered
the Guarantee to DBSA
[65]
It is apposite to have regard to the
relevant parts of the Guarantee, which will assist with the
determination of this dispute.
Clause 2 stipulates as follows;
“
The
Guarantor hereby renounces the benefits of the exception non
numeratae pecunia; non causa; debiti; excussionis et divisionis;
and
all other exceptions which could be pleaded against the enforcement
of this guarantee, with the meaning and effect whereof
I declare
myself to be conversant, and undertake to pay the Employer the amount
guaranteed, during the period when the claim was
received by the
Guarantor, on receipt of a written demand from the Employer, or his
delegated official, to do so and which demand
the Employer, or his
delegated official, may make if the Employer has a right of recovery
against the contractor in term of clause
33.0 of the contract”.
[66]
The
principles of interpretation find application in this matter. These
principles were eloquently settled in
Endumeni
[8]
.
There,
the court emphasized that the process of interpretation is a unitary
and objective exercise that gives due regard to the
text, context,
and purpose of the document or instrument being interpreted. Further,
a sensible meaning is to be preferred to the
one that leads to
insensible or unbusinesslike results
[67]
In my view, the Guarantee is
self-explanatory; a sensible interpretation is that Fusion is liable
to DBSA in the sum of R 3 370 640.74.
[68]
Subject to the right of recovery in terms
of clause 33.0. This clause has been eloquently explained by the
court in
Granbulid
as
follows:”[53]…
That the
guarantee should be construed consistently with this machinery is
important for the practical implementation of the guarantee
and for
the protection of the rights of the employer and guarantor. If one
were to hold that “right of recovery” in
the guarantee
refers not to the existence of a payment certificate entitling the
employer to recover a certified amount but to
the notional underlying
contractual right to which a certificate is intended to give effect,
the guarantor would only be obliged
to pay if the underlying
contractual right were established. Put differently, the contractor
would be entitled , even where there
has been a certificate, to go
into the underlying merits. A guarantee on those terms would be
conceivable but unbusinesslike, at
least from the perspective of the
employer and guarantor, who are the immediate parties to the
guarantee.”
[69]
This means, therefore, that the right of
recovery is simply not the existence of the right to claim damages
for breach of contract.
What is rather intended in clause 33.0 is the
payment certificate as issued by the principal agent.
[70]
Having regard to all the circumstances
alluded to above, the plaintiff has established and is entitled to
the order that it seeks.
[71]
Default judgment is granted against the
second defendant.
COSTS
[72]
That trite principle of our law is that
costs must follow suit. I find no reason not to make an order that
costs must follow the
event. Having regard to the quantum of the
claim and the issues raised in the matter, I am of the view that
costs must be awarded
to the plaintiff on the party and party scale
C.
[73]
I therefore make the following order.
ORDER
1.
The first defendant is ordered to pay the
plaintiff the sum of R3 370 640.74, plus interest at the prescribed
rate from the date
of demand, being 14 October 2014, to date of
payment.
2.
Costs of suit on Scale C.
3.
The second defendant is ordered to pay the
plaintiff the sum of R6 366 994.93, plus interest at the prescribed
rate of interest
from the date of issue of the summons until payment
in full.
4.
Costs of suit on Scale C.
DLAMINI J
Judge of the High
Court
Gauteng Division,
Johannesburg
For
the Plaintiff:
Adv L Segeels-Ncube
segeels@advocatesa.co.za
Instructed
by:
CLIFF DEKKER HOFMEYR
INC
Krevania.Pillay@cdhlegal.com
For
the first Defendant
,
Adv. P. Louw S.C
pflouw@law.co.za
gjkotze@counsel.co.za
Instructed
by:
COWAN-HARPER-MADIKIZELA
ATTORNEYS
hkorsten@chmlegal.co.za
[1]
2003 (1) SA 11
CSA at 5
[2]
1945
AD at 556
[3]
2004
(5) SA 586
[4]
(2012/17774)
[2014] ZAGP JHC 440 4
[5]
(560/2016)
[2016] ZANWHC 54
(15 December 2016)
[6]
693/2021)[2022]
ZASCA 180 (14 December 2022
[7]
5021/2015) [2015] ZAWHCH 83 (5 June 2015)
[8]
(920/2010)
[2012] ZASCA 13
sino noindex
make_database footer start
Similar Cases
Development Bank of Southern Africa v Hollard Insurance Company Limited and Another (096485/2023 ; 008205/2024) [2026] ZAGPJHC 30 (15 January 2026)
[2026] ZAGPJHC 30High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Development Bank of Southern Africa Limited v Proline Trading 60 (PTY) Ltd (30282/2020) [2022] ZAGPJHC 639 (5 September 2022)
[2022] ZAGPJHC 639High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Development Bank Of South Africa v Fusion Guarantee (Pty) Ltd and Another (37332/18) [2023] ZAGPJHC 1123 (6 October 2023)
[2023] ZAGPJHC 1123High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Technologies Acceptances Receivables (Pty) Ltd and Another v Thavalerie Travel CC and Another (2022/11927) [2025] ZAGPJHC 573 (10 June 2025)
[2025] ZAGPJHC 573High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Technologies Acceptances Receivables (Pty) Limited and Others v Selebogo Incorporated and Another (2022/001657) [2025] ZAGPJHC 491 (21 May 2025)
[2025] ZAGPJHC 491High Court of South Africa (Gauteng Division, Johannesburg)99% similar