Case Law[2023] ZAGPJHC 1123South Africa
Development Bank Of South Africa v Fusion Guarantee (Pty) Ltd and Another (37332/18) [2023] ZAGPJHC 1123 (6 October 2023)
Headnotes
an amount of R 762 852 90, as retention in terms of the Contract. The contract value of the replacement contract to complete the Works was R 31 627 823.04. The plaintiff says it thus suffered damages of R 12 237 633.67 being the difference between the replacement contract value of R 31 627 823 .04 and the total available amount of R19 390 189.37
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 1123
|
Noteup
|
LawCite
sino index
## Development Bank Of South Africa v Fusion Guarantee (Pty) Ltd and Another (37332/18) [2023] ZAGPJHC 1123 (6 October 2023)
Development Bank Of South Africa v Fusion Guarantee (Pty) Ltd and Another (37332/18) [2023] ZAGPJHC 1123 (6 October 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_1123.html
sino date 6 October 2023
IN THE HIGH COURT OF SOUTH
AFRICA,
GAUTENG
DIVISION, JOHANNESBURG
Case no.
:
37332/18
NOT REPORTABLE
NOT OF INTEREST TO OTHER
JUDGES
REVISED
In the matter between:
DEVELOPMENT
BANK OF SOUTH AFRICA
Plaintiff
And
FUSION GUARANTEE
(PTY) LTD
First
Defendant
REITY TRADING
ENTERPRISE CC.
Second
Defendant
Coram:
Dlamini J
Date of hearing: 16
August 2023
Date of delivery of
judgment: 6 October 2023
The Judgment is deemed to
have been delivered electronically by circulation to the parties’
representatives via email and
the same shall be uploaded onto the
caselines system.
JUDGMENT
DLAMINI J
[1]
This a special plea application brought by
the first defendant against the plaintiff's Particulars of Claim. The
plaintiff, the
Development Bank of SA (“DBSA”) issued
summons against the defendants and claimed payment of the sum of R3
370 640.74.
as against the first defendant (“Fusion”)based
on the performance guarantee issued by the first defendant and a sum
of R 12 237 633. 67 against the second defendant. The second
defendant has not entered an appearance to defend.
BACKGROUND FACTS
[2]
The facts underlying the dispute are
largely common cause.
[3]
On 18 July 2014, the plaintiff awarded a
Contract to a joint venture between the second defendant and an
entity called Phumi HD
Construction CC (‘the Contractor’)
for the demolition and additions of the new administration block,
dining and nutrition
center, computer room and related works to the
New Waban Senior Secondary School, Libode, Eastern Cape.
[4]
In terms of the aforesaid contract, the
Contractor was required to procure and obtain a performance guarantee
on behalf of the Contractor
in favor of the plaintiff. The contract
consisted of the following;
4.1 The Agreement
and Contract Data and the Special Conditions of Contract.
4.2 The General
Conditions of Contract, the JBCC Series 2000 Principal Building
Agreement ( Edition 4.1 of March 2005)
( the JBCC).
[5]
According to the plaintiff, the Contractor
provided a fixed guarantee in terms of clause 14 of the Contract,
issued by Fusion as
security for the due fulfillment of the Contract.
[6]
It is apparent that the Contractor
struggled with the timely completion of the scope of the Works. As a
result, the plaintiff extended
the completion of the works to 6
August 2015. As a result of the Contractor's failure to meet the
revised practical completion
date of 6 August 20215, the plaintiff on
10 October 2015 canceled the Contract.
[7]
After the cancellation of the Contract,
DBSA issued a new tender and appointed a new service provider who
completed the project.
[8]
According to the plaintiff on the date of
cancellation of the Contract, DBSA avers that it had already paid the
Contractor an amount
of R 15 079 071.00 in the form of interim
payments. The balance of the value of the contract was
R18 827 336.47. DBSA
had withheld an amount of R 762 852
90, as retention in terms of the Contract. The contract value of the
replacement contract
to complete the Works was R 31 627 823.04. The
plaintiff says it thus suffered damages of R 12 237 633.67
being the difference
between the replacement contract value of R
31 627 823 .04 and the total available amount of
R19 390 189.37
[9]
Having
filed a notice to defend and a plea, Fusion also filed a special plea
of prescription, alleging that the plaintiff's claim
has been
prescribed in terms of section 11 (d) of the Prescription Act
[1]
("The Act").
[10]
This is so insists Fusion,
because the plaintiffs purported in terms of clause 36 of the written
construction contract to
cancel the contract on or about 5 September
2015. The first defendant submitted that the plaintiff's summons were
served on the
first defendant on or about 11 October 2018 which is
more than three years after the date on which the plaintiff alleges
its claim
arose against the first defendant. claim arose. Therefore
the plaintiff's claim has prescribed.
ISSUE FOR
DETERMINATION
[11]
The issue for determination at this stage
is a very narrow one, the question is when did the DBSA claim arose
against Fusion. The
issue is not whether DBSA has a valid claim
or not against Fusion. That is, whether the plaintiff's particulars
of claim
disclose any cause of action or not against the first
defendant. The determination of this aspect, I submit must be left
and be
adjudicated upon during trial. The numb of the issue between
the parties at this stage concerns the date on which DBSA alleges its
claim arose against Fusion. It is contended by Fusion that the
only debt for which it could be liable arose at the least
after the
extended date of the practical completion on or before 7 August 2015,
whilst the plaintiff insists that the claim arose
on or after the
date of cancellation that is 10 October 2015.
[12]
It is important to point out that at this
stage that we are only concerned with the interpretation of the terms
of clause 11(d)
of the Act.
[13]
The case made by Fusion is that any
potential relevant claim to be made against it must have arisen
before the Contract was
canceled. This is so submit Fusion
because the effect of the cancellation of a contract is in general to
terminate all the
obligations between the parties. Second, is
that Fusion bound itself only to make good the Contractor's
contractual obligations
vis-à-vis the employer. That
cancellation completely extinguishes an obligation and has no
existence after the termination
of the contract.
THE GUARANTEE
RELATIONSHIP
[14]
It is argued on behalf of Fusion that in
this case the Guarantee is conditional, that it is a suretyship that
incorporates the principle
of accessories and does not have the
principle of independence as a feature. Thus only in case of a
principal debt owing by the
Contractor to the Employer being in
existence that the Employer can rely on the Guarantee vis-à-vis
the Guarantor.
CONDITIONAL NATURE OF
LIABILITY
[15]
According to Fusion, the Guarantee was only
given for a very specific and very limited type of obligation by the
Contractor owing
to the Employer, namely a right of recovery against
the contractor in terms of clause 33 of the JBCC. Thus insists Fusion
that
the Employer's claim against the Contractor is for damages
flowing from the cancellation of the Contract and not from the
Contractor's
breach. Therefore the debt against it could thus not
arise upon cancellation. Furthermore, Fusion could be liable for any
debt
by reference to clause 33 and that such debt has prescribed.
[16]
Accordingly, Fusion submits that the
plaintiff's claim has prescribed in terms of section 11 of the Act,
since the summons was served
on 11 October 2018, which, the defendant
insists is more than three years after the date on which the DBSA’s
claim against
Fusion arose.
[17]
In sum, DBSA contends that the first
defendant has not challenged its allegation that its debt against
Fusion and the second defendant
arose on or after 10 October 2015,
when DBSA canceled the contract. The plaintiff avers that
Fusion challenges the merits
of the DBSA's claim, not when the debt
arose. DBSA submits that this issue is not a matter that this Court
can adjudicate upon
at the prescription stage. That at the
prescription stage, it must be accepted as it should, that the DBSA's
claim as pleaded is
valid, the issue being when the debts arose and
not if the debt is valid as against the defendants. I agree with the
plaintiff’s
submission in this regard.
[18]
It is apposite at the stage to look at
section 11 (d) of the Act. It stipulates as follows:
The periods of
prescription of debts shall be the following:
(d) save where an Act
of Parliament provides otherwise, thee years in respect of any other
debt.
[19]
The
principle of interpretation of statutes is now well established and
has been repeated in numerous judgments of our courts. A
sensible
meaning is to be preferred to one that leads to insensible or
unbusinesslike results or undermines the apparent purpose
of the
document. This process, it should be emphasised entails a
simultaneous consideration of having regard to the context, the
document as a whole, and the circumstances attendant upon its coming
into existence. See
Natal
Joint Municipal Pension Fund v
Endumeni
Municipality
.
[2]
[20]
A sensible and business interpretation of
the Act means that any plaintiff who avers that it has a claim
against any defendant must
issue and serve summons within three years
against that defendant. The Act is not concerned about the validity
or otherwise of
the plaintiff's claim. The plaintiff insists that its
claim against Fusion arose on 10 October 2015 and that it
issued served
summons upon the first defendant on 11 October 2018.
[21]
In my view, once Fusion has conceded as it
has done in this case that DBSA cancelled the contract on 10 October
2015 and Fusion
concedes that the summons was issued and served on
them on 11 October 2018. The logical conclusion is that the summons
were validly
issued and served on Fusion within three years as
prescribed by the Act. This therefore means that DBSA’s claim
is valid
and was issued and served within the statutory limits as
required by the Act.
[22]
In light of the foregoing, this must be the
end of this inquiry. In any event, Fusion is entitled to pursue the
rest of its complaints
against the plaintiff's particulars of claim
either through an exception or during trial. The Act is clear and
unambiguous, it
only requires the plaintiff to issue its claim within
three years from the date within which the claim arose. The Act is
not concerned
about the validity or otherwise of the plaintiff's
claim.
[23]
In all the circumstances that I have
mentioned above I am not satisfied that Fusion has discharged the
onus that rested on its shoulders
to prove that the plaintiff’s
claim has prescribed.
ORDER
1.
The defendant’s special
plea application of prescription is dismissed with costs.
DLAMINI J
JUDGE OF THE HIGH COURT
OF SOUTH AFRICA
GAUTENG DIVISION,
JOHANNESBURG
Date of hearing: 16
August 2023
Delivered: 6
October 2023
For
the Plaintiffs:
Adv L Segeels-Ncube
segeels@advocatesa.co.za
Instructed by:
CLIFF DEKKER HOFMEYR INC
Krevania.Pillay@cdhlegal.com
For the first
Defendant
:
Adv. P. Louw S.C
pflouw@law.co.za
gjkotze@counsel.co.za
Instructed by:
COWAN-HARPER-MADIKIZELA
ATTORNEYS
hkorsten@chmlegal.co.za
[1]
The
Prescription Act, Act 68 of 1969.
[2]
[
2012] ZASCA 13
;
2012 (4) SA 593
(SCA).
sino noindex
make_database footer start
Similar Cases
Development Bank of Southern Africa v Fusion Guarantees (Pty) Ltd and Another (37332/2018) [2025] ZAGPJHC 824 (26 August 2025)
[2025] ZAGPJHC 824High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Development Bank of Southern Africa Limited v Proline Trading 60 (PTY) Ltd (30282/2020) [2022] ZAGPJHC 639 (5 September 2022)
[2022] ZAGPJHC 639High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Development Bank of Southern Africa v Hollard Insurance Company Limited and Another (096485/2023 ; 008205/2024) [2026] ZAGPJHC 30 (15 January 2026)
[2026] ZAGPJHC 30High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Communication Genetics (Pty) Ltd v Schonenberger and Another (025959/2025) [2025] ZAGPJHC 338 (2 April 2025)
[2025] ZAGPJHC 338High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Various parties obo minors v Anglo-American South Africa Limited and Others (2020/32777) [2023] ZAGPJHC 1474 (14 December 2023)
[2023] ZAGPJHC 1474High Court of South Africa (Gauteng Division, Johannesburg)99% similar