Case Law[2024] ZAGPJHC 1100South Africa
Kwagga Holdings (Pty) Ltd v Member of Executive Council for Roads and Transport of Gauteng Provincial and Others (6577/20219) [2024] ZAGPJHC 1100 (25 October 2024)
High Court of South Africa (Gauteng Division, Johannesburg)
25 October 2024
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2024
>>
[2024] ZAGPJHC 1100
|
Noteup
|
LawCite
sino index
## Kwagga Holdings (Pty) Ltd v Member of Executive Council for Roads and Transport of Gauteng Provincial and Others (6577/20219) [2024] ZAGPJHC 1100 (25 October 2024)
Kwagga Holdings (Pty) Ltd v Member of Executive Council for Roads and Transport of Gauteng Provincial and Others (6577/20219) [2024] ZAGPJHC 1100 (25 October 2024)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2024_1100.html
sino date 25 October 2024
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
(1)
Reportable NO
(2)
Of Interest To Other Judges NO
(3)
Revised
CASE
NUMBER : 6577/2019
In
the matter between:
KWAGGA
HOLDINGS (PTY) LTD
Applicant
and
THE
MEMBER OF THE EXECUTIVE COUNCIL FOR ROADS AND TRANSPORT OF THE
GAUTENG PROVINCIAL GOVERNMENT
1
st
Respondent
THE
GAUTENG DEPARTMENT OF ROADS AND TRANSPORT
2
nd
Respondent
ADV
GHANDI BADELA N.O.
3
rd
Respondent
CASE
NUMBER : 40523/2019
In
the matter between:
TALEDI
MOROSI BUILDING CONSTRUCTION CC
Applicant
and
THE
MEMBER OF THE EXECUTIVE COUNCIL FOR ROADS AND TRANSPORT OF THE
GAUTENG PROVINCIAL GOVERNMENT
1
st
Respondent
THE
GAUTENG DEPARTMENT OF ROADS AND TRANSPORT
2
nd
Respondent
ADV
GHANDI BADELA N.O.
3
rd
Respondent
CASE
NUMBER : 11460/2022
In
the matter between:
CATAGRICT
IMPRIMERE (PTY) LTD
1
st
Applicant
MAFUBE
ENGINEERING SERVICES CC
2
nd
Applicant
BASIC
BLUE TRADING 689 CC
3
rd
Applicant
And
ADV
GHANDI BADELA N.O.
1
st
Respondent
THE
MEMBER OF THE EXECUTIVE COUNCIL FOR
ROADS
AND TRANSPORT OF THE GAUTENG PROVINCIAL GOVERNMENT
2
nd
Respondent
THE
GAUTENG DEPARTMENT OF ROADS
AND
TRANSPORT
3
rd
Respondent
CASE
NUMBER : 23359/2022
In
the matter between:
KOPANO
KOFIFI PROJECTS CC
Applicant
And
THE
MEMBER OF THE EXECUTIVE COUNCIL FOR ROADS AND TRANSPORT OF THE
GAUTENG PROVINCIAL GOVERNMENT
1
st
Respondent
THE
GAUTENG DEPARTMENT OF ROADS AND TRANSPORT
2
nd
Respondent
ADV
GHANDI BADELA N.O.
3
rd
Respondent
JUDGMENT
VAN
DER BERG AJ
[1]
The applicants in these four applications
concluded agreements with the Department of Roads and Transport,
Gauteng (“
the Department”
)
in terms of which the applicants were to perform road maintenance in
the Gauteng Province. Disputes arose between these applicants
and the
Department. The disputes were referred to adjudication under
circumstances explained below.
[2]
The six applicants (three applicants joined
in the one application) were joined as claimants before the
adjudicator. The adjudicator
dismissed all their claims.
[3]
These are applications to set aside the
award of the adjudicator. The applicants (in at least three of the
applications) ask that
his award be substituted with an order for
payment of a specific amount.
[4]
The MEC for Roads and Transport of the
Gauteng Provincial Government is cited as a respondent in all the
applications. I refer to
the MEC and the Department collectively as
“
the respondents”
.
The adjudicator (“
the adjudicator
”
or “
Adv Badela
”
to distinguish him from a previous adjudicator) is cited as a
respondent and abides the decision of the court.
[5]
I shall refer to the six applicants jointly
as “
the claimants
”
as in the adjudicator proceedings. The particulars of the
applicants/claimants and applications and how they will be referred
to are: Kwagga Holdings (Pty) Ltd (Case no 6577/2019) (“
Kwagga”
);
Taledi Morosi Building Construction CC (Case no 40523/2023)
(“
Taledi”
);
Catagrict Impremere (Pty) Ltd, Mafube Engineering Services, and Basic
Blue Trading 69 CC (Case no: 11460/2022) (“
Catagrict”
,
“
Mafube”
and “
Basic Blue”
);
Kopano Kofifi Projects CC (Case no 23359/2022) (“
Kopano
Kofifi”
).
[6]
By agreement between the parties and by
directive of the Deputy Judge President the four applications were
heard together. The applications
were heard over two days in two
separate motion court weeks.
[7]
I intimated at the hearing that I would
hand down four separate judgments. I have since decided to hand down
one judgment. It would
lead to unnecessary repetition to hand down
four judgments where most of issues are common to all the
applications. Where the same
adjudication award is sought to be set
aside it would be illogical to hand down separate judgments. I shall
however cater for the
differences between the applications in the
judgment.
[8]
Issues (factual and legal) which are common
to all the applications will first be dealt with. It is necessary to
determine whether
the adjudicator’s award is reviewable and
whether the claimants could bring reconsideration applications in
terms of the
NEC contract. Thereafter the individual applications are
discussed.
#
# EARLY
HISTORY AND APPOINTMENT OF ADJUDICATOR
EARLY
HISTORY AND APPOINTMENT OF ADJUDICATOR
[9]
It is relevant to explain how Adv Badela
was appointed as adjudicator, as it has a bearing on the submission
that he exceeded his
powers. On the early history of the matter and
the appointment of the adjudicator I follow the respondents’
version as set
out in the answering affidavit in the various
applications as these facts have not been disputed.
[10]
On 28 September 2008, the Department
appointed sixty-nine (69) contractors (including the claimants) to
perform routine road maintenance
of Gauteng Provincial Roads. The
appointment of the contractors was done after a competitive
procurement process. Subsequently,
during December 2008, the
Department and each of the claimants concluded NEC 3 contracts to
perform routine road maintenance for
a specified region in Gauteng
(“
the NEC 3 Contract”
).
[11]
I shall set out some of the relevant terms
of the NEC 3 Contract below. For current purposes it is relevant to
note that Mr Lloyd
Mogotsi (“
Mr
Mogotsi”
) was appointed by the
parties as the adjudicator in terms of the contract data which formed
part of all their contracts.
[12]
During March 2010 the Department and each
of the claimants concluded an addendum to the main contract (“
the
first addendum
”). In terms of the
first addendum the fixed contract amount fell away and all work was
done according to a “signed
works order with quantities and
rates”.
[13]
In March 2012 the Department and each of
the claimants concluded a second addendum to the main contract. It
inter alia
amended the contract to be effective from 1 April 2011 and to
terminate on 31 March 2013.
[14]
Both the first and second addenda form part
of the contractual relationships between the Department and the
claimants.
[15]
On or about 25 June 2013, the six claimants
referred the disputes that had arisen between them and the Department
to adjudication.
Mr Mogotsi, who had been appointed as adjudicator in
all these disputes, did not finalise the adjudication within the
timeframes
stipulated in the contracts or at all. (This is disputed
by some of the claimants and dealt with below.)
[16]
During 2019 the six claimants –
dissatisfied with the failure of Mr Mogotsi to finalise the
contractual claims submitted to
him – approached the High Court
for relief under case number 6577/19. The six claimants’ claims
before the High Court
were based purely on an alleged breach of
contract by the Department. The six claimants sought payment in the
combined amount of
R102 008 389.99.
[17]
The claimants did not claim for the
enforcement of any award.
[18]
The
matter became before Yacoob J who on 7 November 2019 made the
following order (“
the
Yacoob J 2019 order”
[1]
):
“
1.1
The application is postponed sine die.
1.2
The applicants have tendered to pay the first and second respondents
(“the respondents”) wasted costs of the
application for the set down of the matter on 7 November 2019, from
29 April
2019.
1.3
By no later than Friday 15 November 2019, the parties’
respective attorneys shall each furnish to the other, a list
of three
names, of persons to act as the adjudicator, in the place and stead
of the third respondent, in terms of clause W.1.1
of the NEC contract
concluded between the parties (“the NEC contract”).
1.4
By no later than Friday 22 November 2019, the parties shall agree on
the identity of the nominated adjudicator. Failing
such agreement, by
no later than Tuesday 26 November 2019, the Chairman of the
Johannesburg Society of Advocates shall appoint
the adjudicator from
one of the six names submitted.
1.5
The claims forming the subject-matter of the application shall be
referred to the adjudicator, who shall commence his/her
adjudication
by no later than 31 January 2020 and conclude same within the time
periods provided for in the NEC contract.
1.6
The parties shall be entitled to raise all arguments in relation to
the adjudication process before the adjudicator and
all the parties’
rights in relation to the NEC contract in general and the
adjudication in particular, are strictly reserved.
1.7
A rule nisi shall issue, calling upon the adjudicator
[Mr
Mogotsi]
to show cause by no later than 25 November 2019, why
and order should not be granted, directing the third respondent, in
respect
of the failed adjudication process to:
1.7.1
Refund by no later than 2 December 2019, all adjudication fees paid
by the applicants to adjudicator in May 2018;
1.7.2
pay mora interest on amount to be refunded, reckoned from the date
when the funds were paid by the applicants, to the date
when the
refund is received by the applicants;
1.7.3
return to the applicants by no later than 2 December 2019, all their
claim records and all other records of the failed adjudication
proceedings.”
[19]
Adv Badela was appointed as the adjudicator
pursuant to the Yacoob J 2019 order. After the exchange of pleadings
and submissions,
Adv Badela delivered an adjudication award which was
dated 17 August 2020. He dismissed all the claimants’ claims. I
return
to the award below.
#
# PREVIOUS
DETERMINATIONS AND HIGH COURT CASES
PREVIOUS
DETERMINATIONS AND HIGH COURT CASES
[20]
Some of the claimants referred –
either in their heads or their founding affidavits – to High
Court cases where awards
of Mr Mogotsi have been upheld.
[21]
By way of example (other claimants made
similar submissions), in its founding affidavit Taledi refers to
these High Court cases
and makes the following submission:
“
I
submit that all the facts, disputes and defences of the first and
second respondents have been comprehensively covered by no less
than
5 judgments of the above Honourable Court.
These
judgments have determined all the issued and defences between the
parties and this Honourable Court have found for other contractors
in
the same position as the applicants and all 4 (sic) judgments were in
favour of the applicants.
”
(sic)
[22]
Taledi then submits in its heads of
argument that the adjudicator “
ventured
outside the scope of the enquiry that was referred to him and
disregarded five judgments of the above Honourable Court,
which
already dealt with the dispute and defences raised by the First and
Second Respondents
” and that
these High Court cases constitute binding precedent.
[23]
I
disagree. There is no evidence of what facts served before
Mr
Mogotsi in those matters. Factual findings in one case do not bind
another court.
[2]
I
could not find any
legal
principle enunciated in any of those cases which supports the
claimants’ case, and I was not referred to any. The adjudicator
(if he was made aware of these judgments) would for the same reason
also not have been bound by these judgments.
[24]
In addition, Mr Mogotsi may have erred which would not
necessarily have rendered his awards reviewable due to the narrow
basis on
which awards are reviewable (see below).
#
# SCOPE
OF THE ADV BADELA’S POWERS
SCOPE
OF THE ADV BADELA’S POWERS
[25]
Taledi contends that the
“initial adjudicator” (this is a reference to Mr
Mogotsi) has determined all the disputes
before him and all that was
required of the adjudicator was a quantification of the amount due to
the applicant. Taledi further
submitted that the scope of Adv
Badela’s enquiry was limited to issues “
undecided
by the initial adjudicator, and he was certainly not
entitled to consider disputes de novo, ignoring
the initial adjudicator's
award
.”
Kopano Kofifi avers that Adv Badela’s “
re-assessed
the merits of the initial dispute, an aspect that falls within the
purview of the initial adjudicator
”
and that he thereby exceeded his powers. Kwagga makes the same
submission but also refers to an alleged earlier award made
by Mr
Mogotsi, which will be dealt with below.
[26]
There is absolutely no factual basis for
these contentions and they fly in the face of the undisputed
evidence:
[26.1]
At the time when the Yacoob J 2009 order
was made Mr Mogotsi had not made published any award. It must be
borne in mind that Mr
Mogotsi was joined as a respondent in the
proceedings before Yacoob J. As pointed out by the respondents, and
shown above, the
claimants approached the High Court on the basis
that Mr Mogotsi had not made any award.
[26.2]
Also damning for the claimants is the fact
that in the proceedings before Adv Badela the six claimants filed a
statement of claim,
a replication and written submissions. It was not
the case presented to the adjudicator that he only had to determine
the “
final figures”
.
For example the claimants
inter alia
stated the following in the adjudication proceedings:
[26.2.1]
The proceedings before Mr Mogotsi were
referred to as “
the failed
adjudication proceedings”
(paragraph 30 of the statement of claim);
[26.2.2]
Reference was made to the “
termination
of the mandate of Mr Mogotsi”
(paragraph 100 of the replicating statement);
[26.2.3]
“
Mr Mogotsi refused to attend to
the adjudication proceedings pending payment of his adjudication
fees.”
(Claimants’ heads of
argument, paragraph 31);
[26.2.4]
“
This [Mr Mogotsi’s failure
to adjudicate the dispute] let the claimants to refer the outstanding
dispute to the High Court
for a decision in terms of W1.4 of the
contract.”
(Claimants’
heads of argument, paragraph 35).
[27]
Accordingly, the claimants’ challenge
to the adjudicator’s award on the basis that he exceeded his
powers must fail.
# NEC
3 CONTRACT: DISPUTE RESOLUTION
NEC
3 CONTRACT: DISPUTE RESOLUTION
[28]
The NEC 3 Contract contains the following
provisions dealing with dispute resolution, the adjudicator’s
powers and how the
adjudicator’s decision can be revised:
[28.1]
Any dispute arising under or in connection
with the contract has to be referred to and decided by the
adjudicator (clause W1.1);
[28.2]
The adjudicator acts impartially and
decides the dispute as an independent adjudicator and not as an
arbitrator (clause W1.2(2));
[28.3]
The adjudicator has the power to decide a
dispute referred to his/her predecessor but not decided at the time
when the predecessor
resigned or became unable to act (clause
W1.2(4));
[28.4]
The adjudicator decides the dispute and
notifies the parties of his decision within four weeks of the end of
the period of receiving
information from a party referring the
dispute (clause W1.3(8));
[28.5]
Clause W1.3(10) of the NEC 3 Contract
provides:
The
Adjudicator’s
decision is binding on the Parties unless and until it is revised by
the tribunal
and is enforceable
as a matter of contractual obligation between the parties and not as
an arbitral award
.
The
Adjudicator’s decision is final and binding if neither Party
has notified the other within the times required by this
contract
that he is dissatisfied with a decision of the Adjudicator and
intends to refer the matter to the tribunal
.”
(Own emphasis)
[28.6]
Clause W1.4 of the NEC 3 Contract provides
in relevant part:
“
(
2)
If, after the Adjudicator notifies his decision a Party is
dissatisfied, he may notify the other Party that he intends
to refer
it to the tribunal.
A Party may
not refer a dispute to the tribunal unless this notification is given
within four weeks of notification of the Adjudicator’s
decision
…
(4)
The tribunal settles the dispute referred to it. The
tribunal
has the powers to reconsider any decision of the Adjudicator
and review and revise any action or inaction of the Service Manager
related to the dispute.
A Party is not limited in the
tribunal proceedings to the information, evidence or arguments put to
the Adjudicator
.”
(Own emphasis)
[28.7]
The “
tribunal
”
is defined as “
a South African
court of law”.
#
# REVIEWABILITY
OF ARBITRATOR’S AWARD
REVIEWABILITY
OF ARBITRATOR’S AWARD
[29]
In
Framatome
v Eskom
[3]
the
Supreme Court of Appeal (per Mathopo JA) referred to the same clause
W1.3(10) in the NEC3 contract and found that “
arbitration
is the appropriate forum”
.
[4]
In that matter the “
tribunal”
was defined as arbitration, whereas in this instance the “
tribunal
”
is defined as “
a
South African court of law
.”
It is clear from this judgment that the court cannot be approached
outside the provisions of clause W1.3(10) and W1.4.
[30]
Mathopo JA continued:
“
[29]
In the final analysis, the question to be asked is whether the
adjudicator's determination is binding on the parties. The answer
to
that question turns on whether the adjudicator confined himself to a
determination of the issues that were put before him by
the parties.
If he did so, then the parties are bound by his determination,
notwithstanding that he may have fallen into error.”
[31]
A
court will only interfere with an adjudication where the adjudicator
has acted in excess of his jurisdiction or mandate, or in
serious
breach of the rules of natural justice. A court will not examine the
merits of the award.
[5]
[32]
I have already rejected the claimants’
submissions that the adjudicator exceeded his mandate.
[33]
No case has been made out that the
adjudicator breached the rules of natural justice.
[33.1]
Some of the claimants submitted that
adjudicator acted with bias, fretted his discretion, took irrelevant
considerations into account,
and acted arbitrarily or capriciously.
Very few factual averments are made in support of these alleged
grounds of review.
[33.2]
The adjudicator gave a well-reasoned
determination. He also considered a number of the respondent’s
defences, i.e. prescription
and that the disputes have been settled,
and dismissed these defences.
[34]
The other so-called “grounds of
review” are merely allegations of errors committed by the
adjudicator on the merits
and do not fall within the ambit of
instances which render an adjudicator award reviewable.
RECONSIDERATION
APPLICATION
[35]
In
terms of clause W1.4 of the NEC contract the tribunal (here the
court) can reconsider the adjudicator’s award. As pointed
out
by Yacoob J,
[6]
clause W1.4(4)
grants the aggrieved party an “
appeal
in the wide sense”
.
That means it is a complete rehearing and a fresh determination on
the merits of the matter with or without additional evidence
or
information. It corresponds with the first category of “appeal”
set out in
Tikly
v Johannes N.O
.
[7]
[36]
The claimants therefore had the opportunity
to have presented evidence on aspects where it fell short before the
adjudicator. They
all however failed to do so.
##
## Delay
Delay
[37]
Clause W1.4(2) expressly states that the
matter may not be referred to the “
tribunal”
(in this instance a court of law) unless a notification was given to
the other parties of the intention to do so within four weeks
of the
date of which the adjudicator notified his decision.
[38]
Whereas a court has a discretion to
consider a legality review or a review in terms of
Promotion
of Administrative Justice Act, 3 of 2000 (“PAJA”)
where
an applicant delayed in bringing it, a court has no discretion to
consider an application to reconsider the adjudicator’s
award
in terms of clause W1.4(4) where notification has not been given
timeously. It is a contractual term which is binding on
the parties.
[39]
Kwagga and Taledi have not given
notification to the other parties of the intention to refer the
matter to court (i.e. the tribunal)
within four weeks of the date of
which the adjudicator notified his decision. They have thus not met
the jurisdictional requirement
for reliance on clause W1.4(4).
ADV
BADELA’S AWARD
[40]
The adjudicator dismissed the claimants’
claims, and
inter alia
held:
[40.1]
the claimants had referred their
contractual claims for adjudication outside the timeframes prescribed
in clause W1 of the NEC 3
Contract;
[40.2]
the time-bar provisions of the NEC 3
Contract are not contrary to public policy and the Constitution of
the Republic of South Africa,
1996;
[40.3]
the contractors had failed to substantiate
their contractual claims;
[40.4]
the contractors failed to produce invoices
which reflected the amounts claimed or at all;
[40.5]
the claims were formulated to be for works
completed when in fact no works had been executed;
[40.6]
the amounts claimed had not been certified
and signed by the consulting engineers as required in terms of the
NEC 3 Contract.
[41]
I now briefly deal with some of these
findings.
##
## Time
Bar
Time
Bar
[42]
Clause W1.3 sets out in an adjudication
table when disputes are to be notified. In four instances a time
period is provided when
notification of the dispute must be given,
and how long after that it must be referred to the adjudicator.
However, the dispute
in this matter falls under “
any
other matter”
in the adjudication
table and the clause providing when a dispute must be referred to the
Adjudicator reads:
“
Between
two and four weeks after notification of the dispute to the other
party and the service manager.”
[43]
There is no provision as to when
notification must be given. The adjudicator upheld the Department’s
defence based on the
time bar on the basis that a dispute was
referred to the adjudicator more than four weeks after the dispute
arose. The date of
the dispute is however not the date when the
“
clock starts ticking”
.
[44]
The claimants argued that they did not have
to give notification at all, and this became an issue in the
adjudication. The claimants
also argued that the time clause had been
waived as there were settlement discussions which took some time
before the disputes
were referred to adjudication (before Mr
Mogotsi).
[45]
The fact that the adjudicator may have
erred in this regard does not avail the claimants and is not an issue
I have to decide.
[46]
Firstly, the adjudicator also dismissed
claimants’ claims on the merits. The finding on the time bar
was thus not determinative
to his ultimate award. (Taledi’s
statement in its supplementary affidavit that the adjudicator
dismissed the claims only
on the basis of the time bar is patently
false.)
[47]
Secondly, this would not be the type of
error which is reviewable.
## Merits:
No certification, lack of evidence, fees for no work done
Merits:
No certification, lack of evidence, fees for no work done
[48]
The adjudicator carefully considered the
claimants’ claims, and
inter alia
made the following findings on the merits:
“
69
Clause Part C1.2 (51.2) provides that amounts on which interest is
payable are those amounts that were
due
and certified by the RMPT
[Road
Maintenance Professional Team]
which
the employer failed to pay within 4 (four) weeks. The said amounts
must not only be due but must also have been certified
by the RMPT.
The claimants have not alleged that the amounts forming part of the
dispute have been certified by the RMPT.”
(The
adjudicator’s emphasis.)
”
“
75
The 1
st
addendum neither guaranteed a minimum number of work orders nor
minimum value amount for work to be done in a month or for the
remainder of the contract between the parties.”
77
The Claimants submitted annexures “C1” to “C6”
as quantification of amounts claimed by the claimants.
The
quantification of claims in these annexures is not supported by
relevant documentation. Further, the said amounts have not
been
certified by the RMPT as required in terms of the NEC3 contract.”
“
79
The contract between the parties at clause Part C1.2(Z3) provides
that in order for a claimant to be entitled to payment
‘The
contractor submits his payment certificate which includes an original
tax invoice to the RMPT for certification. The
certification should
be done within twenty-four hours, and submitted to the Project
Manager for approval in terms of cluse 51.1
of NEC3 contract. The
contractor must submit his valid tax certificate, original tax
invoice, vender number and an original certificate
signed by the RMPT
within the time required”
“
80
The Claimants did not submit, in these proceedings, any tax
certificate, tax invoice, vender number and a certificate signed
by
the RMPT to substantiate both their entitlement and claims.”
“
113
The Claimants failed to state the contractual terms they rely on for
alleged rights to guaranteed minimum works orders.
The terms of both
the 1
st
and 2
nd
addenda replaced guaranteed contract value with works orders with
bills of quantities and rates. There is not term in both the
1
st
and 2
nd
addenda that guarantees a number of works order that must be issued
by the 2
nd
Respondent to each Claimant.”
“
118
The Claimants’ claims, except for alleged unpaid invoices, were
formulated as though the Claimants executed works
and incurred
expenses yet no works were executed. In this case the claimants did
not execute any work under the new regime introduced
by the 1
st
and 2
nd
addenda. Yet, in reality the claim should have been for damages (loss
of profit) as a result of alleged contractual breach.”
[49]
These findings are unassailable and
justified on the material furnished by the claimants to the
adjudicator. These shortcomings
in the claimants’ case have not
been addressed in the applications in the High Court.
LACK
OF CERTIFICATION
[50]
Kwagga and Taledi submit that certification
by the RMPT was no longer necessary due to an amendment in the second
addendum. The
second addendum however amended clause 14 of part C3.1,
which provides that the RMPT was entitled to make any variations for
the
quality or quantity of the work and deals with additional works
or compensation events. In the second addendum “the RMPT”
was merely replaced with “the employer”. The
certification clause contained in part C1.2, clause 51.2 has not been
amended in the second addendum.
[51]
In
the absence of certification, the claimants’ claims are
unliquidated
claims for damages which must be pursued by the institution
of an action. Motion proceedings are unsuited
to the prosecution
of claims for unliquidated damages.
[8]
#
# CLAIM
FOR WORK NOT RENDERED
CLAIM
FOR WORK NOT RENDERED
[52]
All the claimants claim for work not
actually rendered. The adjudicator correctly found that there is no
clause that provides for
such a claim.
[53]
Kopano Kofifi also relies on a letter from the Department and
argues that there was an implied provision in the MEC Contract that
the contractors were entitled to monthly work order. The letter
reads:
“
The
Department of Road and Transport offers this contract on the basis of
a 100 km work schedule, wherein the work will be allocated
according
to the monthly issued works order.”
[54]
Catagrict, Mafube and Basic Blue refer to a
letter addressed by the respondents where they said that they had not
issued any work
orders due to budgetary constraints.
[55]
These letters do not form part of the
written contracts and are excluded in terms of the parol evidence
rule. In any event, these
letters do not support an interpretation
that contractors can charge for work not rendered.
[56]
Catagrict, Mafube and Basic Blue further
rely on the first addendum which provides that
“
all
work would be done according to a signed works order with quantities
and rates”
. This term does not support the submission that
they ca claim for work not done.
[57]
Insofar
as the claimants rely on a tacit term, they face a number of
problems:
[9]
[57.1]
A tacit term was not pleaded.
[57.2]
It is incumbent on a party relying on an
alleged tacit term to formulate the tacit term. The applicant has
failed to do so.
[57.3]
There can be no tacit term contrary to an
express term. The references to work orders make it quite clear that
payment can only
take place in respect of work orders issued by the
Department.
[57.4]
The claimants have not shown that a tacit
term is required to give business efficacy to the agreement.
#
# KWAGGA
KWAGGA
Mogotsi
Kwagga Award
[58]
Kwagga avers that Mr Mogotsi did make an
award in its dispute with Department (“
the
Mogotsi Kwagga Award
”). Kwagga
contends that all that was required of the adjudicator (Adv Badela)
was to have examined the final figures of the
“initial
adjudication”. Kwagga then submits that Adv Badela exceeded his
powers by making an award on the merits. As
shown above, this was not
the case presented to Adv Badela.
[59]
Kwagga however goes further and seeks an
order that the so-called “
initial
adjudication”
be declared final
and binding and enforceable.
[60]
A copy of the (purported) award did not
form part of the court record. An attempt to upload it to CaseLines
during the hearing was
opposed by counsel for the respondents, and
the attempt was abandoned. According to the notice of motion the
award is unsigned.
No evidence was presented as to how it came to the
knowledge of the parties, or how it was purportedly published.
[61]
It
was submitted that it is common cause that the Mogotsi Kwagga Award
exists, and that the award therefore stands until set aside
by a
court. Reliance was placed on the
Oudekraal
[10]
rule which says an unlawful administrative act exists in fact and may
give rise to legal consequences for as long as it has not
been set
aside. In my view the
Oudekraal
rule
finds no application in this matter.
[61.1]
It is not clear to me that it is common
cause that the Mogotsi Kwagga Award exists
as
an award.
The respondents refer to it
in their answering affidavit as a “purported award”.
There is no evidence that it was published
in terms of the NEC3
contract.
[61.2]
The Yacoob J 2019 order (properly
construed) contemplates that any proceedings before Mr Mogotsi
ceased, and that Mr Mogotsi’s
appointment as adjudicator came
to an end. Any purported award which Mr Mogotsi may have produced
after the Yacoob 2019 order was
not an award at all. Mr Mogotsi was
no longer a decision-maker whose decisions had any effect.
[61.3]
The
following dictum is apposite:
[11]
“
There
is a distinction in law between the improper exercise of power as
in Oudekraal and the purported exercise of power
where none
exists. In the present matter Hani did not improperly exercise his
power by signing the second contract. He simply possessed
no
conferral of power or jurisdiction to extend the first contract
.”
[61.4]
The respondents do not have to set the
Mogotsi Kwagga Award aside – the Yacoob J 2019 order has
already dealt with this issue.
[61.5]
If
the Mr Mogotsi attempted or purported to publish the Mogotsi Kwagga
Award after Adv Badela’s award had been published,
it could not
undo or wipe out Adv Badela’s award.
[12]
[62]
Accordingly, Kwagga’s challenge to
the adjudicator’s award on the ground that he exceeded his
mandate (based on the
Mogotsi Kwagga Award) must fail. The prayer in
the notice of motion seeking that Mr Mogotsi’s award be
declared final and
binding and enforceable also stands to be
dismissed.
Kwagga:
other prayers
[63]
The applicant styles its review of the
adjudicator’s award a “legality review”. The award
is however not reviewable.
[64]
In the alternative to its prayers for reviewing and setting
aside Adv Badela’s award and for the Mogotsi Kwagga Award to be
held binding, Kwagga brings a contractual claim relying on clause
W1.4. However, it cannot do so as it was out of time in notifying
the
other parties.
[65]
It may be mentioned that even if Kwagga did
give timeous notice, it still would not have proved its case. I
briefly state my reasons
for coming to this conclusion.
[66]
Kwagga has not remedied the defects in its
case that there was no certification of the works, and that invoices
and the like have
not been submitted. In this regard the
adjudicator’s determination and reasoning still applies.
[67]
Kwagga’s attempt to prove its alleged
damages in the founding affidavit is wholly inadequate. It contains
lists of invoice
numbers, months, and global amounts. No attempt is
made to explain the figures. The invoices are not even annexed. It is
impossible
to determine how Kwagga calculated its damages from these
numbers.
#
# TALEDI
TALEDI
[68]
Taledi has framed its application as a
review. In its heads of argument it is referred to as a legality
review. The adjudicator’s
award is however not reviewable.
[69]
Taledi also relies on clause W1.4,
presumably as an alternative to its review application.
[70]
As mentioned Taledi was out of time to
bring a reconsideration application. It may be mentioned that even if
Taledi did give timeous
notice, it still would not have proved its
case. I briefly state my reasons for coming to this conclusion.
[71]
Taledi has not remedied the defects in its
case that there was no certification of the works, and that invoices
and the like have
not been submitted. In this regard the
adjudicator’s determination and reasoning is still applicable.
[72]
Taledi in the founding affidavit states
that a “complete breakdown” of its claim is attached as
annexure FA15. This
annexure consists of tables showing the relevant
periods, invoice numbers and a column headed as “outstanding
works order”.
The invoices are not attached. The claims for
most periods are stated to be “…
where
no work was issued and there was no compensation.
”
This clearly does not constitute proof of any damages or loss. No
other proof of Taledi’s alleged damages is
offered.
#
# CATAGRICT,
MAFUBE AND BASIC BLUE
CATAGRICT,
MAFUBE AND BASIC BLUE
[73]
In prayer 1 of their notice of motion
Catagrict, Mafube and Basic Blue expressly state that they seek that
Adv Badela’s determination
be set aside in terms of clause
W1.4(2) of the MEC3 Contract. It is confirmed in the founding
affidavit that the application is
based on this clause. These
claimants did timeously give notice in terms of clause W1.4(2).
[74]
This is therefore not a legality review or
a review in terms of PAJA, but a reconsideration application.
However, in the founding
affidavit the attacks on the award create
the impression that this is in fact a legality or PAJA review.
Insofar as Catagrict,
Mafube and Basic Blue did intend in the
alternative to rely on a legality review, I repeat that the award is
not reviewable.
Reconsideration
application
[75]
In
this application the claimants have timeously given notice in terms
of clause W1.4(2) and it is the only application of the four
applications where the claimants get out of the starting blocks.
[13]
I shall therefore deal with the merits of their reconsideration
application in some detail.
[76]
In the founding affidavit it is averred
that the claims of Catagrict, Mafube and Basic Blue are made up of
the following:
[76.1]
shortfall on payments received;
[76.2]
annual escalations;
[76.3]
outstanding work orders;
[76.4]
late payments and carry over interest;
[76.5]
interest accumulated from 2014 to 2017
financial years.
[77]
It is then stated that the quantifications
of the amounts of these items appear in annexures “J1” to
“J3”
attached to the founding affidavit.
[78]
When one turns to annexure “J1” (actually attached
as annexure “CM18”) one finds a document of 96 pages.
The
first page seems a covering page of an email addressed to Mr Mogotsi.
The next 54 pages contain parts (or the whole) of the
MEC3 Contract,
the addenda and an annexure thereto. The last 41 pages seem to be the
quantification of Catagrict’s claim
and contain (as far as I
can tell) different categories of the claim:
[78.1]
There is a category called “shortfall on payment
received”. It has a column setting out the payment date, a
column mysteriously
headed “expected works order”, a
column headed “amount paid” and a column headed
“shortfall amount”.
No explanation is furnished for these
entries.
[78.2]
One then finds a category for “escalation on payments
received”. Here we have a column for dates, a column for
amounts
received, a column headed “escalated amounts received
at 10%”, and the final column being the claim amount (including
VAT). There is no indication what the “escalated amounts
received” is, and no explanation whatsoever as to what the
claim amount is. There is no discernible correlation between the
amounts in the last column and the previous columns.
[78.3]
There follows a category styled “outstanding work
order”. It has a column named “outstanding month”
and
then a column headed “amount of outstanding works order”.
No breakdown of these amounts is furnished.
[78.4]
The next category is “interest on late payment”.
There are columns for amounts paid, invoice dates, payment date, paid
late, and then “average interest”. It is unclear how this
rate is calculated. I will return to interest on late payments.
[78.5]
Lastly one finds a category “calculation of carried over
interest”. This phrase is not explained. There is an “interest
rate” column (without stating how the interest rate is
determined), a column headed “interest opening balance”,
a column “interest per month”, and a column “interest
closing balance”. The amounts do not correlate with
one
another. The court is not informed where the opening balance comes
from. How the closing balance is determined remains a mystery.
[79]
Annexures “J2” and “J3”
which pertain to
Mafube and Basic Blue
are
in the same vein.
[80]
There
is no indication in the founding affidavit on what contractual
clause(s) in the
MEC3
Contract or the addenda these items are based. It is trite that a
founding affidavit constitutes both the evidence and the
pleadings.
[14]
An applicant or
plaintiff must at least plead the relevant terms of the contract and
the applicability of those terms to its claim.
[15]
The founding affidavit in this case does not even meet the
requirements of a pleading based on contract let alone furnishing
sufficient
evidence.
[81]
It is not for the respondents or the court to page through
these annexures and try to determine how the applicants attempted to
calculate their claim. This type of documentation, without any
explanation in the founding affidavit, does not constitute proof.
[82]
In
Lipschitz
and Schwartz NNO v Markowitz
[16]
1976 (3) SA 772
(W) the
court observed at 775H-776A:
“
Mr Peart ultimately
took refuge in the last paragraph of the founding affidavit . . ..
This is the blanket allegation
that perusal of the record of evidence
will reveal some prima facie case of misfeasance. I am not
prepared to accept
this proposition.
A
litigant cannot, as it were, throw a mass of material contained in
the record of an enquiry at the Court and his opponent, and
merely
invite them to read it so as to discover for themselves some
cause of action which might lurk therein, without identifying
it. If
this were permissible, the essence of our established practice and
which is designed and which still evolves as a means
of accurately
identifying issues and conflicts so that the Court and the litigants
should be properly apprised of the relevant
conflicts, would be
destroyed
.
”
[17]
(Own emphasis)
[83]
Accordingly, not only has Catagrict, Mafube and Basic Blue
failed to prove their case before the adjudicator, in this rehearing
application they have also dismally failed to do so.
## Alleged
Irregularities
Alleged
Irregularities
[84]
Catagrict, Mafube and Basic Blue aver that
there are a number of irregularities in the award. Even if this is
correct, this will
not avail Catagrict, Mafube and Basic Blue as they
have failed to prove their case. I shall however briefly refer to the
alleged
irregularities.
##
## First
ground: time bar
First
ground: time bar
[85]
I have already dealt with the time bar and
the fact that it is not determinative of the application.
##
## Second
ground: guaranteed minimum works orders
Second
ground: guaranteed minimum works orders
[86]
Catagrict, Mafube and Basic Blue complain
about the adjudicator’s finding (in paragraph 113) that there
was no guaranteed
works order. They say it was not pleaded as a
defence and that the adjudicator accordingly fashioned out a defence
on behalf of
the respondents. As found by the adjudicator, the
claimants had to “
state the
contractual terms they rely on for alleged rights to minimum works
order
.” They bore that onus. In
any event, Catagrict, Mafube and Basic Blue have also failed to prove
in these proceedings that
they were entitled to payment for work not
done.
##
## Third
ground: amendment of claims
Third
ground: amendment of claims
[87]
Catagrict, Mafube and Basic Blue challenge
the adjudicator’s finding that the claimants had no basis to
amend their claims
6 years after referral of the dispute to
adjudication.
[88]
However, the adjudicator also (correctly)
found that the claimants did not plead any invoices in support of
their alleged claims
to escalation and interest (which form part of
the amended claims).
[89]
For reasons set out above, Catagrict,
Mafube and Basic Blue have failed in this application to prove any
claim whatsoever.
##
## Fourth
ground: certification
Fourth
ground: certification
[90]
Catagrict, Mafube and Basic Blue aver that
the absence of certification was not pleaded before the adjudicator,
and that the adjudicator
therefore fashioned out a defence on behalf
of the respondents. This misses the point. In the absence of
certification, Catagrict,
Mafube and Basic Blue had to prove their
claim and quantum.
##
## Fifth
ground: interest
Fifth
ground: interest
[91]
Catagrict, Mafube and Basic Blue take issue
with the adjudicator’s finding that because the claimants’
claims were time
barred, the question of interest does not arise. In
that the claim was not time barred, Catagrict, Mafube and Basic Blue
aver that
the adjudicator therefore erred and that interest should
accrue to their claims. This is incorrect, as the arbitrator also
found
that no invoices were pleaded by the claimants in support of
their claim to interest. In other words, he also dismissed the
interest
claim on the merits.
[92]
Catagrict, Mafube and Basic Blue have
failed to prove the interest claim in these proceedings. It was
required of Catagrict, Mafube
and Basic Blue to have at least pleaded
and to have furnished documentary and/or other evidence as to:
[92.1]
date when payment was due in respect of
each invoice (with due reference to the relevant terms of the
contract);
[92.2]
the amount of the invoice;
[92.3]
date when it was paid;
[92.4]
contractual entitlement to a specific rate
of interest, or proof of the interest as a damages claim or that they
claim
mora
interest.
## Allegation
that decision is irrational
Allegation
that decision is irrational
[93]
It is further averred that the
adjudicator’s decision is irrational. The grounds for this
finding are simply based on a number
of findings the adjudicator made
against the claimants, for example that there were no tax
certificates, invoice numbers or certification.
There are no grounds
for finding that the award was irrational.
##
## Constitutional
Considerations
Constitutional
Considerations
[94]
Catagrict, Mafube and Basic Blue also
submit that the contract should be viewed
“
within the
purview of the Constitution and public policy”
. It is not
spelt out how the adjudicator or this court should deal with the
matter differently in light of the Constitution or
public policy. The
issue is whether Catagrict, Mafube and Basic Blue proved their
contractual claim against the respondents.
#
# KOPANO
KOFIFI
KOPANO
KOFIFI
Noice
of motion and proposed amendment
[95]
Kopano Kofifi in prayer 1 of its notice of
motion seeks that the determination of the adjudicator be reviewed
and set aside. Prayer
2 then reads:
“
2.
That the dispute previously referred to Mr Lloyd Mogotsi be finally
determined by the above Honourable Court.”
Prayer
3 deals with the costs of the application.
[96]
No case for payment is made out in the
founding affidavit.
[97]
The applications were heard over two days,
more than a week apart. On the eve of the second day of the hearing
Kopano Kofifi caused a notice of amendment of the notice of
motion to be uploaded on CaseLines. In terms of the proposed
amendment
prayer 2 was to be deleted in its entirety and replaced by
the following:
“
2.
Directing the first and second respondents jointly and severally, the
one paying the other to be absolved, to pay the applicant
the sum of
R27 810 304,42 (VAT inclusive).”
The
proposed amendment also includes interest on the above amount.
[98]
At the hearing on the next day counsel
moved for the amendment from the Bar. He relied on rule 28(10). There
was no affidavit in
support of the application. The proposed
amendment was vigorously opposed by respondents’ counsel.
[99]
In the midst of the debate about the
proposed amendment, further documentation was uploaded on CaseLines
without prior notice. The
first document consists of one page headed
“
Financial Year 2017”
with various columns and amounts. The second document is a document
of 41 pages headed “
Submission,
Calculations: Kopano Kofifi Projects”
.
There is also a third document, but it appears to be a
duplication of the first document. The documents are not confirmed
on
oath.
[100]
When it came to light that these documents
had been uploaded onto CaseLines, respondents’ counsel
obviously objected to their
admissibility. I stated that I will rule
on the amendment and the admissibility of the documents in this
judgment.
[101]
The documents have not been confirmed on oath. These documents
do not fall within any recognised class of documents which prove
themselves on mere production. They are inadmissible in evidence.
[102]
The factors which a Court will consider
before granting a late amendment are trite.
[102.1]
A
party who seeks the amendment bears the onus of proving that the
other party will not suffer prejudice as a result. Doubt as to
whether the other party might suffer prejudice will result in refusal
of the application.
[18]
In
this instance the respondents will clearly suffer prejudice, as they
had no opportunity to deal with the relief seeking a monetary
payment.
[102.2]
The
party seeking a late amendment must also prove that it did not delay
in making the application after becoming aware of the evidential
material upon which reliance is placed and must provide a
satisfactory reason why the amendment was not sought at an earlier
stage.
[19]
Kopano Kofifi did
not do so.
[102.3]
The
party seeking the amendment must also show that it has a triable
issue, ie a dispute which will probably be established by the
evidence foreshadowed.
[20]
In
this case the applicant relies on documentation which has not been
confirmed under oath and does not constitute evidence. In
addition,
for the same reasons that apply to the applications of the other
claimants, the documents (even if admissible) would
in any event have
been insufficient to establish a monetary claim.
[103]
The application for amendment of the notice of motion is
dismissed, and it is ruled that the documents filed on CaseLines on
01-281
to 01-324 are inadmissible.
Merits
and additional submissions
[104]
Kopano Kofifi did give timeous notice in terms of clause W1.4,
and therefore could bring a reconsideration application. In the light
of the fact that it did not present any admissible evidence, its
application for reconsideration must fail.
[105]
Its application was similarly worded as a review application
if regard is had to the contents of prayer 1 of the notice of motion
and the founding affidavit. However, as found above, the award of the
adjudicator is not reviewable.
[106]
I need to deal with an additional issue raised by Kopano
Kofifi in its founding affidavit. In the founding affidavit the
following
is stated:
“
The
third respondent
[Adv
Badela]
reassessed the merits of the
initial dispute, an aspect with falls within the purview of the
initial adjudicator. He thereby exceeded
his powers by assuming the
power to review the merits of
the first
adjudication award
, when the Contract
did not afford him those powers. Indeed, it can be argued that he
usurped the role of the Tribunal by examining
the merits.”
(Own
emphasis)
[107]
I have already indicated that no such
argument was presented to Adv Badela.
[108]
Kopano Kofifi refers to a document attached to its founding
affidavit which is an email addressed by Mr Mogotsi which shows that
Mr Mogotsi had started to consider the claims. In the email he raised
certain queries and asked for further information. There
is however
no evidence of a “first adjudication award”.
[109]
During oral argument on behalf of
Kopano
Kofifi
, reference was made to a portion of a
disputed settlement agreement which had been concluded between the
contractors and the Department
years ago.
The claimants in the
proceedings before Adv Badela opposed the introduction of the
settlement agreement and the adjudicator found
in their favour. A
party cannot cherry pick portions of an inadmissible settlement
agreement in order to support its case.
#
# COSTS
AND CONCLUSION
COSTS
AND CONCLUSION
[110]
The
application stands to be dismissed, and costs should follow the
result. A cost order should be made under rule 67A(3) read with
rule
69 in respect to work rendered after 12 April 2024.
[21]
Scale C is appropriate if regard is had to the importance, value and
complexity of the case. In respect of work rendered before
12 April
2024, t
he
respondents are entitled to party and party costs.
Whilst
I am of the view that the employment of senior counsel was justified,
a
court
does not make a specific order stipulating that the costs should
include the costs of senior counsel.
[22]
#
# ORDERS
ORDERS
[111]
I accordingly make the following orders:
Case
number 6577/2019
:
1.
The application is dismissed.
2.
The applicant is ordered to pay first and
second respondents’ costs,
such costs to be on the party
and party scale to 11 April 2024, and with effect from 12 April 2024
on scale C in terms of rule 67A
read with rule 69 of the Uniform
Rules of Court.
Case
number 40523/2023
:
1.
The application is dismissed.
2.
The applicant is ordered to pay first and
second respondents’ costs,
such costs to be on the party
and party scale to 11 April 2024, and with effect from 12 April 2024
on scale C in terms of rule 67A
read with rule 69 of the Uniform
Rules of Court.
Case
number 11460/2022
:
1.
The application is dismissed.
2.
The applicants are ordered to pay second
and third respondents’ costs, jointly and severally,
such
costs to be on the party and party scale to 11 April 2024, and with
effect from 12 April 2024 on scale C in terms of rule 67A
read with
rule 69 of the Uniform Rules of Court.
Case
number 23359/2022
:
1.
The application is dismissed.
2.
The applicant is ordered to pay first and
second respondents’ costs,
such costs to be on the party
and party scale to 11 April 2024, and with effect from 12 April 2024
on scale C in terms of rule 67A
read with rule 69 of the Uniform
Rules of Court.
VAN
DER BERG AJ
APPEARANCES
Case
no 6577/2019
For
the applicant:
Adv
J A Venter
Des
Naidoo & Associates
For
the first and second respondents:
Adv
M B Lecoge SC
Instructed
by:
Malatjie
& Co Attorneys
Case
no 40523/2023
For
the applicant:
Adv
J A Venter (heads of argument drawn by attorney)
Instructed
by:
Des
Naidoo & Associates
For
the first and second respondents:
Adv
M B Lecoge SC
Instructed
by:
Malatjie
& Co Attorneys
Case
no: 11460/2022
For
the applicants:
Adv
LH Lekalakala
Instructed
by:
Ndobe
Inc. Attorneys
For
second and third respondents:
Adv
M B Lecoge SC
Instructed
by:
Malatjie
& Co Attorneys
Case
no 23359/2022
For
the applicant:
Adv
H Salani (1
st
day) and Adv LH Lekalakala (2
nd
day)
Instructed
by:
Ramatshila-Mugeri
Inc
For
first and second respondents:
Adv
M B Lecoge SC
Instructed
by:
Malatjie
& Co Attorneys
Dates
of hearing: 29 July 2024 and 7 August 2024
Date
of judgment: 25 October 2024
[1]
Yacoob
J also handed down an earlier judgment in a matter between other
contractors and the Department.
[2]
VN
v Member of the Executive Council for Health & Social
Development of the Eastern Cape Province
2022 JDR 1691 (ECP), para 20
[3]
Framatome
v Eskom Holdings SOC Ltd
2022
(2) SA 395 (SCA)
[4]
Para 22
[5]
Sasol
South Africa (Pty) Ltd v Murray & Roberts Ltd
(Case
No: 425/2020)
[2021] ZASCA 94
(28 June 2021;
Tubular
Holdings (Pty) Ltd v DBT Technologies (Pty) Ltd
2014
(1) SA 244 (GSJ)
[6]
Department
of Roads and Transport v Mogotsi NO and 3 others
(GJ Case Numbers 5163/2018 & 5164/2028)(11/02/22). The case was
referred to by claimants and attached to the papers. In that
case
the Department brought applications to review an adjudication award
made by Mr Mogotsi.
[7]
Tikly
v Johannes N.O.
1963
(3) SA 588 (T)
[8]
Economic
Freedom Fighters and Others v Manuel
2021
(3) SA 425
(SCA) at paragraph [105]
[9]
See
in general:
Alfred
Mcalpine and Son (Pty) Ltd v Transvaal Provincial Administration
1974 (3) SA 506
(A) at 531
[10]
Oudekraal
Estates (Pty) Ltd v City of Cape Town
2004 (6) SA 222
(SCA) paragraph [26].
[11]
Nelson
Mandela Bay Municipality v Tsatsire
(1479/14) [2015] ZAECPEHC 19 (31 March 2015); 2015 JDR 0676 (ECP)
[12]
Magnificent
Mile Trading 30 (Pty) Ltd v Celliers NO and Others
2020
(4) SA 375
(CC), paragraph [43]
[13]
Kopano Kofifi also gave timeous notice, but its application has
other problems. This is dealt with below.
[14]
Radebe
and Others v Eastern Transvaal Development Board
1988
(2) SA 785
(A) at 793C – G
[15]
Prins
v Universiteit van Pretoria
1980
(2) SA 171
(T) at 174G-H.
[16]
Lipschitz
and Schwartz NNO v Markowitz
1976 (3) SA 772
(W) at 775H-776A
[17]
See also:
Swissborough
Diamond Mines (Pty) Ltd and Others v Government of the Republic of
South Africa and Others
1999 (2) SA 279
(T) at 324G: "
(I)t
is not open to an applicant or a respondent to merely annex to its
affidavit documentation and to request the court to have
regard to
it. What is required is the identification of the portions thereof
on which reliance is placed and an indication of
the case which is
sought to be made out on the strength thereof. If this were not so
the essence of our established practice
would be destroyed. A party
would not know what case must be met
."
[18]
Kali
v Incorporated General Insurance
1976 (2) SA 179
(D) at 128B - D
[19]
Trans-Drakensberg
Bank Ltd (Under Judicial Management) v Combined Engineering (Pty)
Ltd and Another
1967
(3) SA 632
(D) at 641A – B;
Apex
Truck & Trailer v PPCF Boerdery CC
2024 JDR 2028 (GJ) at para 10
[20]
Consol
Ltd t/a Consol Glass v Twee Jonge Gezellen (Pty) Ltd
2005
(6) SA 23
(C) at 36I–J.
[21]
Mashavha
v Enaex Africa (Pty) Ltd
(2022/18404) [2024] ZAGPJHC 387 (22 April 2024); 024 JDR 1686 (GJ)
[22]
Singh
v BMW Financial Services (SA) (Pty) Ltd
2010 JDR 1157 (SCA) para 28
sino noindex
make_database footer start
Similar Cases
Kwababa and Another v Yandisa Investment Properties (Pty) Ltd and Others (2022/003687) [2024] ZAGPJHC 538 (6 June 2024)
[2024] ZAGPJHC 538High Court of South Africa (Gauteng Division, Johannesburg)99% similar
Qabaka and Others v South African Women In Mining Association and Others (37505/2019) [2023] ZAGPJHC 1105 (6 April 2023)
[2023] ZAGPJHC 1105High Court of South Africa (Gauteng Division, Johannesburg)99% similar
K.G obo T.J.G v Road Accident Fund (32263/2021 (Y)) [2023] ZAGPJHC 1093 (29 September 2023)
[2023] ZAGPJHC 1093High Court of South Africa (Gauteng Division, Johannesburg)99% similar
South African Securitization Program (RF) Limited and Others v Maxidor SA (Pty) Ltd and Others (2022/8473) [2024] ZAGPJHC 669 (25 July 2024)
[2024] ZAGPJHC 669High Court of South Africa (Gauteng Division, Johannesburg)99% similar
South African Board of Sheriffs v Cibe (000219/2023) [2024] ZAGPJHC 583 (21 June 2024)
[2024] ZAGPJHC 583High Court of South Africa (Gauteng Division, Johannesburg)99% similar