Case Law[2023] ZAGPJHC 1469South Africa
Eskom Holdings SOC Limited v TSSA (Pty) Ltd and Others (038256/2022) [2023] ZAGPJHC 1469 (21 December 2023)
High Court of South Africa (Gauteng Division, Johannesburg)
21 December 2023
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2023
>>
[2023] ZAGPJHC 1469
|
Noteup
|
LawCite
sino index
## Eskom Holdings SOC Limited v TSSA (Pty) Ltd and Others (038256/2022) [2023] ZAGPJHC 1469 (21 December 2023)
Eskom Holdings SOC Limited v TSSA (Pty) Ltd and Others (038256/2022) [2023] ZAGPJHC 1469 (21 December 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2023_1469.html
sino date 21 December 2023
IN THE HIGH COURT OF
SOUTH AFRICA,
GAUTENG LOCAL
DIVISION, JOHANNESBURG
Case No: 038256/2022
NOT REPORTABLE
NOT OF INTEREST TO OTHER
JUDGES
NOT REVISED
In
the matter between:
ESKOM
HOLDINGS SOC LIMITED
Applicant
and
TMMSA
(PTY) LTD
1
st
Respondent
ADVOCATE
PATRICK LANE SC
ADVOCATE
MOHAMMED CHOHAN SC
MR
GEOFREY GRANT
ADVOCATE
AZHAR BHAM SC
ADVOCATE
CHRIS LOXTON SC
2
nd
Respondent
3
rd
Respondent
4
th
Respondent
5
th
Respondent
6
th
Respondent
ADVOCATE
LEE HARDING
7
th
Respondent
JUDGMENT
NOKO J
Introduction
[1] The applicant
launched proceedings for interim interdict to stay the adjudication
of two disputes before two Dispute Adjudication
Board Panels (DAB
panels) pending the outcome of events set out below.
[2] The first dispute
relates to Claims Dispute (constituting of two parts, viz, merits and
time-bar parts) which is sought to be
stayed pending the finalisation
of the adjudication of arbitration proceedings and also pending the
finalisation of the investigations
conducted by the Special
Investigation Unit (SIU) into contractual arrangements between the
applicant and the respondent. The panel
would be referred to as
Claims DAB panel. The panel is constituted by second to fourth
respondents. Members of the panel are not
opposing the application
and have filed notice to abide.
[3] The second dispute
sought to be stayed relates to the termination of contractual and
transactional arrangements between the
parties. The stay should also
be ordered pending the finalisation of the investigation by the SIU.
The panel constituted to adjudicate
this dispute would be referred in
this
lis
to as Termination DAB panel and is constituted by
fifth to seventh respondents. Members of this panel are also not
opposing the
application and have also filed notice to abide.
[4] Reference to
respondent in this lis refers to TMMSA (Pty) Ltd.
Background
[5] The background set
out below is in general common cause between the parties and shall be
dealt with under the separate headings.
Contract and SIU
Investigation.
[6]
The parties
entered into a building contract on or about 2 or 3 November 2010 in
relation to works to be executed at the applicant’s
Kusile
Power Plant (
Kusile
contract
).
The contract was based on the FIDIC Conditions of Contact for Plant
and Design-Build, first edition 1999 (Yellow Book). The contract
had
three sections, first, P24B Contract, which related to terrace
materials handling. Secondly, P24E Contract, which related to
the
limestone works and thirdly, P24C Contract, which related to
stockyard works
[1]
. The disputes
between the parties arose from the execution of the P24B Contract.
[7]
During
April 2018 the SIU commenced investigations relating to
maladministration and corruption in the business and operations of
the applicant. Relevant to this matter the applicant avers that
“…
the
scope of the SIU investigations include the Contract concluded
between Eskom and TMMSA, TMMSA’s Claims dispute against
Eskom,
reported corrupt fraudulent activities, and the existence of TMMSA’s
alleged global settlement.”
[2]
Some corrupt (fraudulent) activities under investigation were
reported by the respondent.
[8]
The SIU’s
investigations were mandated in terms of Proclamations R11 of 2018
[3]
and R3 of 2020
[4]
. The
investigation includes the declaration of findings and evidence of
the investigations by the SIU and recommendations NDPP
for possible
charges emanating from the investigations. Despite the launch of the
investigation the implementation of the Kusile
contract continued.
Claims Dispute
[9] In February 2019 the
respondent submitted several claims which related to additional costs
and extensions of times arising from
Eskom’s alleged breaches
of the contract. The claims were considered and disapproved by the
applicant’s Engineer. The
respondent aggrieved by the
engineer’s decision submitted the disapproved claims for
adjudication by a DAB in accordance
with the dispute resolution
procedure under the contract. The referral submission was made on or
about 16 April 2021.
[10] The Claims Dispute
has two prongs. First, time-bar aspect which relates to the question
whether the claims were submitted on
time and secondly, the merits
aspect (and quantum) of the claims. The parties have agreed that the
time-bar aspect of the dispute
will be adjudicated first and
separately from the adjudication of the merits which shall come
second. The adjudication of the time-bar
aspect continued, and the
Claims DAB panel decided in partly in favour of the respondent. The
parties were not satisfied with this
outcome thereof and filed notice
of dissatisfaction in terms of which Claim DAB’s outcome is
referred for arbitration.
[11] Notwithstanding the
referral of the outcome to arbitration the respondent informed the
applicant that merits aspect of the
claim should be adjudicated by
the DAB panel. The applicant resisted the suggestion and contended
that the arbitration should first
determine the time bar aspect of
the claim and only thereafter and (if applicable), the parties should
proceed with the adjudication
on the merits. The Claims DAB
panel has also conveyed to the applicant that indeed the adjudication
on the merits should
proceed as contended by the respondent and
unless the proceedings are interdicted through an order of court
otherwise the adjudication
on the merits aspect would commence.
[12] Pursuant thereto the
applicant launched these proceedings.
Termination dispute
[13]
The
applicant terminated the contract with the respondent via a letter
dated 13 December 2021 on the basis,
inter
alia
,
that respondent has “…
committed
various acts in violation of sub-clause 15,2(f). The unlawful conduct
is common cause, given the self-reporting by TMMSA
of some of these
acts
”.
The letter of termination further stated that
“
[T]he parties
respective experts have been collaborating with the Special
Investigating Unit to determine the quantum of the overpayment
to
TMMSA arising out of the bribery and corruption in terms of
Sub-clause 15.2(f), which quantification is near completion. The
current Quantum Progress Update from these experts details millions
of Rands in overpayment to the Contractor as a result of bribery
and
corruption.”
[5]
[14] The respondent in
retort disputed the applicant’s alleged right to terminate the
contracts and further averred that the
conduct of the applicant is
construed as repudiation which was rejected by the respondent. The
respondent then proceeded to issue
a termination letter to the
applicant. In the premises both parties contends that each of them
has validly terminated the contract.
[15] Termination would
ordinarily trigger repayment of amounts received by the Applicant
following its recourse on various security
bonds under the contract
if the termination at the instance of the respondent is found to be
valid. At the same time if the termination
is determined in favour of
the applicant there are also financial consequences.
[16] Pursuant to the
aforegoing the parties constituted a second DAB (Termination DAB
panel) to adjudicate over the termination
dispute. In one of the
pre-hearing meetings the parties agreed that “
the dispute
…between the Parties is as defined in the DAB agreement”
.
The parties are not, yet, in agreement as to what the dispute should
be. The applicant contends that the dispute should only deal
with
termination whereas the respondent contends that it should deal with
both termination and consequences of termination.
[17]
The DAB has
determined that it is not endowed with jurisdiction in view of the
fact that, though the parties have appointed the
panel “…
parties
have not concluded a DAB agreement, defining the dispute to be
submitted… for determination”.
[6]
[18]
The
respondent has pursuant to the decision of the termination DAB panel
elected on 1 December 2022 to refer the dispute to arbitration
since
“…
as
the parties had failed to constitute a dispute adjudication board to
hear the Termination Dispute.”
[7]
.
That notwithstanding the applicant has launched the proceedings to
interdict the DAB on termination dispute to which the
respondent
raised a point
in
limine
that there is no dispute before DAB and as such the relief sought is
nugatory.
Issues
[19] The issues for
determination are, first, point
in limine
and secondly whether
the applicant has made out a case for the reliefs sought.
Points in limine.
[20] The respondent
contends that the issue in relation to the stay of the claims dispute
(merits aspect) has been rendered nugatory
since the respondent has
already agreed to the stay of the proceedings pending arbitration of
the time bar aspect of the claims
dispute.
[21] The applicant in
retort contends that the concession to the stay was only made after
the court papers were served on the respondent
and the court should
grant an order confirming the stay by agreement
inter se
and
further order the respondent to pay costs at a punitive scale. This
is predicated on the argument that the attempts were made
to procure
the concurrence of the respondent to the stay adjudication of the
merits aspect of the claim but the latter was recalcitrant
and only
took a
volte face
stance after the court papers were served.
[22] I will therefore
make an order that the merits aspect of the claim dispute shall be
stayed pending arbitration on the determination
by the Claims DAB on
the time-bar aspect of the claim dispute.
[23]
Regarding
the termination dispute it is axiomatic to note that the Termination
DAB made a ruling
[8]
that it has
no “
jurisdiction
to deal with any dispute as might exist between the parties”.
[9]
As such
until such time as the parties agree on the dispute the Termination
DAB panel is seized with no dispute to adjudicate upon.
The ruling by
the Termination DAB panel has been referred to arbitration by the
respondent in accordance with the notice of referral
annexed to the
respondent’s answering affidavit marked AA6.
[10]
Termination DAB is therefore appointed in
vacuo
.
It therefore follows that there is no dispute pending before the
Termination DAB panel. As such the relief sought in this regard
in
unsustainable and incompetent.
[24] I therefore find in
favour of the respondent that the relief sought relative to the
termination dispute is incompetent.
Interim interdict
[25]
Having
dealt with points
in
limine
raised by the respondent the only outstanding issue serving before me
relates to the second relief sought by the applicant under
Claims
Dispute, being that the claim dispute should be stayed pending the
finalisation of the investigation by the SIU.
[11]
This relief cannot be competent or co-exist with relief to stay
pending arbitration. Otherwise, the orders would be mutually
contradictory
and self-destructive. The application should have been
to either stay the Claims dispute (merits aspect) pending arbitration
alternatively
pending SIU investigation. The applicant is therefore
approbating and reprobating. To this end, the second relief under
Claims
Dispute is bound to fail.
[26] In view of the above
findings any other issue raised by the parties need not detain this
court any further.
Costs
[27] The applicant
contends that the court should convey its displeasure by mulcting the
respondent with punitive costs order due
to its recalcitrant.
attitude. It does not appear to have been an unreasonable reaction by
the respondent as it was also shared
by the three senior counsels who
also ruled that the adjudication on the merits should continue even
though the dispute on the
time bar aspect is pending before the
arbitration. To this end mulcting the respondent with costs on
punitive scale may not be
appropriate under the circumstances.
[28] Both parties have
however been successful in that the dispute on time bar aspect of the
claim dispute is stayed pending the
arbitration as a relief sought by
the applicant. On the other hand, the respondent succeeded in
argument advanced that the there
is no dispute pending before the
termination DAB panel regarding termination of the Kusile contract
between the parties. In
the premises, I find that ordering each
party for their respective legal costs would be apt.
[29] I make the following
order:
1. That the merits aspect
of the claims dispute is stayed pending arbitration of the claim
dispute on time-bar aspect of the claim.
2. The application for
the stay of the proceedings of the claim dispute pending SIU
investigation is dismissed.
3. The application for
the stay of the termination dispute pending SIU Investigation is
dismissed.
4. Each party shall pay
their respective legal costs.
Mokate Victor Noko
Judge of the High
Court
This judgement was
prepared and authored by the Judge whose name is reflected and is
handed down electronically by circulation to
the Parties / their
legal representatives by email and by uploading it to the electronic
file of this matter on CaseLines. The
date of the judgment is deemed
to be
21 December 2023.
Appearances
For
the Applicant: Adv A Jansen van Vuuren
Attorneys
for the Applicant: Kapditwalwa Inc. t/a Dentons, Johannesburg.
For
the Respondent: Adv Burman
Attorneys
for the Respondent Pinsent Masons South Africa Inc.
Date
of hearing: 4 September 2023
Date
of judgment: 21 December 2023
[1]
See
para 8.2 of the Applicant’s Founding Affidavit, CL 001-26.
[2]
See
para 6.22 of the Applicant’s Founding Affidavit, on CL 001-18.
[3]
Published
in Government Gazette No 41561, 6 April 2018.
[4]
Published
in Government Gazette No. 42979, 31 January 2020.
[5]
[5]
See
para 9.4 of the Applicant’s Founding Affidavit, CL 001-31. The
applicant alleged, strangely, in para 53.3 of the Replying
Affidavit
that “[T]he applicant contends it terminated the Contract with
TMMSA on the basis of fraud, corruption and
TMMSA’s
insolvency
”.
(underlining added).
[6]
See
para 39 of the DAB panel’s ruling on jurisdiction/Disputes, CL
007-51.
[7]
See
para 7.3 of the Respondent’s Answering Affidavit, CL 007-9.
[8]
The applicant appreciate that the dispute has not been defined
and has stated in para 57.4 of the Applicant’s Replying
Affidavit. CL 008-28 that “…
the
parties agreed that on the DBA Panel to be appointed, but the
applicant disputed the nature and scope of the dispute before
the
DAB Panel, so that it would not be overly broad or open-ended. The
Termination DAB Panel agreed with this in its ruling.”
[9]
See DAB panel’s ruling para 39.3, CL 007-63.
[10]
See
para 7.3 of the Respondent’s Answering Affidavit, CL 007-9.
[11]
See
para 9.2 of the Applicant’s Replying Affidavit, CL 008-6
sino noindex
make_database footer start
Similar Cases
Eskom Holdings SOC Ltd v Santam Ltd and Another (44268/19) [2022] ZAGPJHC 1045 (12 August 2022)
[2022] ZAGPJHC 1045High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Rotek Industries SOC Ltd v Geo-X (Pty) Ltd (2021/41489) [2023] ZAGPJHC 1140 (11 October 2023)
[2023] ZAGPJHC 1140High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holding SOC Limited Ltd v Sokweba and Others (101726/2024) [2024] ZAGPJHC 935 (18 September 2024)
[2024] ZAGPJHC 935High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holdings Soc LTD v Babcock Ntuthuko Engineering (Pty) Ltd (A2023/099598) [2024] ZAGPJHC 990 (3 October 2024)
[2024] ZAGPJHC 990High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holdings SOC Ltd v City of Johannesburg Metropolitan Municipality and Others (2024/048808) [2024] ZAGPJHC 579 (20 June 2024)
[2024] ZAGPJHC 579High Court of South Africa (Gauteng Division, Johannesburg)100% similar