Case Law[2022] ZAGPJHC 1045South Africa
Eskom Holdings SOC Ltd v Santam Ltd and Another (44268/19) [2022] ZAGPJHC 1045 (12 August 2022)
High Court of South Africa (Gauteng Division, Johannesburg)
12 August 2022
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: South Gauteng High Court, Johannesburg
South Africa: South Gauteng High Court, Johannesburg
You are here:
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2022
>>
[2022] ZAGPJHC 1045
|
Noteup
|
LawCite
sino index
## Eskom Holdings SOC Ltd v Santam Ltd and Another (44268/19) [2022] ZAGPJHC 1045 (12 August 2022)
Eskom Holdings SOC Ltd v Santam Ltd and Another (44268/19) [2022] ZAGPJHC 1045 (12 August 2022)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPJHC/Data/2022_1045.html
sino date 12 August 2022
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
DIVISION, JOHANNESBURG
Reportable:
Yes
Of
interest to other judges: Yes
12
Aug 2022
Vally
J
Case
No.: 44268/19
In
the matter between:
Eskom
Holdings SOC
Ltd Applicant
and
Santam
Ltd First
Respondent
Jyoti Structures
Africa (Pty)
Ltd Second
Respondent
Judgment
Vally
J
Introduction
[1]
The applicant (Eskom) entered into a
contract
on 29 April
2016 with the second respondent (Jyoti)
in terms of which Jyoti was to construct a transmission line for
Eskom. The contract is
a standard engineering and construction
contract (NEC3) utilised by Eskom when procuring services from a
party. On 16 May 2019,
as security for the proper performance of its
obligations, Jyoti issued Eskom with a Performance Bond - Demand
Guarantee (Guarantee)
- which Eskom could call before its expiry
date, 31 October 2019. It was underwritten by the first respondent
(Santam).
[2]
In terms of the Guarantee, Santam agreed that it holds a sum of
R20 339 245,
25 (Twenty-Million three hundred and
thirty-nine thousand two hundred and forty-five rands and twenty-five
cents) ‘at the
disposal of Eskom, as security for the proper
performance by [Jyoti] … and agreed to pay Eskom, on written
demand received
from Eskom prior to’ 31 October 2019. The
written demand for payment (demand) had to meet three conditions. The
first condition
was that it had to ‘be signed on behalf of
Eskom by a director of Eskom or an authorised delegate.’ The
second condition
was that it had to ‘state the amount claimed’.
And the third condition was that it had to ‘state that the
Demand
Amount is payable to Eskom in the circumstances contemplated
in the’ contract between Eskom and Jyoti.
[3]
On 17 October 2019 Eskom issued the demand. Attached to the demand
was
a copy of the Guarantee. The demand is brief and succinct. Given
the importance of the demand for determination of the dispute it
is
necessary to quote it in full:
‘
CONSTRUCTION OF
SECTION A OF ARIADNE EROS 132/400 KV MULTI CIRCUIT LINE PURCHASE
ORDER NUMBER: 4502349088
CALL-UP OF PERFORMANCE
BOND-JYOTI STRUCTURES (PTY) LTD
Eskom Holdings SOC
Limited and Jyoti Structures Africa (Pty) Ltd entered into a contract
for construction of the Ariadne Eros Section
A, 400 KV line. This
contract was signed by both parties 29 April 2016.
As security for the
proper performance by the contractor of its obligations in terms of
and arising from the said contract, Santam
issued an on demand
guarantee under number 13731, the copy of original of which is
attached to this document, for payment of the
guaranteed sum, as
defined in the said guarantee.
Eskom herewith demands
payment of the total said guaranteed sum, and confirm that this is
the demand amount as defined in the said
guarantee.
This demand is made in
circumstances as contemplated in the contract between the parties.
The signatory hereof has
been duly authorised to make this demand.’
[4]
The material elements of the demand are captured in three sentences
that
are intended to meet the three conditions:
[4.1]
The sentence directed at meeting the first condition reads:
‘
The signatory
hereof has been duly authorised to make this demand.’
It was signed by a Mr
Clint Fisher who was the ‘Senior Manager Projects’.
[4.2]
The sentence directed at meeting the second condition reads:
‘
The demand is made
in circumstances as contemplated in the contract between the parties’
[i.e. Eskom and Jyoti]
[4.3]
The sentence directed at meeting the third condition reads:
‘
Eskom herewith
demands payment of the total guaranteed sum, and confirm that this is
the demand amount, as defined in the said guarantee.’
[5]
Santam refused to meet the demand. The reason for its refusal,
according
to its legal representative who wrote to Eskom, was that
the Guarantee was a ‘conditional guarantee akin to a
suretyship.’
As a result, Eskom launched the present
application.
[6]
There can be little doubt that the claim by Santam conveyed by its
legal
representative was manifestly wrong. A simple reading of the
Guarantee makes it plain that it was not a conditional one akin to
a
suretyship. Having received the application Santam changed its reason
for refusing to meet the demand. In its answering affidavit
it said
that the demand did not comply with any of the three conditions set
out in the Guarantee, thereby allowing it to repudiate
the call.
The
law
[7]
The law on guarantees is straightforward. It has been wholly adopted
from
English law.
[8]
A
guarantee, a performance bond and a letter of credit are essentially
the same.
[1]
Each of them is a
contract ancillary to another contract, the latter being the
underlying or principal contract. Without it the
principal contract
is incomplete and incapable of being put into effect. The guarantee
introduces a third party – normally
a bank or an insurance
company - to the relationship between the two principal contracting
parties. At the behest of one of the
parties – seller of
services or purchaser of goods – the third party promises to
pay the other party a pre-determined
sum of money. The purpose of a
guarantee then is to provide security to one party to a contract that
the other party shall perform
its obligations, or at least it shall
be compensated, should the party fail to perform its obligations.
[9]
While the
guarantee is ancillary to the principal contract it however enjoys an
independent existence. Because of its independent
existence the
question of whether the party has failed to perform does not often
arise when the guarantee is drawn upon, or is
irrelevant. This is
normally so because the terms of the guarantee are often irrevocable
and require payment on demand when due,
and the party furnishing the
guarantee – third party, such as a bank or insurance company –
is not a party to the contract
and has no role to play therein. A
guarantee is an indispensable part of international trade.
[2]
There must however be compliance with the terms of the guarantee for
it to honoured. Put differently, courts do not concern themselves
with disputes between the parties to the contract. Once the terms of
the guarantee are complied with, the obligation on the part
of the
bank or insurance company to pay can only be avoided in very strict
circumstances, such as a clear case of fraud. Thus,
‘courts are
not concerned with [the contracting parties’] failure to
enforce their claims against each other; these
are risks [the
contracting parties] take.’
[3]
The principle has been repeatedly enunciated in many judgments,
[4]
and is now accepted as trite.
The
issue
[10]
There is a single issue which requires determination: does the demand
satisfy the three
conditions set out in the Guarantee?
Analysis
[11]
Eskom had a right to draw on the Guarantee by demand. It exercised
the right. Its demand
is focussed. To recall: Santam’s
avoidance of liability is based on the contention that it does not
satisfy any of the three
conditions set out in the guarantee.
[12]
The
averment by the author of the demand, a Mr Clint Fisher, makes it
abundantly clear that he ‘is authorised to make the
demand
hereof’. Absent a challenge to his authority, which challenge
had to be raised at the time the demand was made, Eskom
has complied
with the first condition. Santam failed to raise the issue of his
authority at the time he made the demand. In its
answering affidavit
it does not say why he is not authorised to make the demand. It
simply baldly denies that he is so authorised
and leaves it to Eskom
to prove his authority. But this, in my judgment, is inadequate; it
had to provide some basis for challenging
his authority.
[5]
Having failed to do so means that Mr Fisher’s averment in the
founding affidavit that he is authorised to make the demand
is
sufficient proof that he is so authorised. Absent a proper challenge
thereof, Eskom has complied with the first condition.
[13]
The demand states that the amount demanded is ‘the total
guaranteed sum’.
It goes further to state, ‘and confirm
that this is the demand amount, as defined in the said guarantee.’
A copy of
the Guarantee was annexed to the demand. On any reading of
the demand there can be no doubt that the demand was for the full sum
of the Guarantee. The full sum as stated in the Guarantee is
R20
339 243, 25. There is no ambiguity, uncertainty or doubt about this.
No reasonable reader having regard to the demand and the
Guarantee
could come to any conclusion other than that the full sum of
R20 339 243, 25 was demanded. Santam’s
contention that the demand fails to meet the second condition is
therefore without
merit.
[14]
The third condition concerns the circumstances under which the demand
is made. The Guarantee
requires that the demand must ‘state
that the Demand Amount is payable to Eskom in the circumstances
contemplated in the’
contract between Eskom and Jyoti. The
demand states that ‘this demand is made in circumstances as
contemplated in the contract
between the parties.’ Mr Mc Aslin
for Santam submitted that, as the wording in the demand is not a
verbatim copy of the wording
used in the Guarantee, the demand fails
to meet the third condition. I cannot agree. The demand says it is in
circumstances as
contemplated in the contract between the parties
whereas the Guarantee says it must state that it is made ‘in
the circumstances
contemplated in the Contract.’ The ‘Contract’
refers to no more than the contract between Eskom and Jyoti. There
is
no other contract. That is common cause. The wording in the demand
refers to ‘contract’ as opposed to ‘Contract’.
But this is of no moment. The demand makes clear that it is the
contract between the parties, and the first paragraph of the demand
explicitly informs that ‘Eskom Holdings SOC Limited and Jyoti
Structures Africa (Pty) Ltd entered into a contract for construction
of the Ariadne Eros Section A, 400 KV line. This contract was signed
by both parties 29 April 2016.’ So the additional phrase,
‘between the parties’ after the word ‘contract’
in the demand is merely a reference to the contract between
Eskom and
Jyoti, which is the same ‘Contract’ referred to in the
Guarantee. In both the Guarantee and the demand the
word is used as a
noun. And both refer to the same agreement between Eskom and Jyoti.
There is neither distinction nor difference
between the wording in
the demand and Guarantee. It follows that the third ground of
challenge must fail.
[15]
The demand, I hold, has fully and unequivocally complied with the
three conditions set
out in the Guarantee.
[16]
Mr Mc Aslin
for Santam submitted that our law has developed to the point that the
demand must comply strictly and not just substantially
with the terms
of the guarantee for it to be valid. There is no
dictum
to this effect in the authorities. Mr Mc Aslin says it can be derived
from how the court in
Delfs
[6]
dealt with the issue. In
Delfs
the court was required to determine whether an oral contract between
an agent – a shipping and forwarding agent to be exact
- and a
principal contained an implied term. The plaintiff (the agent) sued
for fees and disbursements. The defendant, (principal)
had sold
certain wild animals to another party in London (the purchaser), who
in turn had sold the animals to a person in Saudi
Arabia. As seller,
the defendant required a letter of credit from a bank before it would
give effect to the purchase and sale contract
between it and the
purchaser. On account of the purchaser, Barclays Bank in London
issued an irrevocable letter of credit. The
plaintiff as agent
arranged for the transportation of the animals - the ‘cargo’,
in transportation parlance. The documentation
relating to the cargo
did not match the actual cargo as some of the animals had died before
they were loaded onto the airplane.
The airline transporting the
animals refused to accept them until the documentation was amended to
reflect the actual amount and
correct description of the animals. The
documentation was accordingly amended ‘to reflect the true
position.’
[7]
The
amendment placed in peril the defendant’s duty to comply with
the terms of the letter of credit. What then occurred is
best
captured in the following paragraph from the judgment:
‘
The animals were
duly transported to Saudi Arabia and the letter of credit was
presented for payment. The bank refused to honour
it on various
grounds. It is unnecessary to refer to each. It relied,
inter
alia
,
on the discrepancies between the specification of the goods in it and
that appearing in the documents to which I have referred.
It was
common cause that the Bank was entitled to refuse to pay out in the
circumstances; that it was the sole responsibility of
the defendant
to obtain the letter of credit in a form acceptable to him; and that
the plaintiff was in no way responsible for
ensuring that the correct
number of animals were available for shipment.’
[8]
Upon being sued by the
plaintiff for fees and disbursements, the defendant pleaded that
there was an implied term to the contract
to the effect that the
plaintiff would ensure that the information on the waybill would
comply with the conditions set out in the
letter of credit so that
the letter of credit would be met by Barclays. The court, after
carefully examining the facts, ruled that
no such implied term was
proven by the defendant. As regards the issue of the right of
Barclays to refuse to honour the letter
of credit the court said no
more than that ‘[i]t was common cause that the bank was
entitled to refuse to pay out in the
circumstances and that it was
the sole responsibility of the defendant to obtain the letter of
credit in a form acceptable to him.’
The court said nothing to
the effect that there has to be strict compliance with the terms or
conditions set out in a letter of
credit, failing which the issuer is
entitled to refuse to honour it. Mr Mc Aslin’s submission that
– to quote from
his heads – ‘the case is
illustrative of the principle of strict compliance in our law,’
is plainly wrong. No
learning to this effect can be drawn from the
sentence in the paragraph quoted here. The court was not concerned
with the issue
of compliance with the terms of the letter of credit
and therefore did not shift the dial on the law regarding letters of
credit.
[17]
That said, there is no need for me to develop the law in this
regard. That must be
left for another day where the facts more
suitable for the consideration of this issue are available, and where
full submissions
on the issue are received. Here the facts are clear:
Eskom has complied with the terms of the Guarantee in every respect.
[18]
To conclude: Santam’s opposition to the application fails on
each of the three grounds
upon which it is based.
Costs
[19]
Both parties agreed that costs should follow the result. I see no
reason to adopt a different
view.
Order
[20]
The following order is made:
1.
The first respondent is to pay the applicant:
1.1
The sum of
R20 339 243, 25 (Twenty million
three hundred
thirty
nine thousand forty thee
rands
and twenty five cents).
1.2
Interest on
the
aforesaid amount from date of demand,
being 17 October 2019, to date
of
payment at the legally prescribed rate of
7 percent per annum.
2
. The first
respondent is to pay the costs of the application
________
Vally
J
Dates
of hearing: 20 July 2022
Date
of Judgment: 12 August 2022
Representation
For
the applicant: A Govender with N
Ndlovu
Instructed
by: Gildenhuys
Malatji Attorneys
For
the respondent: C J Mc Aslin SC
Instructed
by: Moll
Quibell and Associates
[1]
In this judgment a reference to one is a reference to all three
[2]
‘They are the life-blood of international commerce’
R
D Harbottle and another v National Westminster Bank Ltd and others
[1977] 2 All ER 862
(QB) at 870b
[3]
Id. See
Lombard
Insurance Co Ltd v Landmark Holdings (Pty) Ltd
2010 (2) SA 86
(SCA) at [20];
Loomcraft
Fabrics CC v Nedbank
[1995] ZASCA 127
;
1996 (1) SA 812
(A) at 815G-H;
OK
Bazzars (1929) Ltd v Standard Bank South Africa Ltd
2002 (3) SA 688
(SCA) at [25]
[4]
Edward
Owen Engineering Ltd v Barclays Bank International Ltd
[1978] 1 All ER 976
(CA) at 981e-984f, and the cases cited therein.
Coface
South African Insurance Co Ltd v East London Own Haven/ Own Haven
Housing Association
2014 (2) SA 382
(SCA) at [10] – [13]
[5]
Wightman
t/a JW Construction v Headfour (Pty) Ltd
[2008] ZASCA 6
;
2008 (3) SA 371
(SCA) at
[12]
- [13]
[6]
Delfs v
Kuehne & Nagel (Pty) Ltd
1990 (1) SA 822 (A)
[7]
[7]
Id at 826E
[8]
Id at 826G-H
sino noindex
make_database footer start
Similar Cases
Eskom Holdings SOC Limited v TSSA (Pty) Ltd and Others (038256/2022) [2023] ZAGPJHC 1469 (21 December 2023)
[2023] ZAGPJHC 1469High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Rotek Industries SOC Ltd v Geo-X (Pty) Ltd (2021/41489) [2023] ZAGPJHC 1140 (11 October 2023)
[2023] ZAGPJHC 1140High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holdings SOC Limited v Akgwevhu Enterprise (PTY) Ltd (4554921) [2022] ZAGPJHC 932 (22 November 2022)
[2022] ZAGPJHC 932High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holdings Soc LTD v Babcock Ntuthuko Engineering (Pty) Ltd (A2023/099598) [2024] ZAGPJHC 990 (3 October 2024)
[2024] ZAGPJHC 990High Court of South Africa (Gauteng Division, Johannesburg)100% similar
Eskom Holding SOC Limited Ltd v Sokweba and Others (101726/2024) [2024] ZAGPJHC 935 (18 September 2024)
[2024] ZAGPJHC 935High Court of South Africa (Gauteng Division, Johannesburg)100% similar