Case Law[2023] ZAGPPHC 759South Africa
Hamsa Consulting Engineers (Pty) Ltd v Sigodi Marah Martin Management Support (Pty) Ltd (32290/2020) [2023] ZAGPPHC 759 (29 August 2023)
Headnotes
Summary:
Judgment
begin wrapper
begin container
begin header
begin slogan-floater
end slogan-floater
- About SAFLII
About SAFLII
- Databases
Databases
- Search
Search
- Terms of Use
Terms of Use
- RSS Feeds
RSS Feeds
end header
begin main
begin center
# South Africa: North Gauteng High Court, Pretoria
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2023
>>
[2023] ZAGPPHC 759
|
Noteup
|
LawCite
sino index
## Hamsa Consulting Engineers (Pty) Ltd v Sigodi Marah Martin Management Support (Pty) Ltd (32290/2020) [2023] ZAGPPHC 759 (29 August 2023)
Hamsa Consulting Engineers (Pty) Ltd v Sigodi Marah Martin Management Support (Pty) Ltd (32290/2020) [2023] ZAGPPHC 759 (29 August 2023)
Download original files
PDF format
RTF format
make_database: source=/home/saflii//raw/ZAGPPHC/Data/2023_759.html
sino date 29 August 2023
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
DIVISION, PRETORIA)
Case
No. 32290/2020
(1)
REPORTABLE:
YES
/
NO
(2)
OF INTEREST TO OTHER JUDGES:
YES
/
NO
(3)
REVISED
NO
DATE:
29 August 2019
In
the matter between:
HAMSA
CONSULTING ENGINEERS (PTY) LTD
PLAINTIFF
And
SIGODI MARAH MARTIN
MANAGEMENT
SUPPORT (PTY) LTD
DEFENDANT
Coram:
Millar
J
Heard
on
:
1
st
& 2
nd
August 2023
Delivered:
29
August 2023 - This judgment was handed down electronically by
circulation to the parties' representatives by email,
by being
uploaded to the
CaseLines
system of the GD and
by release to SAFLII. The date and time for hand-down is deemed
to be 10H00 on 29 August
2023.
Summary:
Claim for payment
of balance of agreed price for engineering services rendered –
defence that scope of work insufficiently
set out in agreement
or pleaded - agreement negotiated between parties who
understood the scope of the work to be done
– conduct of
parties establishing that they were
ad idem
as to what
was to be done and what was to be paid for it.
ORDER
It
is Ordered
:
[1]
The defendant is ordered to pay the plaintiff the sum of
R4 118 756,52.
[2]
The defendant is ordered to pay to the plaintiff interest on the
sum of R4 118 756,52 a
tempore morae
at the rate
of 8,75% per annum.
[3]
The defendant is ordered to pay the costs of suit on the scale as
between party and party.
JUDGMENT
MILLAR
J
[1]
This is a case in which the plaintiff, a
firm of consulting engineers (HAMSA) sued the defendant (SMM), for
the outstanding balance
for services rendered. SMM was appointed as a
sub-contractor by LTE who was the successful tenderer for works to be
done for the
Kwa-Zulu Provincial Government. SMM had then, it was
asserted, sub contracted HAMSA to do certain of the works.
[2]
The circumstances under which SMM engaged
with HAMSA, the agreement between them and their respective
subsequent conduct provide
the backdrop against which this matter was
contested.
[3]
It was the case for HAMSA that a contract
had been concluded between it and SMM, it had performed and SMM had
partially performed
by making certain payments. SMM’s case was
that there was never any contract between the parties and for that
reason it was
under no obligation to HAMSA to pay it anything.
[4]
On 18 April 2019, Mr. Andrew Pillay who
represented SMM attended at the offices of HAMSA in Umhlanga, Durban.
There he met with
Mr. Vinodh Munessar for HAMSA, and they concluded
an agreement. I pause to mention at this juncture that I refer to
what was concluded
as an “agreement” because that is what
they cast it as. Whether it was in its terms a binding contract is
the crux
of the case to be decided.
[5]
The agreement was reduced to writing by SMM
and provided for the appointment of HAMSA as a sub-contractor to SMM.
The appointment
which was accepted in writing the same day provided
inter alia
that:
“
Sigodi
Marah Martin Management Support Development and Engineering
Consultants (SMMMS) has been appointed by the LTE CONSULTING
ENGINEERS to conduct a condition assessment of 10 KZN Districts Water
and Sanitation Infrastructure and 24 KZN Local Municipalities
Licensed Electrical Distributors Infrastructure.
As
part of the scope this project, we are pleased to inform you that
Hamsa Consulting Engineers (Pty) Ltd is hereby appointed for
the
provision of the above services as a sub-contractor to SMMMS based on
the agreed price of
R 8 500 000,00
(Incl. VAT) and inclusive
of disbursements for the condition assessment of electrical
infrastructure in 10 KZN District Municipalities
Water and Sanitation
Infrastructure and 24 Local Municipalities Licensed Electrical
Distributors Infrastructure. The municipalities
are highlighted below
……”
[6]
The agreement went on to list the 10 district municipalities at which
the electrical component of the water
and sanitation infrastructure
were to be condition assessed and also the electrical infrastructure
of the 24 local municipalities
which were licensed electrical
distributors. In total 34 separate locations were identified for
condition assessment.
[7]
The agreement concluded with the following:
“
Kindly
note that is as per agreement reached at your offices on 18
th
April
2019.
A sub-consultant
agreement will follow in due course.”
[8]
It was common cause that no “sub-consultant agreement”
was ever entered into.
[9]
It was the case for SMM that there was in fact no agreement. This was
premised on the contention that “condition
assessment”
had not been particularized in either the agreement or in the
pleadings.
[10]
The argument was that in the absence of a proper description of the
scope of the works to be undertaken by HAMSA, SMM
was not in a
position to know whether HAMSA had complied with the terms of the
agreement entitling it to claim payment and what
the terms for
effecting payment were. Furthermore, even if there was an agreement,
it was vague.
[11]
It was also argued that the agreement was a synallagmatic one –
it did not contain reciprocal obligations but was
in its terms a
bilateral agreement in which each simply undertook obligations to the
other.
[12]
SMM argued that the agreement was, properly construed, nothing more
than an agreement to agree and for that reason it
could not be
considered to be a binding agreement – there being no deadlock
breaking mechanism in the agreement. I was referred
to
Shepherd
Real Estate Investments (Pty) Ltd v Roux Le Roux Motors CC
[1]
,
Southernport
Developments (Pty) Ltd v Transnet Ltd
[2]
and
Makate
v Vodacom Ltd
[3]
as authority for this proposition.
[13]
SMM’s argument in this regard was predicated upon the last line
in the agreement in which it was stated “
a sub consultant
agreement will follow in due course
”. From this, the
inference to be drawn was that what had been agreed was not binding
and that the further sub consultant,
which was never concluded, would
have contained the further material terms which would have made the
agreement binding.
[14]
Having regard to the agreement as a whole, it seems that this clause
was not the proverbial “agreement to agree”
that SMM
contended for but rather a statement of intent on the part of SMM.
This intent never manifested and what is left is what
preceded the
statement of intent, which was in its express terms, the agreement
between the parties. On this basis, the authorities
to which I was
referred are distinguishable on the facts from this case.
[15]
In any event, it was the case for HAMSA that there was no ‘deadlock’
to be broken. The dispute concerned
the failure of SMM to honour a
part of the agreement by paying the outstanding balance of the agreed
price – after there
had already been full performance by HAMSA.
[16]
HAMSA called the evidence of two witnesses
– Mr. Vinodh Munessar (Mr. Munessar) and Mr. Sunil
Chundrikpersad (Mr. Chundrikpersad).
[17]
Mr. Munessar testified that he is an
electrical engineer and one of the directors of HAMSA. He has
worked as an engineer for
23 years, 21 of those with HAMSA. He
confirmed the agreement entered into between HAMSA and SMM and that
he had signed it
on behalf of HAMSA and that Mr. Andrew Pillay (Mr.
Pillay) had signed on behalf of SMM. He testified that he was
aware that
SMM had been sub-contracted by LTE to carry out electrical
infrastructure condition assessments. He confirmed that the
written
agreement had been negotiated by himself and Mr. Pillay.
He also testified that although the agreement reflected that a
sub-contract
agreement would follow in due course, no such agreement
had ever eventuated.
[18]
His evidence was that meetings had been
held between himself and Mr. Pillay at which what was required of
HAMSA had been discussed
as well as how HAMSA would execute the
work. All the work requested had been done save in respect of
one particular municipality
which was under administration and where
HAMSA had been prevented from carrying out any work.
Notwithstanding the quoted
price for all 34 condition assessments,
HAMSA was only seeking payment for the 33 that had actually been
done. In this regard,
the particular invoice for that
municipality incorrectly reflected a charge for the work having been
done and this was to be adjusted.
[19]
HAMSA was well aware of what the “condition
assessments” entailed and no other particularity was needed in
the agreement.
Mr. Munessar explained that since the parties
that had negotiated the agreement were engineers, what was entailed
was well understood
and was in fact what had been done by HAMSA. The
work had commenced, and invoices were submitted to SMM. Payments
were received
in July 2019 in the sum of R1 200 000,00.
Between July and December 2019, work had been held back because of
non-payment
but payments had subsequently been made in October and
November 2019.
[20]
The difficulty with receiving payments from
SMM had been raised with them and had resulted in a payment schedule
signed by Mr. Lansana
Marah, a director of SMM being sent to HAMSA on
27 September 2019. This was because there was no agreement that
HAMSA would
wait for payment of its invoices.
[21]
The
payment schedule resulted in further payments of R300 000.00 in
October 2019 and R1 million in November 2019. A further
payment of
R300 000.00 was made in January 2020. In April 2020, HAMSA
had instructed its attorneys to send a letter
in terms of section 345
of the Companies Act
[4]
to SMM and in response to this, a further payment of R1 million was
received. Throughout his dealings with SMM, they
had never
disputed that the work was done or that payment was due or for that
matter, the amount to be paid.
[22]
He
also testified that when the work had been completed, he had informed
both Mr. Pillay as well as LTE and that confirmation had
been
received from LTE that they were satisfied that the work had been
completed. All the relevant documents required by
LTE had been
sent to them electronically.
[5]
On this aspect his evidence was corroborated by Mr. Chundrikpersad.
[23]
His evidence was that of the R8.5 million
that had been quoted, taking into account the R3,8 million paid, the
outstanding balance
was R 4 345 834,51. Deducting the
adjustment for the municipality where they had been unable to do the
work in the amount
of R227 077,99 left an amount of
R4 118 756,52 for which judgment is sought.
[24]
It was put to Mr. Munessar in cross
examination that the agreement did not specify what the “
condition
assessments
” entailed and he
explained that it was an engineering term and that engineers knew
what it meant. He fairly conceded
that the agreement did not
specify when the works would be complete or how payment would be
made. Furthermore, he conceded
that the agreement did not refer
to interim payments or specify when HAMSA would in fact be entitled
to payment.
[25]
Mr. Chundrikpersad testified that he is the
payment coordinator employed at HAMSA. His evidence was that he
oversaw the payments
of all invoices and followed these up until the
project was completed. He has been with HAMSA for 13 years.
He attended
a number of prior meetings with SMM to discuss the
implementation plan of the agreement, prior to the signature of the
agreement.
[26]
He confirmed the evidence of Mr. Munessar
that an email had been sent to LTE confirming the completion of the
work and that all
the relevant documents had been sent
electronically. His evidence was that LTE had acknowledged that
the work was completed.
[27]
Mr.
Munessar’s evidence was not disturbed in cross examination and
Mr. Chundrikpersad was not crossed examined.
[6]
Both their evidence stands unchallenged. Both were in my
view impressive witnesses who testified in a forthright manner
and
Mr. Munessar in particular made concessions in favour of SMM when
there was no reason for him to do so. It bears, in my view,
testament
to, in particular his truthfulness and I have no hesitation in
accepting his evidence.
[28]
SMM chose to confine its engagement in the
case to “within the four corners of the pleaded case”.
For this reason,
neither Mr. Munessar nor Mr. Chundrikpersad were
cross examined on anything outside these parameters. In the
circumstances,
SMM failed to engage at all with the evidence of Mr.
Munessar that the parties knew and understood what was required for
purposes
of what was required for the “condition assessments.”
[29]
SMM,
in adopting this course of action, relied upon
Minister
of Safety and Security v Slabbert
[7]
in which it was held:
“
[11]
The purpose of the pleadings is to define the issues for the other
party and
the court. A party has a duty to allege in the
pleadings the material facts upon which it relies. It is
impermissible
for a plaintiff to plead a particular case and to seek
to establish a different case at the trial. It is equally not
permissible
for the trial court to have recourse to issues falling
outside the pleadings when deciding a case.”
[12] There are,
however, circumstances in which a party may be allowed to rely on an
issue which was not covered by the pleadings.
This occurs where
the issue in question has been canvassed fully by both sides at the
trial. In South British Insurance Co Ltd
v Unicorn Shipping Lines
(Pty) Ltd, this court said:
“
However,
the absence of such an averment in the pleadings would not
necessarily be fatal if the point was fully canvassed in evidence.
This means fully canvassed by both sides in the sense that the Court
was expected to pronounce upon it as an issue.”
[30]
Counsel for SMM placed on record on more
than one occasion, the reason for failing to cross examine was so as
to ensure that it
could not be argued that the issue of what was
meant by “condition assessments” had been canvassed at
the trial.
[31]
The evidence led on behalf of HAMSA was
consistent with the agreement and the documents referred to by them
in evidence relating
to the engagements between HAMSA and SMM
subsequent to 18 April 2019. SMM called no witnesses and closed its
case. Accordingly,
the evidence of the witnesses for HAMSA stands
uncontradicted.
[32]
What is not in issue between the parties is
that the agreement was signed on 19 April 2019, that HAMSA invoiced
SMM for work done
and that SMM made payments to HAMSA in the sum of
R3.8 million. Furthermore, over the 12-month period between the
signature
of the agreement and the last payment in the sum of R1
million, there is nothing before the court to indicate that the fact
that
HAMSA had done the work or that SMM was liable to HAMSA was ever
placed in issue, before the amendment of SMM’s plea and the
trial – long after HAMSA’s performance had been
complete. The evidence led at the trial which corroborated the
documents that had been exchanged between the parties established
that the work that HAMSA had been contracted to complete had
been
completed to the satisfaction of LTE.
[33]
HAMSA characterized the defences raised,
which are somewhat technical in nature as indicative of SMM “not
wanting to fully
pay for services completely rendered.”
[34]
In
ABSA
Bank v Swanepoel N.O.
[8]
,
it was held that:
“
[6]
At its simplest, a contract is an enforceable promise to do or not to
do something. But when parties record an agreement
in writing,
they often add provisions that do not embody such promises. A
contract may have a preamble. It may contain
‘recordals’
and ‘recitals’. It may document prior events, or
record the parties future intentions.
It may contain
clarificatory or explanatory statements. The parties may place
on record matters that bear on the interpretation
of what they have
undertaken. It is therefore wrong to approach a written
contract as though every provision is intended
to create contractual
obligations. ”
And
“
[7]
. . . but the question whether a contractual provision has
operational content is fundamental to the ambit of the obligations
the parties undertake, and it precedes the application of rules
designed to establish the proper interpretation of their
undertakings.
Only once it is determined that a provision was
intended to have contractual effect will the Court try to interpret
it so as to
give it business efficacy. If it was not so
intended, those rules of interpretation do not come into play.
No ‘business
meaning’ can be conjured out of a clause
that was not intended to have contractual effect at all.”
[35]
In
BK
Tooling (Edms) Bpk v Scope Precision Engineering (Edms) Bpk
[9]
it was held:
“
It
would be useful for a few aspects of the principle of reciprocity and
its application by means of the exceptio non adimpleti
contractus to
be mentioned:
1.
In contracts wherein reciprocal
obligations are created it is basically a matter of interpretation
whether the obligations are so
closely linked that the principle of
reciprocity applies. If, however, no other intention appears,
the principle applies
by operation of law to certain well known
contracts, such as, eg, the contract of sale and
locatio
conductio operis
.
2.
The sequence of performance and
counter-performance also depends upon the contractual provisions.
If, however, another intention
does not appear, the contractor, in
locatio conductio operis for example, must first perform.” (my
underlining)
[36]
In
the present matter, the terms of the agreement properly construed
constitute a
locatio
conductio operis
[10]
.
The conduct of the parties makes plain that the parties understood
that the agreement was not synallagmatic but was in fact
one which
created reciprocal obligations between the parties – HAMSA
would render services to the client of SMM, LTE, and
SMM would pay
HAMSA for those services.
[37]
In
Comwezi
Security Services (Pty) Ltd and Another v Cape Empowerment Trust
Ltd
[11]
it
was held:
“
In
the past, where there was perceived ambiguity in a contract, the
courts held that the subsequent conduct of the parties in
implementing
their agreement was a factor that could be taken into
account in preferring one interpretation to another. Now that
regard
is had to all relevant context, irrespective of whether there
is a perceived ambiguity, there is no reason not to look at the
conduct
of the parties in implementing the agreement. Where it
is clear that they have both taken the same approach to its
implementation,
and hence the meaning of the prevision in dispute,
their conduct provides clear evidence of how reasonable business
people situated
as they were and knowing what they knew, would
construe the disputed provision. It is therefore relevant to an
objective
determination of the meaning of the words they have sued
and the selection of the appropriate meaning from among those
postulated
by the parties.”
[38]
“
Businessmen
often record the most important agreements in crude and summary
fashion; modes of expression sufficient and clear to
them in the
course of their business may appear to those unfamiliar with the
business far from complete or precise. It is
accordingly the
duty of the Court to construe such documents fairly and broadly,
without being too astute or subtle in finding
defects.”
[12]
[39]
In
the present matter, I find that the agreement signed between the
parties on 18 April 2019 was a binding agreement with reciprocal
obligations. Insofar as SMM argued that the agreement was void
for vagueness, I was referred to
Levenstein
v Levenstein
[13]
in
which the court set out the four situations in which contracts could
be so classified. The first and fourth are not relevant
to the
present matter. It was argued that the second “
where
the vague and uncertain language justifies the implication that the
parties were never ad idem”
and
the third “
where
there is no concluded contract as in the case of ‘continuing
negotiations’ broken off in medio”
should find application in this matter.
[40]
The evidence establishes that the language
used in the agreement was clear and unequivocal as between the
parties. The completion
of the work by HAMSA and the partial
payment as and when it was called for by SMM lead to the ineluctable
inference, as a matter
of common sense, that the parties knew what
they had contracted for. It follows that they were
ad
idem
. I have already dealt with
the issue of sub consultant agreement – it too is of no moment
in the present matter for
the reasons that I have stated.
[41]
The only point of dispute is that SMM
failed to make full payment of what was agreed.
[42]
For the reasons that I have set out above,
I find that SMM is liable to HAMSA for the balance due to it under
the agreement.
[43]
In regard to costs, it was argued on behalf
of HAMSA that a punitive order for costs should be made. This
was predicated on
what was argued as being dilatory conduct on the
part of SMM insofar as having the matter brought before the court for
hearing
was concerned. On consideration of the matter of a
whole, I am not persuaded that a punitive order for costs is
appropriate.
In the circumstances I intend to make the costs
order that I do.
[44]
In the circumstances, I make the following
order:
[44.1] The
defendant is ordered to pay the plaintiff the sum of R4 118 757,02.
[44.2] The
defendant is ordered to pay to the plaintiff interest on the sum of
R4 118 757,02 a
tempore morae
at the rate of 8,75%
per annum.
[44.3] The
defendant is ordered to pay the costs of suit on the scale as between
party and party.
A
MILLAR
JUDGE
OF THE HIGH COURT
GAUTENG
DIVISION, PRETORIA
HEARD
ON:
1
ST
& 2
ND
AUGUST 2023
JUDGMENT
DELIVERED ON: 29
AUGUST 2023
COUNSEL
FOR THE PLAINTIFF: ADV. M Z
SULEMAN
INSTRUCTED
BY: LARSON
FALCONER HASSAN PARSEE INC
REFERENCE: 22/H361/036
COUNSEL
FOR THE DEFENDANT: ADV. A B ROSSOUW SC
INSTRUCTED
BY: CARI
DU TOIT INC ATTORNEYS
REFERENCE:
C DU TOIT/SIG1/0064
[1]
2020
(2) SA 419
(SCA) at para [1] – the clause in issue in this
matter provided “
that
the rental and costs shall be mutually agreed
”.
No such provision was agreed in the present matter.
[2]
2005
(2) SA 202
(SCA) at para [17] where it was held “
For
what elevates this agreement to a legally enforceable one and
distinguishes it from an agreement to agree is the dispute
resolution mechanism to which the parties have bound themselves
.”
No such provision was agreed in the present matter.
[3]
2016
(4) SA 121
(CC) at para [97]. Distinguishable from the present case
as there the agreement was to negotiate in good faith. In the
present
case the agreement had been reached and reduced to writing.
[4]
61
of 1973.
[5]
The
documents were too large to send by email, so they had been sent by
WE-Transfer which had then generated a download receipt
for HAMSA
once they had been downloaded by LTE.
[6]
President
of the Republic of South Africa and Others v South African Rugby
Football Union and Others
2000
(1) SA 1
(CC) at para [61].
[7]
2009
JDR 1218 (SCA) at paras [11] – [12].
[8]
2004
(6) SA 178
(SCA) at paras [6] & [7].
[9]
1979
(1) SA 391
(A) at the headnote.
[10]
A
contract where services are rendered in exchange for remuneration.
[11]
2012
JDR 1734 (SCA) at para [15]. See also
Capitec
Bank Holdings Ltd and Another v Coral Lagoon Investments 194 (Pty)
Ltd and Others
2022
(1) SA 100
(SCA) at para [46] and in particular “
words
without context mean nothing, and context is everything. It
has given a wide remit to the admission of extrinsic evidence
as to
context and purpose so as to interpret the meaning of a contract.”
[12]
Hillas
& Co Ltd v Arcos Ltd
[1932] UKHL 2
;
(1932) 147 LT 503
(HL) at 514. See also
Natal
Joint Municipal Pension Fund v Endumeni Municipality
2012 (4) SA 593
(SCA) – “
Whatever
the nature of the document, consideration must be given to the
language used in the light of the ordinary rules of grammar
and
syntax; the context in which the provision appears; the apparent
purpose to which it is directed;
and
the material known to those responsible for its production.”
(my
underlining).
[13]
1955
(3) SA 615
(SR) at 619.
sino noindex
make_database footer start
Similar Cases
Hamsa Consulting Engineers (Pty) Ltd v Sigodi Marah Martin Management Support (Pty) Ltd (32290/2020) [2023] ZAGPPHC 1187 (22 September 2023)
[2023] ZAGPPHC 1187High Court of South Africa (Gauteng Division, Pretoria)100% similar
LSO Consulting Engineers (Pty) Ltd and Another v Ndyamara and Others (56620/2021) [2022] ZAGPPHC 168 (23 March 2022)
[2022] ZAGPPHC 168High Court of South Africa (Gauteng Division, Pretoria)98% similar
Proserve Consulting (Pty) Ltd v RMV Engineering Projects (Pty) Ltd (A95/2022) [2024] ZAGPPHC 9 (15 January 2024)
[2024] ZAGPPHC 9High Court of South Africa (Gauteng Division, Pretoria)98% similar
Sezigen Consulting Engineers And Project Managers (Pty) Ltd v Mpati N.O and Others (25428/22) [2024] ZAGPPHC 193 (9 February 2024)
[2024] ZAGPPHC 193High Court of South Africa (Gauteng Division, Pretoria)98% similar
Kgoano Consulting and Projects Management CC and Another v Business Partners Limited (30127/2021) [2024] ZAGPPHC 319 (4 April 2024)
[2024] ZAGPPHC 319High Court of South Africa (Gauteng Division, Pretoria)98% similar